TESTING AND COMMISSIONING

Energypac Engineering Ltd.

33 KV bus Disconnector Switch

Customer Mirsharai Poultry Farms


Substation 33/11 KV Substation,Mirsharai,Chittagong
Location/Feeder 33 KV incomer

DS NAME PLATE DETAILS:

INSULATION RESISTANCE OF DS:

TESTING EQUIPMENT: INSULATION RESISTANCE TESTER

MAKE: KYORITSU

MODEL: 3125

Applied Voltage, Insulation Resistance in GΩ


5KV DC R -E Y-E B-E R-Y Y-B B-R
DS CLOSED 7.4 5 6.3 17 15 12

CHECKLIST FOR DS:

1. Check the erection of equipment is carried out as per the approved drawings

2. The Isolator main contacts are aligned for simultaneous


Operation of three poles & proper engagement during closing

3. Check for free movement of arms of Main Contacts


During closing & opening of Isolator

4. Main contacts are cleaned and greased

5. Check Earth connections from isolator structure to Earth mat


.
6. Check the insulators are cleaned and free from dust/dirt etc.

7. All moving parts of drive mechanism are lubricated

Tested By Witnessed By Date: