MST

Project Properties
Calendar
Calendar Name MST Calendar
Working Days 6 day excluding holidays
Working hours 8 hours
Time Period 8am-5pm

CALENDAR EXCEPTIONS

Date Holiday
01-Jan-23 New Year's Day

Chinese New Year

25-Feb-23 EDSA Revolution Anniversary

09-Apr-22 Day of Valor

Maundy Thursday

Good Friday

Black Saturday

01-May-22 Labor Day

03-May-22 Eidul Fitr

12-Jun-22 Independence Day

09-Jul-22 Eidul Adha

21-Aug-22 Ninoy Aquino Day

29-Aug-22 National Heroes Day

01-Nov-22 All Saints' Day

30-Nov-22 Bonifacio Day

08-Dec-22 Immaculate Conception

25-Dec-22 Christmas Day


30-Dec-22 Rizal Day

m
t
w
th
f
sat
MST ACTIVITY SHEET SAMP

Date Holiday
New Year's Day

Chinese New Year

EDSA Revolution Anniversary

Day of Valor

Maundy Thursday

Good Friday

Black Saturday

Labor Day

YEAR Eidul Fitr

2023 Independence Day

Eidul Adha

Ninoy Aquino Day

National Heroes Day

All Saints' Day

Bonifacio Day

Immaculate Conception

Christmas Day
Rizal Day
ET SAMPLE
MST ACTIVITY SHE
WBS
1 PreConstruction
1.2 General Requirements
2 Construction
2.1 Earthworks
2.2 Civil/Structural Works
2.2.1 Substructure
2.2.2 Superstructure
2.3 Archi Works
2.4 MEPF Works
3 Post Construction

OVERVIEW
TABLE WBS ABC PROJECT DURATION PREDECESSORS
1 1 PreConstruction
2 1.1 General Requirements
3 1.1.1 Downpayment 0d
4 1.1.2 Permit Acquisition 0d
5 1.1.3 Mobilization 5d 4,3
6 1.1.4 Survey Works 2d 5
7 2 Construction
8 2.1 Earthworks
9 2.1.1 Clearing & Grubbing 2d 6
10 2.1.2 Excavation 3d 9
11 2.1.3 Hauling & Disposal 1d 10
12 2.1.4 Backfilling & Compaction 3d 11,17
13 2.2 Civil Works
14 2.2.1 Substructure
15 2.2.1.1 Installation of Rebar 4d 10
16 2.2.1.2 Installation of Formworks 3d 15
17 2.2.1.3 Concrete Pouring 1d 16
18 2.2.2 Superstructure
19 2.2.2.1 Installation of Rebar 4d 12
20 2.2.2.2 Installation of Formworks 3d 19
21 2.2.2.3 Concrete Pouring 1d 20
22 2.3 Archi Works
23 2.3.1 Wet Works 7d 21
24 2.3.2 Dry Works 8d 23
25 2.3.3 Specialty/ Finishing Works 7d 24
26 2.4 MEPF Works
27 2.4.1 Installation of 1st Fix 2d 15SS
28 2.4.2 Installation of 2nd Fix 3d 27,23
29 2.4.3 Installation of 3rd Fix 2d 28,25FF
30 3 Post Construction
31 3.1 Punchlisting & Cose Out 5d 25,29