COMPLIANCE STATEMENT REPORT (CSR) FOR Topographical Survey Drawings (KOC REF # 17051790/KC/L/096)
Action
S.NO Comments Reply
Code
COMMENTS
1) Correct the project tittle in the drawings as per contract. A Noted & Updated
Page 1 of 3
PROJECT : UPGRADATION OF GAS & CONDENSATE AT SOUTH KUWAIT AREA-II
COMPLIANCE STATEMENT REPORT (CSR) FOR Topographical Survey Drawings (KOC REF # 17051790/KC/L/096)
Action
S.NO Comments Reply
Code
Its is noticed that the proposed FG lines are passing through
existing shed located before MF/S1 & MF/S4 as per details Proposed FG Lines is modified and the revised location co-ordinates
9) A
shown in the sheet 12/17. Contractor shall review the same in are revised accordingly.
view of construction feasibility.
Right of way for CO-31A shall be used aas track road in place of Track road shall be field modified pipeline route has been follwed as
10) A
point IF 107 after construction of pipeline per contract
17051790-E-S-6001
Contractor shall study the method of pipeline laying nearby BS-
(Rev A) Method statement will be submitted separately for approval by m/s
1 12) 160 (sheet 12/17 ) and submit the method of statement for A
(Sheet 7/17, 10/17 to KCCEC
Comapany review
13/17 & 15/17)
Specify the missing road crossing details (near undefined line &
13) A Noted & Updated
nearby MF/C-3L & drain lines) in the table of sheet 13/17
Page 2 of 3
PROJECT : UPGRADATION OF GAS & CONDENSATE AT SOUTH KUWAIT AREA-II
COMPLIANCE STATEMENT REPORT (CSR) FOR Topographical Survey Drawings (KOC REF # 17051790/KC/L/096)
Action
S.NO Comments Reply
Code
17051790-E-S-6001 Contractor shall refer our earlier comments sent vide letter ref.
16) A Noted & Updated accordingly
(Rev A) 17051790/KC/L/088 dated 19/06/2018
1
(Sheet 7/17, 10/17 to
13/17 & 15/17) Contractor shall avoid duplication of drawing sheet submission in
17) A Noted
his future correspondences.
ACTION CODES: A - CONCUR; B - CLARIFICATION PROVIDED; N - NON-CONCUR