FOR APPROVAL

JUNG WOO
0 12.FEB.2019 C.W.Hyun J. C. PARK FOR APPROVAL
KIM

Rev Date Prepared Checked Approved Details of Revision

Owner JAWAHARPUR VIDYUT UTPADAN NIGAM LIMITED


(A UP Government Undertaking)

Owner’s Engineer DESEIN PRIVATE LIMITED,


Consulting Engineers

Contractor DOOSAN POWER SYSTEMS


INDIA PVT. LTD
METHOD STATEMENT
FOR ALUMINIUM FRAME WORK
DP16003-CC02-P0-UMA-780010

Supplier

Project JAWAHARPUR SUPER THERMAL POWER STATION


(2 X 660 MW)

Date Project Code


Name Title
(16.01.2019) DP16003

UAS Code
JUNG WOO
Prepared
KIM
DD09

Unit Code
Checked C.W.Hyun
METHOD STATEMENT
P0
FOR
KKS Code
Approved J. C. PARK ALUMINIUM FRAME WORK
UMA

Reg. No.
Department Architecture DEPT.
780010

Owner’s Consultant Document No. Rev.

Contractor’s Document No. Page-No.

DP16003 – DD09 - P0 - UMA – 780010 1 of 7

Supplier’s Document No.

JAWAHARPUR THERMAL POWER STATION (2x660 MW) Rev. 0


Page 2 of 7
METHOD STATEMENT
FOR ALUMINIUM FRAME WORK
DP16003-CC02-P0-UMA-780010

Revision History

0 12.FEB.2019 J.W.Kim C.W.Hyun J.C. PARK FOR APPROVAL

Rev Date Prepared Checked Approved Details of Revision

JAWAHARPUR THERMAL POWER STATION (2x660 MW) Rev. 0


Page 3 of 7
METHOD STATEMENT
FOR ALUMINIUM FRAME WORK
DP16003-CC02-P0-UMA-780010

INDEX

ARTICLE DESCRIPTION

COVER PAGE INDEX

1.0 PURPOSE

2.0 MATERIAL

3.0 TOOLS AND TACKLES

4.0 REFERANCE DRAWINGS

5.0 MANPOWER

6.0 ACTIVITY DESCRIPTION

7.0 SAFETY

JAWAHARPUR THERMAL POWER STATION (2x660 MW) Rev. 0


Page 4 of 7
METHOD STATEMENT
FOR ALUMINIUM FRAME WORK
DP16003-CC02-P0-UMA-780010

METHOD STATEMENT FOR ALUMINIUM FRAME WORK

1.0 Purpose
To Define the Work Methodology to be adopted for Carrying out fixing of
Aluminum door and window frame at the Project.
2.0 Material
Approved material will be use for the said work.
3.0 Tools & Tackles
Cutting machine,
Drilling machine,
Spirit level,
Measurement tape (metallic of 3m/5m)
Chisel.
4.0 REFERANCE DRAWINGS
Project Contract Agreement Technical specification
Approved Drawing
5.0 Man Power
Adequate Skilled manpower shall be arranged for every activity.
6.0 Activity Description
1-The make and the section of the aluminum sections shall be approved by
client / consultant from preferred manufacturers.
2-Shop drawings for fabrication of shall be submitted for approval to
client/consultant and approved shop drawings shall be used for fabrication.
3-The door / window sections shall be fabricated and assembled as per

JAWAHARPUR THERMAL POWER STATION (2x660 MW) Rev. 0


Page 5 of 7
METHOD STATEMENT
FOR ALUMINIUM FRAME WORK
DP16003-CC02-P0-UMA-780010

approved shop drawings.


4-Make sure there is a lintel above any window before you fix it, as aluminum
windows are not designed to be load bearing.
5- Check size and style of window matches your order.
6- All sections, including that of frames shall be perfectly straight, without any
bends, twists etc.
7- Check application of lime wash around window.
8- Clean site around window, including removal of ornaments and curtains etc.
9-Window installation shall be done before starting of paint. The site should be
clear of unnecessary material like cement, scaffolding to avoid damage to the
windows.
10-If fitting a sill, position on to the brickwork, ensuring the up stand fits against
the plaster line of the jambs. If necessary, trim the horns (part of exterior sill that
extends past width of window, ideally by 12mm at each end).
11-Use the plastic packers to level the sill with around 5mm clearance between it
and the block work.
12- Door/Windows are fixed in each aperture with anchor fasteners.
13- Fixing of window/ventilator frames shall be done in place according to the
specified drawings using stainless steel screws.
14- Use a spirit level to ensure the window is vertical and up against the plaster
line, if appropriate.
15- Use silicone seal along the back edge of the sill up stand.
16- Gaps between the masonry and the frame are filled with high grade silicone
and Neutral Cure Silicon.
17- Push sealant forward, rather than pulling back to ensure it pushes into any
gaps.

JAWAHARPUR THERMAL POWER STATION (2x660 MW) Rev. 0


Page 6 of 7
METHOD STATEMENT
FOR ALUMINIUM FRAME WORK
DP16003-CC02-P0-UMA-780010

18- Glazing shall be done with approved make of glass.


19- EPDM gasket shall be provided around the glass.
20- Before positioning the glass, insert glazing bridges in the frame recess.
21- Fit the top glazing bead first, followed by the bottom and then the sides.
22- Inside, place a bead of silicone between plaster and door/window.
23- Leave doo/window for a couple of hours before opening, allowing seals to set.
24-Ensure that door/window opening is smooth and check for lock & key.
7.0 Safety Measures
1. Safety helmets, shoes, belts and gloves will be provided for worker and helpers.
2. Area lighting will be provided for night work. Good housekeeping will be
ensured.
3. Safety Supervisor shall ensure that Safety Precautions are taken and Safe
Work Environ mentis maintained

JAWAHARPUR THERMAL POWER STATION (2x660 MW) Rev. 0


Page 7 of 7