You are on page 1of 27

Rig 812

0-01 Advance Move Plan 0-07 Daliy Move Checklist

0-02 Trucking Procedure 0-08 Driver Daily Checklist Rig Release :

0-03 Emergency Plan 0-09 Daily Moving Report Rig Move:- From K-27 To Bhit-13

0-04 Route Map 0-10 Main Camp Loads Moving Distance:- 380 Km

0-05 Camp Lay-out 0-11 Rig Loads Total Move Time:- 15 Days

0-06 Rig Lay-out Lay-out 0-12 Pre-spud Checklist Rig Spud:

Khalid Awan
Rig 812 Advance Rig And Camp Move Plan
Moving Gears PreMove Move Day - 01 Move Day - 02
Pre move extra loads to new location. CONVOY # 01 CONVOY # 02
Flat-bed ( Single Axle ) 30 trucks Load & Move pipe bins to new location. Load mud tanks/ mud pumps/ HPL manifold Load Mast sections/ beams/ dog houses
Low-bed ( Double Axle ) 12 trucks Check all first aid boxes. & ORS. skid/ trip tank/ shakers/ water tank on low- triangle frames/ air tank/ "A" legs/ BOP
Heavy Hauler ( Double Axle )10 trucks Help the Doctor to arrange all. bed trailers & remaining trailers will be loaded skid/ koomey unit/ other DP, DC bins/
55ft. Long-bed 02 trucks with tool bins, drill pipes bins at k-27. Total genie lift & other miscellaneous loads at
Heavy Pusher 03 trucks 27 loads will be loaded on 1st day Meanwhile k-27. Total 25 trucks will be loaded. This
Forklift (10 tons) 01 no lower rig floor & mast & start dismantling convoy will leave k-27 on early morning of
45-50 tons crane 3 Cranes mast & sub-structure. The convoy will leave 3rd day & reach staging area by 4th day
45 tons crane 6 Cranes k-27 on morning of 2nd day and reach staging morning. Single Axle loads will be trans-
Ambulance 2 area at Bhit field on 3rd day morning. Single ferred to double axle while other double
Double Cabin 2 Axle loads will be transferred to double axle axle trucks will proceed to Bhit-13 after
while other double axle trucks will proceed security checks & inspections by ENI
to Bhit-13 after security checks & inspection mechanics
by ENI mechanics.

Crew - A Crew - B
STP NTP
STC STC
Chief Mechanic Chief Electrician
Asst. mechanic Asst, Electrician
Driller Driller
Asst, Driller Asst, Driller
Derrick man Derrick man
4x Floormen 4x Floormen
4x Roustabout 4x Roustabout
Welder W.H.Man
Radio Operator Radio Operator

Schlumberger Private
Schlumberger Private
Move Day - 03 Move Day - 04 Move Day - 05 Move Day - 06
Complete dismantling of substructure CONVOY # 03 Location clean-up, housekeeping & CONVOY # 04
meanwhile cleaning substructure beams Load sub-bases/ substructure acce- site restoration while waiting for trailers Will load 25 trucks with choke manifold,
and preparing loads and house keeping ssories/ draw works etc/ engine house to arrive at location. gas buster, welding workshop, cat-walk
on location. VFD houses/ diesel tank/ cable trays/ Convoy# 02 will reach on evening of 4th stairs, V-door, spare water tanks, 29"
warehouse/ fire fighting system/ rotary day at Bhit-13. Offloading & spotting diverter, 21 1/4" BOP, WDI crane, WDI
table/ mini-camp & generator for mini equipments will be started on 5th day Forklift & other baskets etc. Need to
camp.28 trucks will be loaded. This morning. load 2 junior caravans from main camp
convoy will leave k-27 on early morning having 12 beds in total which will be
of 5th day & reach staging area by 6th rigged up with mini-camp at Bhit-13 to
day morning.Single Axle loads will be accommodate crew while moving &
transferred to double axle while other rigging up main camp. This convoy will
double axle trucks will proceed to Bhit- leave k-27 on early morning of 7th day
13 after security checks & inspections & reach staging area by 8th day morning
by ENI mechanics. Single Axle loads will be transferred to
Convoy #01 will reach on evening of 3rd double axle while other double axle trucks
day at Bhit-13.Offloading & spotting will proceed to Bhot-13 after security
mud systems will be started on 4th checks& inspections by ENI mechanics.
day morning.

Schlumberger Private
Schlumberger Private
Move Day - 07 Move Day - 08 Move Day-09 Move Day - 10 & 11
Location restoration, cement pad Load all approximately 15 remaining CONVOY # 05 Cont. Rigging up equipments at Bhit
cleaning,& collecting all trash, conta- loads at k-27. Clear location & send The main camp will be loaded. 33
minated sand etc while waiting for all contractors cranes to main camp. loads in total & camp location will
trucks to arrive. Cont. rigging up sub-structure & mast be cleaned & restored for handing over
Convoy#03 will reach on evening of 6th & Mini-camp R/U will be completed by to ENI. Afterwards, 3 contractor cranes
day at Bhit-13. offloading & spotting of 8th day. working at k-27 will be released. This
sub-bases, & offloading & R/U minicamp convoy will leave Main Camp Site on
will be started on 7th day. Also rig up early morning of 10th day & reach
VFD & engine rooms.(Need to order staging area by 11th day morning.
Diesel). Single Axle loads will be transferred
STP, Chief Mechanic & Chief Electrician to double axle while other double axle
to leave k-27 for Bhit-13 early in the trucks will proceed to Bhit-13 after
morning. security checks & inspections by ENI
mechanics. R/U main camp will start
by morning of 12th day & will be com-
pletely rigged up (including water,
sewerage connections & power supply)

Schlumberger Private
Schlumberger Private
Move Day - 12 Move Day - 13 Move Day - 14 Move Day - 15
Convoy# 05 will reach on evening of 11th Main camp will be 100% rigged up (including Raise mast & Rig Floor prepare rig floor, Complete rig up 100% Check mud tank
day & offloading will begin on morning of water, sewerage connections & power supply) rig up stairs, standpipes, V-door, cat-walk leakage, mix spud mud, pressure testing
12th day at Bhit-13, Offloading & R/U main Continue rigging up. String up drilling line, & pickup TDS, connect the power supply surface lines, rig up diverter, preparing to
camp will start by morning of 12th day. and R/U tong lines, air tugger lines, pipe function test TDS & the hydraulic unit spud on Well Bhit-13. Realest all rig moving
Two junior side caravans to be shifted fromspinner line, put mast on the high horse. should be 100% ready & tested. equipment.
mini camp to main camp. Rig up monkey board. Visual inspection of
loose objects & safety pins on the mast.

Schlumberger Private
Schlumberger Private
TRUCKING PROCEDURE
TRUCK DRIVERS BRIEFING.

THE TRUCK DRIVERS WILL BE BRIEFED BEFORE STARTING THE MOVE ( TOOL BOX MEETING)
AT THE START OF THE DAY, OR WHEN REQUIRED.
THE BRIEFING INCLUDES:
(1) THE BACK GROUND OF THE RIG MOVE.
(2) NUMBER OF LOADS AND TYPES.
(3) TIME PLANNING.
(4) ROAD SAFETY POLICY AND GENERAL SAFETY RULES.
(5) TRAFFIC OFFICERS ( TRUCK PUSHER ) POSITION.
(6) OVERHEAD POWER LINES.
CHECK LIST
HIRED CRANES WILL BE INSPECTED BY MECHANIC AND MIC.
THE TRUCKS WILL BE CHECKED BY THE TOOL PUSHER OR HIS DESIGNATE
AND THE SAFETY OFFICER WHEN THEY ARRIVE ON LOCATION.
THE FORMAT FOR THE CHECKS IS ATTACHED WHEN ACCEPTABLE THE TRUCK WILL BE LOADED.
RECORDING LOADS VERSUS TRUCKS

THE TOOL PUSHER WILL NOMINATE WARE HOUSE MAN TO RECORD THE LOAD AGAINST THE TRUCK,
SUCH THAT, AT THE END OF THE DAY, A GOOD RECORD OF THE WORK DONE CAN BE PRODUCED,
WHICH WILL BE USED FOR UPDATING RIG MOVE PLANNING.
THE TRUCK PUSHER RESPONSIBILITY.
THE TRUCK PUSHER WILL STOP TRUCKS AWAY FROM THE HEAVY WORK AREA. THE DRIVER SHALL
CHECK THE BINDING OF THE LOADS ONCE AGAIN THEN FOLLOW THE TRUCK PUSHER'S
COMMAND.

Schlumberger Private
Schlumberger Private
MEDICAL EMERGENCY RESPONSE PLAN RIG-812
FOR RIG MOVE FROM K-27 To BHIT 13
Weatherford
Drilling International
Rig or well site Base Road
The Rig 812 contains a well equipped clinic, the medical coverage team on the Rig 812 consists of:
-*RIG-812 Doctor
During the rig moving ,the Doctor will be responsible for providing the medical coverage under the supervision
Assess level of emergency of the Rig superintendent.
Contact client and respond as per guidelines in ERP The distance between xxxxxxx
Company Man For all regular loads:380.Km
or
Field Manager (Bhit)
CALL THE BASE BY PHONE OR RADIO A-PLAN BEFORE THE CLINIC IS SHIFTED TO THE NEW LOCATION
24 hours: Security Manager. 1-AT OLD LOCATION (K-27):
Cell number: 0301-8565211 The medical coverage will be provided through the clinic with rig-812 Doctor assistance during the working hours
Alternates: 051-2850054-55, 051-2850846-48 All the equipment and the drugs for the administration of first aid will be present.
Night hours 7pm to 7am: Head Office (who will contact security olc) The ambulance of Rig -812 will be on the old location with Doctor, however another doctor with a separate ambulance will be
Phone number: 051-2850054-55, 051-2850846-48 stationed at new location.
Give the following information: IN CASE OF EMERGENCY THE DOCTOR WILL DO THE FOLLOWING:
Your own identity
Accident location a-Will provide first aid and resuscitation to the patient
Number of injured b-Will inform the MIC and the ENI representative
Injuries description c-Will accompany the patient ,depending upon the condition of the patient, after consolation with
A phone number or a radio code where you can be called back MIC .However once the doctor and/or the ambulance leaves the location , the operation will be
suspended until the medical coverage is restored.
Security Manager calls 2-ON NEW LOCATION( Bhit-13 ):
The doctor with an ambulance will be available on location for the whole working hours with the following:
a-A well equipped first aid kit.

Country Manager b-A straight stretcher.


QHSE Manager
Direct phone: Nabil Yacoub / Jean Paul ( Alternate ) c-2 blankets
0300-8522113 Ambulance will be mobilized d-A resuscitator with oxygen cylinders and AMBU bag.
your own identity, all from location upon advice of e-Ambulance ( on new location )
details collected and doctor present at site
a phone number
where the doctor can
B-PLAN AFTER SHIFTING THE CLINIC TO THE NEW LOCATION
call you back
authorized manager The medical facilities previously present on the old location will be shifted to the new location .(and the ambulance
activate advance will be available for both locations)
In case of medical emergency ,the Doctor will follow the line of actions as he was using before.

In case of emergency and if the patient has to be transported (by road) and
Security Manager decide/ advise EMT / Company Man on EVAC
it needs to contact the hospital medical services ,the emergency
and nearest HOSPITAL clinic for Medicare and /or stabilization

Evacuation from site


contact point will be the WDI
Call Security Manager
0301-8565211
if necessary, call QHSE Manager
In case of evacuation by air, point of contact will be ENI
at
0300-8522113

follow instructions by on-duty


IMPORTANT CONTACT NUMBERS
transportation to Transportation to Transportation to Doctor
instruction.
Aga Khan Nearby Hospital Shifa Hospital Arrange injured transportation to Nabil Yacoub Jean Paul
air ambulance ETD.
Security to clear airport Country Manager 0302-8543158 Operation Manager 0301-8215289
procedures ,landing/taking off
authorization and refueling if
necessary.
Shams ul Islam Naeem Subhani
Rig Supt. 0302-8543265 QHSE Manager 0300-8522113

Decision made Muhammad Khalid Awan Shifa Hospital Hira Medical Center
by EMT leader
to medevac out Rig Supt. 0300-5006204
of site Sukkur 071-5613501
( Waheed Akhund )
051 4603666 071-5614555
(Dr. Saeed Akhund)

Col. Mateen Aga Khan Hospital


Security Manager 0301-8565211 021 34930051

ENI Radio Room OMV Radio Room ( Kadinwari )


021-35879951 Ext. 2516 0243-638515,514

Schlumberger Private
Khalid

Schlumberger Private
MAIN BASE CAMP SITE

Jr. Jr. Sr. Sr. VIP-1 VIP-3 A-1 B-1 D-1 E-1 F-1 G-1 C-1
Mess Kitch Kitch Mess 2 Bed 2 Bed

VIP-2 VIP-4 A-2 B-2 D-2 E-2 F-2 G-2 C-2


2 Bed 2 Bed
GENERAOTOR

H-1 H-2
STORE

STORE

I-1 I-2

Y-1 Y-2 Y-3

Main J-1 K-1 L-1 M-1 O-1 P-1 Q-1 R-1


TV ROOM

WASHROOM
MOSQUE

Gate
J-2 K-2 L-2 M-2 O-2 P-2 Q-2 R-2

J-3 K-3 L-3 M-3 O-3 P-3 Q-3 R-3


LAUNDARY

Water Tank
1

3
WDI-812 Rig Layout

1500

Reserve 2 Reserve 1
1500
1500

Mixing Hopper Mixing Tank Suction Tank Mud Cleaner Tank Shaker Tank
980 1500

3010
Suction Skid

3000
Water Tank 3 Water Tank 1 Water Tank Trip Tank
1000 9300

11260
Fire Tank Manifold

M.P.3

M.P.2

M.P.1

2600
12980
Water Tank 4 water Tank 2
Skid

2100

2100

14515
1000

1040

10015
4500 4500 191100

Cable Trey 10720 O.D.S. Sub Base


12350
2900

7350
VFD Room 2 Cable Trey Cat Walk

Cable Trey

3675

6325
1000

2645
D.S. Sub Base
VFD Room 1
2900

5090

36000
Engine Skid 4

Engine Skid 3

Engine Skid 2

Engine Skid 1
Diesel Tank

15000

3000 3000 3000 3000 Prepared By: Hosny Aly


DRIVER AND VEHICLE CHECKLIST
Vehicle Registration Make and type of vehicle
Drivers Personal details
Drivers Name
Drivers License Valid Yes / No
Safety Boots Helmet Gloves Overalls Yes / No Yes / No Yes / No Yes / No
Drivers / Helper
Helpers Name
Drivers License Valid Yes / No
Safety Boots Helmet Gloves Overalls Yes / No Yes / No Yes / No Yes / No
Prime Mover Comments
Lights Headlights Yes / No
Stop/tail Yes / No
Indicators Yes / No
Tyres Serviceable Yes / No
Tread Yes / No
Cuts / Bulges Yes / No
Different Size Yes / No
Condition of spare (serviceable) Yes / No
Windscreen Wipers and Wash Yes / No
Horn Serviceable Yes / No
Fifth Wheel lubricated and serviceable Yes / No
Air and electrical connections serviceable Yes / No
Braking system serviceable. Dual System Yes / No
Trailer
24 ton capacity (minimum) Yes / No
12 x 2.4 mtr (minimum) Yes / No
Platform clean and serviceable Yes / No
Tyres Serviceable Yes / No
Tread Yes / No
Cuts / Bulges Yes / No
Different Size Yes / No
Condition of spare (serviceable) Yes / No
Trailer legs Serviceable Yes / No
Trailer hand brake operates Yes / No
Lights Stop / Tail Yes / No
Indicators Yes / No
No cracks in Stanchion pockets 2/4 Yes / No
Side Stanchions pockets 2/4 Yes / No
3 Chains With clevis hooks (minimum) Yes / No
3 loadbinders (minimum) to 20 ft cont Yes / No
Chain and tension device Yes / No
Fire extinguisher Yes / No
Safety belt fitted and serviceable Yes / No
First aid kit Yes / No
Hazard warning triangle Yes / No
Dual circuit brakes Yes / No
Drivers behavior during loading V.good Good Satisfactory Bad
Drivers behavior during the journey
Drivers behavior during off loading
Driver followed all instructions
Driver acceptable for future moves Yes / No
Vehicle acceptable for future moves Yes / No

Schlumberger Private
Driver Check List
Rig 812
DATE:- MOVE NO:-

PLAN FOR DAYS WORK DISCUSSED WITH SUPERVISOR

SAFETY MEETING

GENERAL SAFETY MEETING WITH PERSONNEL

SUPERVISORS WITH INDIVIDUAL CREWS

EMERGENCY CONTINGENCY PLANS ISSUED FOR

OLD LOCATION

NEW LOCATION

SAFETY INSPECTION OF EQUIPMENT

CRANE REMARKS

TRUCK

FORKLIFTS

OILFIELD

SLINGS

Remarks:

Schlumberger Private
Daily Rig Move Report
Rig 812
Rig Move Report
Day- 01
Date: 14-12-2005 Distance 00 Km
Camp Loads 0
Rig Loads 0
Dherki Makhdood deep - 2 Total Loads 0
Old Location New Location Rolling Gears
Rig Down 0% Rig Up 0% Single Excels:
Rig Move 0% Rig Up ( camp) 0% Low Beds:
Camp Down 0% Loads Arrived Today 0 Crane:
Camp Move 0% Total Loads Arrived 0 Wheal loader:
Total Loads Moved Total Loads 0 Total Trucks: 21

Description Personnel On Board


Old Location New Location
Client 0 0
SDS 0 0
Catering 0 0
Others 0 0
Total 0 0
Remarks

Khalid Awan Supt.812


Nb of
CAMP SITE loads Trailer Type Comments
J CARAVAN 1 FLAT BED Priority 1
K CARAVAN 1 FLAT BED Priority 1
DRY STORE / COLD STORE 1 FLAT BED Priority 1
SENIOR RECREATION 1 FLAT BED Priority 1
JUNIOR RECREATION 1 FLAT BED Priority 1
SENIOR KITCHEN 1 FLAT BED Priority 1
SENIOR MESS 1 FLAT BED Priority 1
JUNIOR KITCHEN 1 FLAT BED Priority 1
JUNIOR MESS 1 FLAT BED Priority 1
L CARAVAN 1 FLAT BED Priority 1
M CARAVAN 1 FLAT BED Priority 1
N CARAVAN 1 FLAT BED Priority 1
O CARAVAN 1 FLAT BED Priority 1
P CARAVAN 1 FLAT BED Priority 1
Q CARAVAN 1 FLAT BED Priority 1
R CARAVAN 1 FLAT BED Priority 1
S CARAVAN 1 FLAT BED Priority 1
JUNIOR BATH 1 FLAT BED Priority 1
VIP CARAVAN 1 FLAT BED Priority 1
H CARAVAN 1 FLAT BED Priority 1
I CARAVAN 1 FLAT BED Priority 1
C CARAVAN 1 FLAT BED Priority 1
B CARAVAN 1 FLAT BED Priority 1
A CARAVAN 1 FLAT BED Priority 1
LAUNDRY 1 FLAT BED Priority 1
JUNIOR BATH 1 FLAT BED Priority 1
CAMP GENERATOR 1 LOW BED Priority 1
FUEL TANK 1 LOW BED Priority 1
WATER TANK-1 1 FLAT BED Priority 1
WATER TANK-2 1 FLAT BED Priority 1
MOSQUE 1 FLAT BED Priority 1
SEWERAGE LINES 1 FLAT BED Priority 1
Rig 812 - Move Planning to Bhit 13
1 2

CAMP SITE Nb of
loads Trailer Type Comments
1 J CARAVAN 1 FLAT BED Priority 1
2 K CARAVAN 1 FLAT BED Priority 1
3 DRY STORE / COLD STORE 1 FLAT BED Priority 1
4 SENIOR RECREATION 1 FLAT BED Priority 1
5 JUNIOR RECREATION 1 FLAT BED Priority 1
6 SENIOR KITCHEN 1 FLAT BED Priority 1
7 SENIOR MESS 1 FLAT BED Priority 1
8 JUNIOR KITCHEN 1 FLAT BED Priority 1
9 JUNIOR MESS 1 FLAT BED Priority 1
10 L CARAVAN 1 FLAT BED Priority 1
11 M CARAVAN 1 FLAT BED Priority 1
12 N CARAVAN 1 FLAT BED Priority 1
13 O CARAVAN 1 FLAT BED Priority 1
14 P CARAVAN 1 FLAT BED Priority 1
15 Q CARAVAN 1 FLAT BED Priority 1
16 R CARAVAN 1 FLAT BED Priority 1
17 S CARAVAN 1 FLAT BED Priority 1
18 JUNIOR BATH 1 FLAT BED Priority 1
19 VIP CARAVAN 1 FLAT BED Priority 1
20 H CARAVAN 1 FLAT BED Priority 1
21 I CARAVAN 1 FLAT BED Priority 1
22 C CARAVAN 1 FLAT BED Priority 1
23 B CARAVAN 1 FLAT BED Priority 1
24 A CARAVAN 1 FLAT BED Priority 1
25 LAUNDRY 1 FLAT BED Priority 1
26 JUNIOR BATH 1 FLAT BED Priority 1
27 CAMP GENERATOR 1 LOW BED Priority 1
28 FUEL TANK 1 LOW BED Priority 1
29 WATER TANK-1 1 FLAT BED Priority 1
30 WATER TANK-2 1 FLAT BED Priority 1
31 MOSQUE 1 FLAT BED Priority 1
32 SEWERAGE LINES 1 FLAT BED Priority 1
RIG SITE

1 Mast Section 1(A ) 1 FLAT BED Priority 2


2 Mast Section 2 1 FLAT BED Priority 2
3 2 pieces Mast Section 2 1 FLAT BED Priority 2
4 2 pieces Mast Section 3 1 FLAT BED Priority 2
5 Mast A-Frame 1 FLAT BED Priority 2
6 Sub-base & Gin Pole 1 1 HH (48 ft) Priority 2
7 Sub-base & Gin Pole 2 1 HH (48 ft) Priority 2

Schlumberger Private
8 Monkey board & Rig Floor 1 FLAT BED Priority 2
9 Drawworks set back 1 FLAT BED Priority 2
10 MAST SUPPORTS 1 FLAT BED Priority 2
11 Crown Block (Mast B) 1 LOW BED Priority 2
12 ACTIVE MUD TANK-1 1 LOW BED Priority 2
13 ACTIVE MUD TANK-2 1 LOW BED Priority 2
14 RESERVE MUD TANK-1 1 LOW BED Priority 2
15 RESERVE MUD TANK-2 1 LOW BED Priority 2
16 TREATMENT TANK/ DEGASSER TANK 1 LOW BED Priority 2
17 RIG WATER TANK + HOPPERS 1 LOW BED Priority 2
18 SPARE MUD TANK ( BLUE ) 1 LOW BED Priority 2
19 PCR 1 LOW BED Priority 2
20 MUD PUMP-1 1 LOW BED Priority 2
21 MUD PUM-2 1 LOW BED Priority 2
22 TRIP TANK SKID 1 LOW BED Priority 2
23 SHAKER SKID 1 LOW BED Priority 2
24 SHAKER SKID WALK WAY-RIGHT 1 LOW BED Priority 2
25 SHAKER SKID WALKWAY - LEFT 1 LOW BED Priority 2
26 RIG ENGINE # 1 1 LOW BED Priority 2
27 RIG ENGINE # 2 1 LOW BED Priority 2
28 RIG ENGINE # 3 1 LOW BED Priority 2
29 KOOMY SKID 1 LOW BED Priority 2
30 DRAWORKS 1 LOW BED Priority 2
31 WHITE WATER TANK + GROUND HOPPER 1 FLAT BED Priority 2
32 GROSS HOPPER 1 FLAT BED Priority 2
33 COOLING SKID 1 FLAT BED Priority 2
34 FLARE LINES / RACKS 1 FLAT BED Priority 2
35 Drill Pipe set back & Rotary table beams 1 FLAT BED Priority 2
36 X-OVER BASKET 1 FLAT BED Priority 2
37 CATWALK / MOUSE HOLE 1 FLAT BED Priority 2
38 RIG TOILET + SULAIR COMPRESSOR 1 FLAT BED Priority 2
39 OIL BASKET 1 FLAT BED Priority 2
40 MECHANICAL BASKET 1 FLAT BED Priority 2
41 ELECTRIC BASKET 1 FLAT BED Priority 2
42 TRAINING ROOM 1 FLAT BED Priority 2
43 DIESEL TANK -1 1 LOW BED Priority 2
44 DIESEL TANK-2 1 LOW BED Priority 2
45 CSG HANDLING DSA BASKET 1 LOW BED Priority 2
46 BOP SKID STUMP 13 5/8" 1 LOW BED Priority 2
47 SUPER CHARGER SKID 1 LOW BED Priority 2
48 DRILLER SHELTER/ HYD UNIT 1 LOW BED Priority 2
49 POOR BOY DEGASSER/ CHOKEMANIFOLD 1 LOW BED Priority 2
50 DRILL COLLAR BASKET 4 3/4" 1 HEAVY HAULER Priority 2
51 3 1/2" DRILL PIPE BASKET # 1( G-11 ) 1 HEAVY HAULER Priority 2
52 3 1/2" DRILL PIPE BASKET # 2 ( G-11 ) 1 HEAVY HAULER Priority 2
53 3 1/2" DRILL PIPE BASKET # 3( G-11 ) 1 HEAVY HAULER Priority 2

Schlumberger Private
54 3 1/2" DRILL PIPE BASKET # 4 (G-111 ) 1 HEAVY HAULER Priority 2
55 3 1/2" DRILL PIPE BASEKT # 5 ( S-135 ) 1 HEAVY HAULER Priority 2
56 NO CHARGE STORE 1 FLAT BED Priority 3
57 RUBBER STORE 1 FLAT BED Priority 3
58 FISHING STORE 1 FLAT BED Priority 3
59 DRILLING STORE 1 FLAT BED Priority 3
60 ELECTRIC STORE 1 FLAT BED Priority 3
61 MECHANICAL STORE 1 FLAT BED Priority 3
62 WELDING SHOP 1 FLAT BED Priority 3
63 PAINT STORE / BOP STORE 1 FLAT BED Priority 3
64 MECHANICAL/ELECTRIC WORKSHOP 1 FLAT BED Priority 3
65 PMS OFFICE 1 FLAT BED Priority 3
66 TOOL PUSHER OFFICE 1 FLAT BED Priority 3
67 COMPANY MAN OFFICE 1 FLAT BED Priority 3
68 CLINIC 1 FLAT BED Priority 3
69 MIC LIVING / RIG MANAGER CARAVAN 1 FLAT BED Priority 3
70 GEOLOGIST ROOM/ RADIO ROOM 1 FLAT BED Priority 3
71 WATER TANKS RIG CAMP 1 FLAT BED Priority 3
72 KOOMY LINES / LADERS 1 FLAT BED Priority 3
73 WELDERS BASKET 1 FLAT BED Priority 3
74 SAFETY CONTAINER 1 FLAT BED Priority 3
Crown Block (Mast B) 1 LOW BED Sukkur yard
Mast Section 1( B ) 1 FLAT BED Sukkur yard
Mast Section 2 1 FLAT BED Sukkur yard
75 2 pieces Mast Section A 1 FLAT BED go to suk yard
76 2 pieces Mast Section A 1 FLAT BED go to suk yard
Mast A-Frame 1 FLAT BED Sukkur yard
77 Sub-base & Gin Pole A 1 HH (48 ft) Dubai
Sub-base & Gin Pole 2 1 HH (48 ft) Sukkur yard
Wooden Matting # 1, drill line 1 FLAT BED Sukkur yard
Wooden Matting # 2 1 FLAT BED Sukkur yard
78 Monkey board & Rig Floor mast A 1 FLAT BED go to suk yard
79 Drawworks set back + mast box frame 1 FLAT BED go to suk yard
Drill Collar Basket # 1( 9 1/2" ) 1 HEAVY HAULER Sukkur yard
Drill Collar Basket # 2 ( 8 1/2" ) 1 HEAVY HAULER Sukkur yard
Drill Collar Basket # 3 ( 6 1/2" ) 1 HEAVY HAULER Sukkur yard
5" Drill Pipe Basket # 1 ( E-75 ) 77 JNTS 1 LOW BED Sukkur yard
5"Drill Pipe Basket # 2 ( G105 ) 60 JNTS 1 LOW BED Sukkur yard
5" Drill Pipe Basket # 3 ( G105 ) 46 JNTS 1 LOW BED Sukkur yard
5" Drill Pipe Basket # 4 ( G105 ) 75 JNTS 1 LOW BED Sukkur yard
5" Drill Pipe Basket # 5 ( G105 ) 65 JNTS 1 LOW BED Sukkur yard
5" Drill Pipe Basket # 6 ( G105 ) 70 JNTS 1 LOW BED Sukkur yard
5" Drill Pipe Basket # 7( G105 ) 50 JNTS 1 LOW BED Sukkur yard
5"HWDP ( 32 JNTS ) 1 LOW BED Sukkur yard
80 set back mast A 1 LOW BED go to suk yard
81 Substructure mast A 1 LOW BED Dubai

Schlumberger Private
Mud Pump # 3 ( Gardner Denver ) 1 LOW BED Rig-15
TDS 2 LOW BED Base
Acceptance Inspection
Spud Miano-8 Well

Load Categorization:
Low beds Total Loads TOTAL
TOTALRIG LOAD
CAMP TO MOVE
LOADS =
TO MOVE=

Schlumberger Private
Pre-spud Checklist
Date:- Yes No Location:- Yes No
General Engines
Access control in place Are all steps and ladders & gratings in place and secure
Pit barriers in place. Life-buoys at waste pit All moving machinery guarded
Communications system working No leaks in fuel supply system
Fire & H2S Alarms working All air compressors hooked up and running
Fire pump run up. Hoses and branch in place Mast
Wind socks erected Escape & Climbing Lines in place and secured
H2S sets in place & full All mast lights operating
All skids connected to Earth ring system Aircraft warning light operational
Earth system connected to conductor Ladders installed and secure
Drill floor Safety lines installed on winch sheaves
Rotary table centered over wellhead All lights fitted with safety wires
Hook hanging over centre of rotary table Kelly spinner hoses snubbed
Air winches operational & pad eye pins secured Kelly and wash down hoses snubbed
Air winch exhausts routed below Drill floor All mast pins in place and secured with safety pins
Winch wires in good condition No damaged or bent spars
Winch wires have free run and clear of mast Stabbing board installed & operational (full stroke)
Winch brakes in good condition Chemical Mixing & Storage Areas
Bulldog clips correctly installed on winch wires Eye wash system operating
All shackles and bolts on hook and swivel secured Deluge shower operational
Geolograph chart operational. Geolograph wire installed EMEC hazardous chemical data sheet posted
PVT system recorder operational Hazardous chemicals segregated and identified
Drawworks brake in good condition and adjusted evenly Adequate protective equipment available
Brake bands MPI’d during rig-move Mud Pumps
Aux. Brake dog clutch lever secured Mud pumps & charge pumps operational
Aux. Brake operational and tested Pulsation dampers pre-charged to +/-300psi (for spud)
Crown-O-Matic operational & tested Pump cooling water clean
Main brake cooling system operational Piston cooling water pumps operating
Engine and SCR Emergency stops tested Jumper hoses snubbed
Traveling block clear of mast Piston covers installed
Fast line clear of mast Relief valve lines secured
Dead line clear of mast Mud Tanks
Block line in good condition All hoses, lines and valves installed
Deadline clamp secured – bolts correctly torque All agitators operating
Sufficient wraps on drum with blocks near drillfloor All transfer pumps operational
All instrumentation purge systems working. SRE charge pumps operating
Weight Indicator operating – correct gap on sensator Shakers operational
Flo-Sho operational Desander and desilter operational and correctly lined up
Rotary torque gauge operating Centrifuge operational &correctly lined up
Pump, DP and Annulus pressure gauges working Eye wash fountain operational
All gauges for one item reading same pressure Deluge shower operational
SPM & Stroke counters operating for both rig pumps No tripping hazards, slippery floors
All warning lights and gauges on SCR panel operational All gratings and plating secure & in place
V-door gate fitted and operational Handrails & stairs secure
All wind-walls secure and safety pins installed Caustic soda mixing barrels in place
All stairs and hand railings installed and secure All lighting working & undamaged
Kelly scabbard installed All rotating machinery guarded.
Mouse hole installed & secured in cellar. Escape sets available
Kelly Spinner operational – forward and reverse Vacuum degasser operational – vacuum gauge fitted
Man-riding winch operational Remote Choke Panel
Pipe spinner operational DP and annulus gauges operational
Rotary table operating - forward and reverse SPM and total strokes for both pumps operational
Rotary brake operational SCR Room
Kelly and swivel assembly pressure tested No material stored on floor in SCR Room
Standpipe system pressure tested AC system working
Wear sub, saver sub and kelly cocks installed on kelly All panels secured and locked
Tong lines correct length, SWL and good condition Entrance doors secured
Tong hanging lines secured and moving smoothly Sub Base
Tong lines bulldog clips installed correctly Cellar jet operational
Tong & slip dies in good condition All mast pins in place and secured with safety pins
Make up and Break-out heads operational Cellar grating in place
Make-up chain and break-out line in good condition All lights operating
Wire line winch operating All lights secured with safety wires
BA sets & escape sets positioned All drip trays installed – all drain hoses secured
Eyewash system operating Trip Tank
First Aid kit and eye wash bottles available Flow line in place and secured
Stretcher available Mechanical level device working -wire free running
All draw works covers installed & moving parts guarded Electric chart recorder working and calibrated correctly
All deck plates secured – no holes in deck Trip tank pump operational
Kellycock (c/w key) & Gray Valve on drill floor. Fill line connected to bell nipple and trip tank pump
Schlumberger Private