NUDO A
Mu ≔ 5 tonne ⋅ m ϕp ≔ 1.2 cm h ≔ 20 cm b ≔ 30 cm
bw ≔ 8 cm
t ≔ 5 cm
h = 20 cm
b = 30 cm
SOLUCIÓN
-CALCULO DEL PERALTE EFECTIVO
1
d ≔ h - rec - ϕe - ―⋅ ϕp = 16.8 cm
2
1
d' ≔ rec + ϕe + ―⋅ ϕp = 3.2 cm
2
-CALCULO DEL MOMENTO DE TRANSICIÓN
⎛ t⎞
Mo ≔ ϕ ⋅ 0.85 ⋅ f'c ⋅ b ⋅ t ⋅ ⎜d - ―⎟ = 3.446 tonne ⋅ m
⎝ 2⎠
-VERIFICACIÓN
if Mu < Mo | = “a>t TRABAJAR COMO SECCION CAJON”
‖ “a<t TRABAJAR COMO SECCION REC.” |
‖ |
else |
‖ “a>t TRABAJAR COMO SECCION CAJON” |
‖ |
C2
-CALCULO DE "a"
Mu = ϕ ⋅ ∑ ci ⋅ zi
Valores de prueba
a ≔ 6 cm
Restricciones
⎛ ⎛ t⎞ ⎛ ⎛ t + a ⎞⎞ ⎞
Mu = ϕ ⋅ 0.85 ⋅ f'c ⋅ ⎜((b ⋅ t)) ⋅ ⎜d - ―⎟ + 2 ⋅ bw ⋅ ((a - t)) ⋅ ⎜d - ⎜――⎟⎟⎟
⎝ ⎝ 2⎠ ⎝ ⎝ 2 ⎠⎠ ⎠
Solver
a = 12.52 cm
-CALCULO DE "umax"
⎛ 0.003 ⎞
cmax ≔ ⎜―――― ⎟ ⋅ d = 0.062 m
f
⎜ 0.006 + ― ⎟
y
⎜⎝ Ey ⎟⎠
amax ≔ cmax ⋅ β1 = 5.289 cm
0.85
wmax ≔ amax ⋅ ―― = 0.268
d
wmax 2
umax ≔ wmax - ――― = 0.225
1.7
-VERIFICACION
verificacion ((a)) ≔ ‖ if a < amax| |
‖ ||
‖ ‖‖ “S.S.A” | |
‖ ||
‖ else ||
‖ ‖ “S.D.A” | |
‖ ‖ |
T1 = C1 + C2
T2
As2 ≔ ―― = 2.855 cm 2 As2 = 2.855 cm 2
fy
kg
f's ≔ ‖ if f's > fy| | = 2914.28571 ―― Como ≔ ‖ if f's > fy ||
‖ | | cm 2 ‖ ||
‖ ‖ fy | | ‖ ‖‖ “f's>fy Mantener la fluencia de acero” | |
‖ ‖ || ‖ ||
‖ else || ‖ else ||
‖ ‖ f's || | ‖ ‖ “f's<fy Asumir la fluencia calculada” | |
‖ ‖ | ‖ ‖ |
Como = “f's<fy Asumir la fluencia calculada”
fy
A's ≔ As2 ⋅ ― = 4.114 cm 2 A's = 4.114 cm 2
f's
DISPOSICIÓN DE ACERO PARA "As"
CONTROL DE SEPARACION
CONTROL DE SEPARACION
2 ϕ16 + 1 ϕ12
3 ϕ20