Jameson L.

Agudelo, MAPA-1
PAD 229, Public Administration and The Economy

Community Development Plan

Project Title:
Brgy. Tapao-Tigue Hi-Way Clean-up Drive & Beautification
Program

Target Community or Beneficiaries:


Brgy Tapao-Tigue, Currimao

Partner Organizations:
Balikbayan Association of Currimao, Currimao Riders Club, &
Brgy. Officials

Community Background:
With a rising number of tourists visiting the municipality of Currimao.
Tapao-Tigue being the first barangay to welcome visitors coming from the
north at Paoay area, it is only fitting and proper to keep the community clean
especially the roadside to give the visitors a good impression and pay a visit
again in the near future.
Though road constructions & repairs have been conducted in the past,
and at present, the installation of street lights, it is noticeable that along the
roadsides are some clutters, dump of sands, growing weeds, and the absence
of trash bins.
This project intends to address these issues thru clean-up drive and
beautification. Recovered PET bottles and the likes from the activity and
collected at the Materials Recovery Facility (MRF) will be recycled into some
creative designs that can be displayed to add to the visual enticement while
traversing across the vicinity of Brgy. Tapao-Tigue.
Steel drums are also intended to be placed at strategic areas along the
roadsides to serve as trash bins. They are also to be painted with vibrant colors
to complement with the clean-up drive.

General Objectives:
The initiative of this plan is not only to lift the image of the community
but hoping to help promote further tourism industry in the locality. Thru this,
participants will be able to recognize the benefit of the project. They are
expected to explain to anyone who would ask the importance of what they
have been into. By demonstrating their tasks well, it is truly understood that
they want to establish not only to themselves but to commit to the group and
to the goal. With all of this, they will have the ingenuity to develop ideas
which could lead to new plans and inspire other non-governmental
organizations to emulate this move.
Specific Objectives:
Establish safe, clean and viable attractive roadways, to enhance and
promote participation among Brgy. officials and constituents. This activity
aims to impart for those involved that keeping cleanliness can have a reward
not by monetary nor in any material way but by self-fulfillment. Organizers
seeks to finish the project within the given time frame.

Community Development Plan Matrix:


(Please note that this proposed project will be implemented after installation of the street lights)

Activities Time Output Resources/ Cost


Frame Materials
Preparation:

Ocular visit at the 2 hrs. Finalization of the Vehicle Fuel- 500


site subject for the location stretch or
plan. boundaries of the
project.

Taking photos of the


target site for
documentation
Meeting with the 3 hours Project approval by Sound System Snacks- 500
Brgy. Officials, the Brgy. Council for the meeting
constituents, and and stakeholders. (Sound system
other stakeholders owned by the
for the planning Preparation and barangay)
and approval of acquisition of the
the project. G.I. Wires-
materials needed.
500

Paints &
brush- 1000
Drafting of 1 hour Solicitation letter Steel drums Steel drums-
solicitation letter was submitted to the 1500 (if
for the possible author’s employer solicitation
requisition or (OEMSERV Phils. don’t
donation of 5 steel Inc.) for the succeed)
drums. requisition or
donation of 5 steel
drums
Activities Time Output Resources/ Cost
Frame Materials
Actual Activities:

Deployment of
activity 2 days Finished cleaning up Brush cutters Gas- 1000
participants to the the area (Brush cutter
location for owned by the
cleaning, removal barangay) Snacks- 1,500
of weeds, and
clearing of any Machetes,
obstruction within brooms, &
the site. other cleaning
materials
(Cleaning
materials
owned by the
participants.

Assembling of the Finished positioning


recovered PET 2 days the assembled crafts G.I. Wires Vehicle is the
bottles into some to their respective service of the
creative designs designations Bamboo barangay
while other
participants gather
bamboo to be used
as post/pole and
placing them in
their respective
areas

Cutting the steel 1 day Positioning the Acetylene Acetylene &


drums into 10 finished steel drums Welding
halves, and in their designated Welding outsource-
painting places. Making sure Machine 1000
they don’t cause any
impediment along Vehicle Vehicle is the
the road to prevent service of the
any accident. barangay
Activities Time Output Resources/ Cost
Frame Materials

Post-
implementation
Activities:

Taking photos of 2 hrs. Comparing photos Cellphones,


the finished before and after the Cameras
project for project.
documentation

Distribution of Finalization of Certificates Print-outs


Certificate of 3 hrs. reports & 1,000
Participation for documentation to be
those involved in held at the Brgy.
the project Hall

Awarding of
Certificate of
Appreciation to
the partner
organizations for
their support and
involvement in the
concluded
program

Maintenance & After For the project to Brgy. Officials If needed


continuous implement serve its purpose for
monitoring of the ation the longest time
finished project possible.
from deterioration
and to avoid being
vandalized.

Total 7 days P 8,500