DRYER COMMISSIONING ACTIVITIES ON

17/07/18: -
S. No ACTIVITY Action BY Time Remark

1 Ribbon and incline screw conveyors started Ctrl room 08:00 am

2 Valve XV-014 of Burner No-1 checking. Worley 09:00 am Solenoid of valve checked
Parson/williams

3 Burner No-4 valve PCV-041 checking done. Worley 09:30 am Diaphragm checked, needs
Parson/williams to be changed.

4 Dryer started Ctrl Room 09:45 am

5 Checking the solenoid V1 and V2 of the pilot burner William 09:50 am Wiring was not done
No-1 properly and got
interchanged. Wiring
interchanged for both the
solenoids.

6 Air fan for burner No-1 started and tried to ignite Ctrl Room 10:15 am Got failed.

7 Air fan for burner No-1 again started Ctrl Room 10:20 am Started firing after
rectification of solenoid
loose connection of the
pilot burner.

8 Burner No-1 flame adjustment William/Ctrl Room 10:25 am Air fan damper valve was
opened fully and closed,
adjustment done and
flame was set on a
particular opening.

9 Replacement of PCV-041 of Burner -4 William 10:30 am Work started.

10 Replacement of PCV-041 of Burner -4 William 11:05 am Work completed.

11 Set point adjustment of PCV-041 William 11:30 am Set Value adjusted to 50


mbar.

12 Burner No-4 firing done. Ctrl Room 12:00 pm Got ignited.

13 Burner No-4 flame adjustment William/Ctrl Room 12:05 pm Air fan damper valve was
opened fully and closed,
adjustment done and
flame was set on a
particular opening.

14 All the burners stopped. Ctrl Room 12:15 pm For sequence testing of
bag house and
concentrate conveying
system to feed bins.

Note: - Bag charging activity postponed for tomorrow.