Independent Progress Monitoring Report

Inspection Date: 19/07/2023 Project Number: 1660 Project Name: FORTE

Developer Number: 1211 Developer Name: EMAAR DEVELOPMENT P.J.S.C.

Plot no: 169 Location: Burj Khalifa Trust A/C bank: DUBAI ISLAMIC BANK (PUBLIC JOINT
STOCK COMPANY)

PROJECT DESCRIPTION INSEPCTION NOTES


THE PROJECT CONSIST OF 5 BASEMENTS, WITH 5 PODIUM LEVEL, AND For Tower.1 mobilization, enabling, foundation, structure,
TWO TOWERS internal,works substantially completed. MEP, Internal finishes,
(G+72 LEVELS) TOWER 1 building envelope and external works progressing at advanced
(G+43 LEVELS). TOWER 2 stages.
For Tower.2 all building construction activities substantially
LOCATED IN BURJ HALIFA COMMUINTY completed. DCD and BCC from Dubai BPS
received on 29/12/2022. All DEWA meters installed. Snagging and
deep cleaning works progressing at site.

INSPECTION PHOTOS

RERA PROGRESS INDICATOR:

Refer to guide for more information


about the RERA Progress Indicator. Independently inspected and progress audited for RERA

Progress Status Main Contract -


Progressing