DATE: 08/01/2023
Project Summary
This project aims to roll out tabletop menu tablets in two Sauce and Spoon restaurant
locations, to assist customers with quick, easy ordering options.
Project Goals
Deliverables
In-Scope:
● Improving employee satisfaction
● Measure staff’s performance
Out-of-Scope:
● Policy changes on order returns
Benefits:
● Training the staff will facilitate change and make good use of investment on
tablets
● The hardware should be integrated with existing POS system and host
software so that there is communication across systems, and it prevents new
errors
● New website will call for new customers, and customized features will allow the
restaurants to promote specific items of the menu
Costs:
● Training materials for staff – 10,000$
● Hardware and Software implementation across locations – 30,000$
● Maintenance – 5,000$
● Updated website and menu design – 5,000$
● Customization fees – 550$
Appendix:
● Deanna and Gilly want to reallocate some of payroll to hire more kitchen staff
to meet higher demand; not yet with data around how the tablets impact table
turn time and changes in revenue; Gilly doesn’t want to give up front-of-house
payroll in case they need to hire more hosts or bartenders; Alex thinks the
kitchen is going to need more staff at some point and in addition to line cooks,
they’ll need more bussers and runners. They’ve decided to measure payroll
and savings in June.
● Alex manages a location with more dinner guests so more need to increase
appetizers, Gilly manages a location with more appetizer guests so not much
need there. The PM decided to place the goal as an average of both locations,
decreasing for Gilly and increasing for Alex.
● Deanna wants to add a goal to decrease guest wait time, but to the PM this
seems redundant with the table turn time goal as if tables turn more quickly,
wait times will decrease naturally. They’ve decided to come back to this later.
● Carter wants to include a goal around improving the satisfaction of the kitchen
staff; PM is not sure how to measure it so we will need to revisit this – a
decision was made that if they can provide specific metrics, we will include it in
the project’s scope.