JUNG WOO
0 12.FEB.2019 C.W.Hyun J. C. PARK FOR APPROVAL
KIM
Supplier
UAS Code
JUNG WOO
Prepared
KIM
DD09
Unit Code
Checked C.W.Hyun
METHOD STATEMENT
P0
FOR
KKS Code
Approved J. C. PARK ALUMINIUM FRAME WORK
UMA
Reg. No.
Department Architecture DEPT.
780010
Revision History
INDEX
ARTICLE DESCRIPTION
1.0 PURPOSE
2.0 MATERIAL
5.0 MANPOWER
7.0 SAFETY
1.0 Purpose
To Define the Work Methodology to be adopted for Carrying out fixing of
Aluminum door and window frame at the Project.
2.0 Material
Approved material will be use for the said work.
3.0 Tools & Tackles
Cutting machine,
Drilling machine,
Spirit level,
Measurement tape (metallic of 3m/5m)
Chisel.
4.0 REFERANCE DRAWINGS
Project Contract Agreement Technical specification
Approved Drawing
5.0 Man Power
Adequate Skilled manpower shall be arranged for every activity.
6.0 Activity Description
1-The make and the section of the aluminum sections shall be approved by
client / consultant from preferred manufacturers.
2-Shop drawings for fabrication of shall be submitted for approval to
client/consultant and approved shop drawings shall be used for fabrication.
3-The door / window sections shall be fabricated and assembled as per