SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - JUNE 2008) REV 3 30-Jun-08

SATR NUMBER DATE APPROVED QR NUMBER


SAUDI ARAMCO TEST REPORT
Overhead T&D - Circuit Polarity, Continuity and Insulation
SATR-P-3219 1-Dec-09 ELECT
Resistance Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED TEST DATE & TIME ACTUAL TEST DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
TEST PROCEDURE ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

A. INSULATION RESISTANCE (MEGGER) TEST PROCEDURES

SAES-P-104
A1 Erect safety barriers and post safety man at conductor remote end.
Sec. 4.1

Check the overhead conductors connections & identification as per SAES-P-104


A2
specification and drawings. Sec. 4.1

SAES-P-104
A3 Insulate overhead conductors from ground.
Sec. 4.1

Measure the insulation resistance of overhead conductor using a megger


tester. The test voltage should be 5000 volts for rated 5000 volts and
above overhead conductors. Connect megohmmeter between each SAES-P-104
A4
phase-to-phase and each phase-to-ground. Record the insulation Sec. 4.1
resistance of each overhead conductor between phase to phase and
phase to ground for one (1) minute.

On completion of insulation resistance test, each overhead conductor SAES-P-104


A5
shall be grounded to allow residual charge to dissipate. Sec. 4.1

Check the conductor connections & phases identification and color coded SAES-P-104
A6
as per specification and drawings. Sec. 4.1

Check conductor bends to ensure the bending radius is equal to or SAES-P-104


A7
greater than the minimum bending radius specified. Sec. 4.1

SAES-P-104
A8 Check for proper conductor support, clamping and blocking.
Sec. 4.1

SAES-P-104
A9 Insulate associated feeder cable cores from ground.
Sec. 4.1

Measure the insulation resistance of feeder cables using a megger


tester, for each core and any metallic armor or sheath grounded at one
end only. Measure insulation resistance at one minute following the SAES-P-104
A10
application of the test voltage. The test voltage should be 5000 volts for Sec. 4.1
5000 volt and above cables. Record the insulation resistance of each
core between phase to phase and phase to ground for one (1) minute.

Record the megohm values of each phase-to-ground and between each


SAES-P-104
A11 phase-to-phase, along with the description of the equipment, the voltage
Sec. 4.1
level, humidity, temperature, time, and the date of the test.

On completion of insulation resistance test, the cable shall be grounded SAES-P-104


A12
to allow residual charge to dissipate. Sec. 4.1

Perform a physical inspection of the overhead feeders to ensure there is


SAES-P-104
A13 not any damage to the poles, conductors at termination points, insulators,
Sec. 4.1
jumpers, cable supports, stays etc. prior to energization.

Page 1 of 7
SAES-P-104
A14 Check tightness of all bolted connections (Torque Wrench Method).
Sec. 4.1

Page 2 of 7
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - JUNE 2008) REV 3 30-Jun-08
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Overhead T&D - Circuit Polarity, Continuity and Insulation
SATR-P-3219 1-Dec-09 ELECT
Resistance Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

Check that the cable test results are recorded in the Saudi Aramco Pre- SAES-P-104
A15
Commissioning Forms. Sec. 13.5 (a)

B. TEST EQUIPMENT

Test shall be performed using an Insulation Resistance Test Set SAES-P-104


B1
(Megohmeter) 5000 V dc minimum. Sec. 13.5 (a)

Schedule Q
B2 The test equipment calibration cycle shall not exceed twelve months. Att. IV
Sec. 7

Test Equipment Manufacturer: Serial Number:

Scale Range and accuracy: Calibration date:

Calibration Company and Technician: Calibration Expiration Date:

C. TEST RESULTS

Test Voltage level__________ Humidity____________ Temperature_______________ Time/Date of Test____________

MEASURED INSULATION RESISTANCE (MΩ)


Temp.
Adjusted
Condu
Insulation Pass Fail Re-Test date
ctor # A-G B-G C- G A-B B-C C-A
Resistance
(MΩ)

D. CONCLUSIONS

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

Compare test results with previous test results and with manufacturer
SAES-P-104
D1 data corrected for temperature variations using manufacturer
Sec. 3.2
recommended correction factors.

Consult conductor manufacturer's published data for acceptable test


results. If published data is not available, investigate any values which SAES-P-104
D2
deviate from previous test results under similar conditions by more than Sec. 3.2
50% of the lowest value.

Test results are acceptable and in accordance with Saudi Aramco


D3 N/A
Engineering Standards and contractual requirements.

E. TEST PROCEDURE FOR CONTINUITY TEST

Using a four-point, low-resistance ohmmeter, connect both C1 and P1 of SAES-P-104


E1
the test set to one end of the conductor. Sec. 3.2

SAES-P-104
E2 Connect C1 and P1 of the test set to one end of the conductor.
Sec. 3.2

Page 3 of 7
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - JUNE 2008) REV 3 30-Jun-08
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Overhead T&D - Circuit Polarity, Continuity and Insulation
SATR-P-3219 1-Dec-09 ELECT
Resistance Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

Connect the C2 and P2 of the test set to the other end of the conductor.
NOTE: Observe the correct orientation for the current circuit (C2) and the SAES-P-104
E3
potential circuit (P2) hook-ups at the opposite end (P2 connection closer Sec. 3.2
to the specimen than C2).

SAES-P-104
E4 Record result.
Sec. 3.2

F. TEST EQUIPMENT AND MATERIALS CRITERIA

SAES-P-104
F1 Test shall be performed using a Ductor, DLRO.
Sec. 3.2

Schedule Q
F2 The test equipment calibration cycle shall not exceed twelve months. Att. IV
Sec. 7

Test Equipment Manufacturer: Serial Number:

Scale Range and accuracy: Calibration date:

Calibration Company and Technician: Calibration Expiration Date:

G. TEST RESULTS

Conductor # Cable type Cable length Resistance (Ω) Pass Fail Re-Test Date

H. CONCLUSIONS

Investigate any breaks in continuity, along with any resistance values in SAES-P-104
H1
excess of 10 ohms per 1000 feet of cable. Sec. 3.2

Test results are acceptable and in accordance with Saudi Aramco


H2 N/A
Engineering Standards and contractual requirements.

REMARKS:

REFERENCE DOCUMENTS:
1. Schedule G -- Material, Tools and Equipment (Pro Forma MP-IK-LS Contract)
2. Schedule Q -- Quality Requirements (Pro Forma Contract), February, 2008
3. SAES-P-100 Basic Power System Design Criteria, 25 June 2007
4. SAES-P-104 -- Wiring Methods and Materials, 13 January 2008
5. S A Pre-Commissioning Form # P-000 Testing Guide Lines, Issue Date (10/97)

Page 4 of 7
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - JUNE 2008) REV 3 30-Jun-08
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Overhead T&D - Circuit Polarity, Continuity and Insulation
SATR-P-3219 1-Dec-09 ELECT
Resistance Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

6. S A Pre-Commissioning Form # P-004 Medium Voltage Cables, Issue Date (10/97)


7. Acceptance Testing Specifications for Electric Power Distribution Equipment and Systems- NETA (1999)
ATTACHMENT DOCUMENT:
Phasing & Insulation Resistance Test Forms

NOTES:
1. Approved - Acceptable to the authority having jurisdiction (i.e., Saudi Aramco ID).
2. Identified - Recognizable as suitable for the specific application by a qualified testing laboratory (i.e., listing and/or labeling).
3. Listed - Equipment and materials included in a list published by an approved qualified organization concerned with evaluation of products
or services, that maintains periodic inspection of production of listed equipment or materials or periodic evaluation of services, and whose listing
states
that the equipment, material, or services either meets appropriate designated standards or has been tested and found suitable for a specified
purpose.
4. Labeled - Equipment or materials to which has been attached a label, symbol, or other identifying mark of an approved qualified organization
concerned
with product evaluation, that maintains periodic inspection of production of labeled equipment or materials, and by whose labeling the manufacturer
indicates compliance with appropriate standards or performance in a specified manner.

Contractor / Third-Party Saudi Aramco


Technician Performing Test* PMT Representative
Name, Title, Department, Test Performed Successfully and Results are Acceptable: T&I Witnessed QC Record Reviewed Work Verified
Company, Initials and Name, Initials and Date:
Date:
QC Inspector PID Representative
Witnessed Test Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Implementation of Test and Analysis of Results Y = YES N = NO F = FAILED

Page 5 of 7
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - JUNE 2008) REV 3 30-Jun-08
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Overhead T&D - Circuit Polarity, Continuity and Insulation
SATR-P-3219 1-Dec-09 ELECT
Resistance Testing
Attachment 1 --

Page 6 of 7
Page 7 of 7