17
Check for all Push Button wiring condition Daily
(Lugs, sleeve, laying, gland tightness)
18 Check Push Button Box Condition (Box & Stand Damage) Daily
19 Check the working condition of Emg Push button. Daily
20 Check the safety plug working condition. Daily
21 Condition of Slide cables,Push button cables, air hoses. Daily
22 Check overflow of jib grease in collection tray. Daily
23 Check side safety guard condition Daily
24 Check the Counter & Buzzer working condition Daily
25 Check the condition of fan secondary rope Daily
26 Drain Moisture in air reciever tank. Weekly
27 Lubricate the Balancer Weekly
28 Check main motor current. (Max.:32A) Weekly
29 Check slide motor current (Max.:3A) Weekly
30 Check condition of slide motor drive chain & greasing Weekly
31 Check the working of safety sensor bypass circuit Weekly
32 Check the mounting condition of safety sensor Weekly
33 Check Condition of sensor reflector acrylic sheet Weekly
34 Check condition of routing of all cables & gland tightness Weekly
35 Check condition of air receiver tank safety valve Weekly
Check by MMD staff/TM Daily
Signature of Sup weekly
FORMAT NO
Note : For Instruction please refer daily check method instruction sheet REV NO 0
DATE
PAGE 1
GROUP LEADER TEAM LEADER
Responsibility
DAILY AND WEEKLY MACHINE CHECK SHEET
MACHINE No & TONNAGE: D-1- 250t MAKE SEW Shift Second
MACHINE MAINTENANCE DEPARTMENT (PRESS)
Sl.
DESCRIPTION OF WORK FREQ. DAILY-WEEKLY CHECK SHEET OF D PRESS MACHINE MONTHJun YEAR2020
No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 REMARKS
1 Check condition of indication lamps. Daily
2 Check condition of stroke indicator. Daily
3 Check the air pressure (Std:5.0 to 5.5 kg/sq.cm.) Daily
4 Check condition of die cushion air pressure gauge Daily
5 Check condition of die light. Daily
6 Check for Abnormal noise from slide during operation. Daily
7 Check the functioning of safety sensor Daily
8 Check the grease flow in both jibs. Daily
9 Check Gear Box oil level Daily
10 Check Con Rod Daily
11 Check Grease level in grease pump Daily
12 Check overload unit oil level Daily
13 Check worm shaft gear oil level Daily
14 Drain Moisture in FRL unit & Check condition of FRL Unit Daily
15 Check air leakage. Daily
16 Check oil Leakage Daily
17
Check for all Push Button wiring condition Daily
(Lugs, sleeve, laying, gland tightness)
18 Check Push Button Box Condition (Box & Stand Damage) Daily
19 Check the working condition of Emg Push button. Daily
20 Check the safety plug working condition. Daily
21 Condition of Slide cables, Push button cables, air hoses. Daily
22 Check overflow of jib grease in collection tray. Daily
23 Check side safety guard condition Daily
24 Check the Counter & Buzzer working condition Daily
25 Check the condition of fan secondary rope Daily
26 Drain Moisture in air receiver tank. Weekly
27 Lubricate the Balancer Weekly
28 Check main motor current. (Max.:32A) Weekly
29 Check slide motor current (Max.:3A) Weekly
30 Check condition of slide motor drive chain & greasing Weekly
31 Check the working of safety sensor bypass circuit Weekly
32 Check the mounting condition of safety sensor Weekly
33 Check Condition of sensor reflector acrylic sheet Weekly
34 Check condition of routing of all cables & gland tightness Weekly
35 Check condition of air receiver tank safety valve Weekly
Check by MMD staff/TM Daily
Signature of Sup weekly
FORMAT NO
Note : For Instruction please refer daily check method instruction sheet REV NO 0
DATE
PAGE 1
GROUP LEADER TEAM LEADER
MONTHLY MACHINE CHECK SHEET Responsibility
Signature Of Supervisor
Signature Of Supervisor
Signature Of Supervisor
2 Check the Main Motor V belts for its proper belt tension and any crack
Cleaning of dust & soil from all electric components and checking for its smooth
3
operation
2 Check the Clutch/Brake operation strokes as per procedure given in manual &
replace the C/B cover
3 Check all relays and contactors for its contacts & humming & replace if required
Check the winding resisitance of motors & record. Check for balance resistance in
5 all phases.
Check voltage drop in isolation switch and contactor
6 (<1 volt)
7 Check Shut Height Indicator Accuracy