You are on page 1of 33

Estimation of Earthwork in

excavation
Tutor: Tshering Tobgyel

10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 1


Procedure to Estimate the Earthwork in excavation for
Road Construction

Roads are constructed either in the plain area or in hilly


areas. To calculate Earthwork in excavation for road, we
have to use the separate formula for plain and hilly areas.
Here I have described both types of estimation for road
construction step by step with numerical examples.

10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 2


A) Estimate the Earthwork in excavation
for Road Construction in Plain Area
• Volume of earthwork
• It is measured in cubic meters without any allowance for
an increase in bulk. The volume of earthwork shall be
calculated by multiplying the length, breadth, and depth
or height measured from the ground from which soil has
been taken out.

10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 3


contd
• Lead and Lift
• Normally earthwork is estimated for 30 m lead for distance
and 1.5 m lift for height or depth, and this distance of 30 m
and the height of 1.5 m are known as normal lead and lift.
• During the estimation of earthwork in the road, the volume of
earthwork may be calculated by the various methods of
mensuration out of which three methods are given below.

10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 4


Method – 1, Mid sectional area method
• Quantity = area of mid section x length
• Area of midsection = Area of rectangular portion + area of two triangular portions.

• Therefore, the Quantity of earthwork,


10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 5
contd
• = (Bd + Sd2) x L
• Where,

• d = Mean depth or height

• B = Formation width

• S = Side Slope

10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 6


The quantity of earthwork may be calculated
in a tabular form as below,

10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 7


Method-2: Mean Sectional Area Method
• Quantity = Mid Sectional area x Length

• In this method, it is not necessary to calculate mean depth but, we should calculate the mean area
after calculating the area of each station.

• The quantity of earthwork may be calculated in the tabular form as given below.

10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 8


contd
• Where,

• Am = Mean sectional area

• d = Height or Depth

• B = Formation width

• S = Side Slope

10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 9


Method – 3: Prismodial formula method

• Quantity of volume = L/6 x (A1+ A2 + 4Am)

• Where,

• A1 = Cross sectional Area at one end

• A2 = Cross sectional Area of another end

• Am = mid-sectional area

10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 10


contd

10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 11


Trapezoidal Formula and Prismoidal formula methods for a
series of cross-sections.
1) Volume by trapezoidal formula

2) Volume by Prismodial formula

10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 12


Numerical example
• Q) Prepare an estimate for the portion of a road from chainage 14 to 22 from the data given
below. Draw typical cross-sections for cutting and banking. The formation width of the
proposed road is 12 m, side slopes 3/2:1 m. cutting and 2:1 in banking.

• The road formation is proposed as a uniform falling gradient 1 in 200 passing through G.L at
chainage 14 length of one chain = 30 m.

10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 13


Solution:-
• Depth of cutting and bankings are denoted by -ve and +ve signs
respectively. Depth of cutting or banking = Difference between G.L
and F.L.
• For a gradient 1 in 200 change of level per chain of 30 m = 30/200 =
0.15

10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 14


B = 12 m, S = 1.5 for cutting, S= 2 for banking
-ve depth = Cutting
+ve depth = Filling

10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 15


Here from chainage 18 to 19, there is a change from
cutting to filling.
Let the distance from 18 chainages up to the portion of
cutting = x
10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 16
X = 13.63 m, Say 14 m
Therefore length of banking portion = 30-14 = 16 m

10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 17


10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 18
B) Estimate the Earthwork in excavation for
Road Construction in hilly area
• Earthwork for hill roads having transverse slope i.e for two-level
sections where contour lines are very close to each other (as in
hilly area) transverse or cross slope cannot be neglected in
calculating earthwork.
• When these transverse and longitudinal slopes are unknown in
between two cross-sections this portion of a road is called two-
level sections. The method of estimating the volume of earthwork
for such cases has been illustrated below.

10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 19


Case:-1 Wholly in Banking or wholly in cutting
• Thus from geometry

• Where,
• s:1 = Side slope
• r:1 = Transverse Slope
• H = Height of banking or depth of cutting
• b = Half of formation width
10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 20
Case:-2
When the centerline (FG) is in the cutting portion
(figure: a)
• a) Partly in Banking and Partly in cutting
• Area of ABE = Area of banking

10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 21


Case:-2 contd
• a) Partly in Banking and Partly in cutting
• Area of EDC = Area of cutting

10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 22


b) When center line (FG) is in banking portion
(figure:b)
• Area of ABE = Area of Banking

10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 23


b) When center line (FG) is in banking portion
(figure:b)-contd
• Area of EDC = Area of Cutting

10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 24


b) When center line (FG) is in banking portion
(figure:b)
• Where,
• H = Center depth of cutting or banking
• S:1 = Side slope of banking
• P:1 = Side slope of Cutting
• b = Half of formation width
• r:1 =Transverse Slope

10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 25


The amount of earthwork can be calculated by three methods
which are explained in E/w in plain area. The methods are given
below,
1. Mid sectional Formula
2. Average end area of mean sectional formula
3. Prismoidal Formula

10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 26


Numerical Example
• Q) Calculate the earthwork for or portion of hill road
from the following data.
Chainage 0 30 60 90
RL of Ground Level 104 m 105 m 106 m 107 m
Formation Level 105 m 105.5 m 106.0m 106.5 m
Transverse Slope 20:1 15:1 12:1 10:1

Formation width = 10 m, side slope in cutting = 1:1


Side slope in banking = 2:1
10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 27
Solution:-
• First, we find the depth of cutting or banking, which are
given below:

RL of GL Formation
Chainage Cross Slope Depth (m)
(m) level (m)
0m 104 105 20:1 1
30 m 105 105 15:1 0.5
60 m 106 106 12:1 0
90 m 107 106.5 10:1 -0.5
10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 28
At chainage 0 m
•s=2
•b=5m
•H=1m
• r = 20

10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 29


At chainage 30 m
•s=2
•b=5m
• H = 0.5 m
• r = 15

10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 30


At chainage 60 m

•s=2
•b=5
•H=0
• r = 12

10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 31


At chainage 90 m

•s=1
•b=5
• H =0.5
• r = 10

10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 32


Hence, earthwork in Cutting = 117.33 m3
Earthwork in filling = 395.82 m3

10/17/2022 Tutor: tsheringtobgyel.cst@rub.edu.bt 33

You might also like