Professional Documents
Culture Documents
00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
SATR-P-3911
Power Transformer Tank - Jobsite Acceptance Test 3-Jul-18 ELECT
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED TEST DATE & TIME ACTUAL TEST DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
TEST PROCEDURE ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
A. Document Review
Schedule Q
A1 Review documents of Material Receiving for the Power Transformer Tank. Att. IV
Sec. 3.3
Schedule Q
Identification procedure reviewed and implemented for the Power
A2 Att. IV
Transformer Tank.
Sec. 4.2
Material identification shall be implemented for all materials, parts and
components, including partially fabricated assemblies. Power Transformer Schedule Q
A3 Tank shall be identified by using tags, stamps, color coding, stencils or Att. lV
labels. The location and method of identification shall not affect the Sec. 4.2
function or quality of the material.
B. General Requirements
C. Material Inspection
Check that the Contractor or it's Saudi Aramco approved third party
Schedule Q
inspector performed the quality activities at the supplier and sub-supplier
C5 Att. llI
locations as required by the inspection level assigned for the materials
Sec. 3.2
and equipment identified in SAER-1972 Inspection Requirements.
Page 1 of 10
Transformers shipped with its main tank filled with insulating liquid and
blanketed with gas under pressure, measure and record the gas pressure
SAES-P-121
D2 and the ambient temperature when the unit arrives at the work site and
Sec. 3.2
every month thereafter.
(Refer to shipping documents & Manufacturer's Instructions)
Page 2 of 10
SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
SATR-P-3911
Power Transformer Tank - Jobsite Acceptance Test 3-Jul-18 ELECT
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
In case the transformer has been stored for more than two months after
the assembly, possible leakages shall be checked. All sealing joints must SAES-P-121
D4
be re-tightened. Sec. 3.2
(Refer to shipping documents & Manufacturer's Instructions)
Turns-ratio test results shall not deviate by more than one-half percent
SAES-P-121
D12 from either the adjacent coils or the calculated ratio.
Sec. 3.2
NETA, ATS- Sec.7.2.2.3.2.3
Page 3 of 10
SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
SATR-P-3911
Power Transformer Tank - Jobsite Acceptance Test 3-Jul-18 ELECT
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
Verify that cooling fans and pumps operate correctly and have appropriate
SAES-P-121
D19 overcurrent protection.
Sec. 3.2
NETA, ATS- Sec.7.2.2.1.11
Verify operation of alarm, control and trip circuits from temperature and
level indicators, pressure relief device, gas accumulator and fault pressure SAES-P-121
D20
relay, if applicable. Sec. 3.2
NETA, ATS- Sec.7.2.2.1.10
Individual CT's: Polarity results shall agree with transformer markings. SAES-P-121
D27
NETA, ATS- Sec.7.10.3.2.1.3 Sec. 3.2
Page 4 of 10
SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
SATR-P-3911
Power Transformer Tank - Jobsite Acceptance Test 3-Jul-18 ELECT
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
Ensure that the unit is properly grounded per project drawings and that the
SAES-P-121
D32 neutral conductor is correctly installed.
Sec. 3.2
NETA, ATS- Sec. 7.13.1.1
Check that all the required accessories are available and correctly
SAES-P-121
D33 installed per manufacturer's data.
Sec. 3.2
Refer to Purchase Order and delivery note.
Ensure that the transformer tap changer is set for correct voltage and
SAES-P-121
D36 record setting after testing is completed.
Sec. 3.2
NETA, ATS- 2009
Determine if the primary bushing and secondary bushing have the proper
length for creepage distance as required by Saudi Aramco standards. 14-SAMSS-534
D39
Bushings shall have a minimum creepage of mm per kV line-to-line Sec.3.2
voltage as specified in Table 6 of ANSI/IEEE C57.12.20.
Page 5 of 10
SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
SATR-P-3911
Power Transformer Tank - Jobsite Acceptance Test 3-Jul-18 ELECT
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
Check that instrument, control cabinet, and tank grounding is correctly SAES-P-111
D42
installed and connected to the main ground system. Sec.9.8.2
E. TEST RESULTS
Core to Ground M-
Insulation Resistance Tester - 1 KV DC Insulation Test Ohms
1 KV
Brand: ______________
S/N: ______________
Calib. Date:___________
Winding Insulation
M-
Insulation Resistance Tester - 5 KV DC Resistance and
Ohms
Polarization Index
5KV
Brand: ______________
S/N: ______________
Calib. Date:___________
Page 6 of 10
SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
SATR-P-3911
Power Transformer Tank - Jobsite Acceptance Test 3-Jul-18 ELECT
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
Winding Insulation
For Control Circuit M-
Resistance and
500 VDC Ohms
Megger Polarization Index
Brand: ______________
S/N: ______________
Calib. Date:___________
Values to be Winding
Milli-
comparable with Resistance
Ohms
Multi Amps Micro Ohm-Meter Factory Test Values Measurement
Brand: ______________
S/N: ______________
Calib. Date:___________
S/N: ______________
Calib. Date:___________
S/N: ______________
Calib. Date:___________
S/N: ______________
Calib. Date:___________
S/N: ______________
Calib. Date:___________
Page 7 of 10
SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
SATR-P-3911
Power Transformer Tank - Jobsite Acceptance Test 3-Jul-18 ELECT
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
Calib. Date:___________
Insulation Power
10 KV Factor Test
Doble Tester (Doble Test)
Brand: ______________
S/N: ______________
Calib. Date:___________
Winding Excitation
10 KV AC RMS Current Test
Doble Tester
Brand: MULTIAMP
S/N: ______________
Calib. Date:___________
S/N : ______________
Calib. Date:___________
Insulation
1000 Volts Resistance Test
Megger
Brand: ______________
S/N : ______________
Calib. Date:___________
S/N : ______________
Calib. Date:___________
Page 8 of 10
SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
SATR-P-3911
Power Transformer Tank - Jobsite Acceptance Test 3-Jul-18 ELECT
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
Polarity Test
Digital Multi Meter
Brand: ______________
S/N : ______________
Calib. Date:___________
Magnetization
Digital Multi Meter Current Testing
Brand: ______________
S/N : ______________
Calib. Date:___________
Burden Test
Digital Multi Meter
Brand: ______________
S/N : ______________
Calib. Date:___________
F. CONCLUSIONS
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
REMARKS:
REFERENCE DOCUMENTS:
Page 9 of 10
SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
SATR-P-3911
Power Transformer Tank - Jobsite Acceptance Test 3-Jul-18 ELECT
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
*Person Responsible for Implementation of Test and Analysis of Results Y = YES N = NO F = FAILED
Page 10 of 10