THE PROVISION OF PIPELINE INSTALLATION

SERVICES

SMG1 FLOWLINE PROJECT

JSA
CONTRACT N°……………………………………………………………….. Rev: 0
Page: 1 of 1

JOB SAFETY ANALYSIS (JSA)


Location: Person in charge: Date:
Work activity (Job): coating activity
Work team:
Potential accidents or hazards Recommendations to eliminate or reduce potential hazards associated
Sequence of basic job steps
associated with each step with each step
Preparation of work place Slip trip and fall hazard Provide good lighting for the working area.
Provide car for any emergency.
Perform housekeeping inside working area.
Organize any trailing cable or hoses.
Insure good access and egress.
Provide signs and safety indication about task performed
into working area.
Cleaning grinding pipe task Debris project Face shield must be used during grinding task
Fire hazard Provide fire extinguisher
Slip trip and falls Remove trailing cable from working area
Application of coating material Wrong safe work method Use competent person
fire (use of propane) Provide safety clump for propane hoses. Fire extinguisher
Burn will have placed near working area. Area will be free from
Fume / Asphyxia paper, wood etc.
Use adequate gloves.
Use mask to avoid fume inhalation.