17/07/18: -
S. No ACTIVITY Action BY Time Remark
2 Valve XV-014 of Burner No-1 checking. Worley 09:00 am Solenoid of valve checked
Parson/williams
3 Burner No-4 valve PCV-041 checking done. Worley 09:30 am Diaphragm checked, needs
Parson/williams to be changed.
5 Checking the solenoid V1 and V2 of the pilot burner William 09:50 am Wiring was not done
No-1 properly and got
interchanged. Wiring
interchanged for both the
solenoids.
6 Air fan for burner No-1 started and tried to ignite Ctrl Room 10:15 am Got failed.
7 Air fan for burner No-1 again started Ctrl Room 10:20 am Started firing after
rectification of solenoid
loose connection of the
pilot burner.
8 Burner No-1 flame adjustment William/Ctrl Room 10:25 am Air fan damper valve was
opened fully and closed,
adjustment done and
flame was set on a
particular opening.
13 Burner No-4 flame adjustment William/Ctrl Room 12:05 pm Air fan damper valve was
opened fully and closed,
adjustment done and
flame was set on a
particular opening.
14 All the burners stopped. Ctrl Room 12:15 pm For sequence testing of
bag house and
concentrate conveying
system to feed bins.