PRODUCT NAME : CAT SWL INLET MACHINED Date of Origin : 20/03/2018 PFC No: PFC/07/SRD- 01
1. Quantity mismatch
RAW MATERIAL FROM 1. No of Qty, 1. Loading and Unloading the material,
10 2. Part mix up ISC - I NA NA
FOUNDRY 2. Free from part mixup. 2. Parts counting.
3. Parts damage.
30 RAW MATERIAL STORAGE Part mix up ISC - II NA NA 1.Keep it in separate bins By using fork lifter
RAW MATERIAL
TRANSPORTATION FROM Surya Engineering By using fork lifter
40 Casting defects NA NA 1.Keep it in separate bins
STORAGE AREA TO SURYA Works
ENGINEERING WORKS
1. Total Thickness,
SURFACE GRINDING-2 1.Distance variation Grinding Machine Feed, Speed, Depth Of Cut, Coolant oil.
90 ISC - II Magnetic table 2. Flatness,
( DATUM "E" FACE - SIDE ) 2.Thickness variation ( M/C No : ISC-II-SGM-01 )
3. Parallelism.
1.M14x1.5
2.ES / CDS-068-Port
3.4.00MM Drill
1. Tools wear in edge,
4.M8X1.25
( DATUM "E" OPPOSITE FACE - 2. Incorrect tools,
5.12.00mm Drill
SIDE ) 3. Hardness of casting, Horizontal Machining Center
6.9/16-18 UNF Feed, Speed, Depth Of Cut, Coolant oil.
100 SPOT FACING, PORT 4. Tools Blend, ISC - II ( M/C No : ISC-II-MAZAK-HMC- ISC-MS-HIC-722
7. 1 5/16-12UN
FORMING, DRILLING, TAPPING 5. Improper clamping, 03 )
8. OSV PER 155M5833
& CHAMFERING 6. Projection in rest &
9. M8X1.0
clamp area
10.7/16-20UNF
11.1 5/18-12 UN
12.6.00MM Drill
1.18.00MM Drill
2.20.00MM Drill
1. Tools wear in edge,
3. M10X1.5-6H
2. Incorrect tools,
( DATUM "E" FACE - SIDE ) 4. 5.00MM Drill
3. Hardness of casting, Horizontal Machining Center
SPOT FACING, PORT 5.4.00MM Drill Feed, Speed, Depth Of Cut, Coolant oil.
110 4. Tools Blend, ISC - II ( M/C No : ISC-II-MAZAK-HMC- ISC-MS-HIC-722
FORMING, DRILLING, TAPPING 6.12.00MM Drill
5. Improper clamping, 03 )
& CHAMFERING 7.8.75 Reamer
6. Projection in rest &
8.IES- 0111-8SAE
clamp area
9. 6 SAE9/16-18 UNF
10. ES-1345
Page 1 of 2
INDO SHELL CAST PRIVATE LTD Doc. No: Customer format
COIMBATORE PROCESS FLOW CHART
INDIA Rev.No / Date: 04 / 15.05.2019
PRODUCT NAME : CAT SWL INLET MACHINED Date of Origin : 20/03/2018 PFC No: PFC/07/SRD- 01
170 MILLIPORE TESTING 1.Dust particles ISC - II MC-01 NA 1.Contaminants clear As per Work Instruction
Revision Details
1 15.11.2018 Reviewed and updated Customer Drawing revision changed ( Rev No---> "B" from Rev No---> "P5" ).
2 07.03.2019 Reviewed and updated Customer Drawing revision changed ( Rev No---> "C" from Rev No---> "B" ).
3 10.04.2019 Reviewed and updated Customer Drawing revision changed ( Rev No---> "D" from Rev No---> "C" ).
4 15.05.2019 Reviewed and updated remove internal 'K' parameters. ( PFC no change )
PREPARED BY: GANESAN.O APPROVED BY : S.SELVAM ISSUED BY : S.SELVAM