Location: L1 - B1 & B2
Nonconformance Description/Mô tả Occurrence day: Ngày xảy ra sự cố
It was notice on 12/10/15, the structural steel kingpost at B2, column line coordinates X7-Y7 and the cast-in-place
concrete column at B1, column line coordinates X7-Y7 are not in vertical axes/alignment whereas the column appear
to off-set by 10-15+ cm. Delta must submit immediately their remedial works method statement for MVN approval
Consultant
Closed
Consultant
Closed as noted
Rejected
Note:/Ghi chú
1. Any approval does not relieve the Contractor from it's contractual responsibilities and obligations./ Dù có bất cứ phê duyệt nào cũng
không làm giảm bớt trách nhiệm và nghĩa vụ của Nhà thầu theo hợp đồng.
Note
2. This is not a Variation Document. If the Contractor considers any part of this response as a Variation to its cost or time of performance, it is
required to notify the Project Manager in accoradance with the Contract.
Đây không phải là hồ sơ phát sinh. Nếu Nhà thầu nhận thấy bất cứ hạng mục nào là vấn đề phát sinh về thời gian hoặc chi phí,
hãy thông báo cho Giám đốc dự án theo hợp đồng.
QA/QC Non Conformance Report (NCR)/ Báo cáo không phù hợp
Project:/Dự án VINHOME CENTRAL PARK
Contract No:/Số hợp đồng Ref No. VHCP-C4-MV-ME-NCR-0000 Rev 0
Client:/Chủ đầu tư: PMU.05 Date: 14/10/2015
QA/QC Manager:/Giám đốc dự án R. DISMUS Subject: Structural steel kingpost (B2) and cast-in-place column (B1) out of
alignment
Contractor:/Nhà thầu DELTA
Location: L1 - B1 & B2
Nonconformance Description/Mô tả Occurrence day: Ngày xảy ra sự cố
It was notice on 12/10/15, the structural steel kingpost at B2, column line coordinates X8-Y7 and the cast-in-place
concrete column at B1, column line coordinates X8-Y7 are not in vertical axes/alignment whereas the column appear
to off-set by 10-15+ cm. Delta must submit immediately their remedial works method statement for MVN approval
Consultant
Closed
Consultant
Closed as noted
Rejected
Note:/Ghi chú
1. Any approval does not relieve the Contractor from it's contractual responsibilities and obligations./ Dù có bất cứ phê duyệt nào cũng
không làm giảm bớt trách nhiệm và nghĩa vụ của Nhà thầu theo hợp đồng.
Note
2. This is not a Variation Document. If the Contractor considers any part of this response as a Variation to its cost or time of performance, it is
required to notify the Project Manager in accoradance with the Contract.
Đây không phải là hồ sơ phát sinh. Nếu Nhà thầu nhận thấy bất cứ hạng mục nào là vấn đề phát sinh về thời gian hoặc chi phí,
hãy thông báo cho Giám đốc dự án theo hợp đồng.
QA/QC Non Conformance Report (NCR)/ Báo cáo không phù hợp
Project:/Dự án VINHOME CENTRAL PARK
Contract No:/Số hợp đồng Ref No. VHCP-C4-MV-ME-NCR-0000 Rev 0
Client:/Chủ đầu tư: PMU.05 Date: 14/10/2015
QA/QC Manager:/Giám đốc dự án R. DISMUS Subject: Structural steel kingpost (B2) and cast-in-place column (B1) out of
alignment
Contractor:/Nhà thầu DELTA
Location: L1 - B1 & B2
Nonconformance Description/Mô tả Occurrence day: Ngày xảy ra sự cố
It was notice on 12/10/15, the structural steel kingpost at B2, column line coordinates X14-Y3 and the cast-in-place
concrete column at B1, column line coordinates X14-Y3 are not in vertical axes/alignment whereas the column
appear to off-set by 10-15+ cm. Delta must submit immediately their remedial works method statement for MVN
Consultant
Closed
Consultant
Closed as noted
Rejected
Note:/Ghi chú
1. Any approval does not relieve the Contractor from it's contractual responsibilities and obligations./ Dù có bất cứ phê duyệt nào cũng
không làm giảm bớt trách nhiệm và nghĩa vụ của Nhà thầu theo hợp đồng.
Note
2. This is not a Variation Document. If the Contractor considers any part of this response as a Variation to its cost or time of performance, it is
required to notify the Project Manager in accoradance with the Contract.
Đây không phải là hồ sơ phát sinh. Nếu Nhà thầu nhận thấy bất cứ hạng mục nào là vấn đề phát sinh về thời gian hoặc chi phí,
hãy thông báo cho Giám đốc dự án theo hợp đồng.
QA/QC Non Conformance Report (NCR)/ Báo cáo không phù hợp
Project:/Dự án VINHOME CENTRAL PARK
Contract No:/Số hợp đồng Ref No. VHCP-C4-MV-ME-NCR-0000 Rev 0
Client:/Chủ đầu tư: PMU.05 Date: 14/10/2015
QA/QC Manager:/Giám đốc dự án R. DISMUS Subject: Structural steel kingpost (B2) and cast-in-place column (B1) out of
alignment
Contractor:/Nhà thầu DELTA
Closed
Consultant
Closed as noted
Rejected
Note:/Ghi chú
1. Any approval does not relieve the Contractor from it's contractual responsibilities and obligations./ Dù có bất cứ phê duyệt nào cũng
không làm giảm bớt trách nhiệm và nghĩa vụ của Nhà thầu theo hợp đồng.
Note
2. This is not a Variation Document. If the Contractor considers any part of this response as a Variation to its cost or time of performance, it is
required to notify the Project Manager in accoradance with the Contract.
Đây không phải là hồ sơ phát sinh. Nếu Nhà thầu nhận thấy bất cứ hạng mục nào là vấn đề phát sinh về thời gian hoặc chi phí,
hãy thông báo cho Giám đốc dự án theo hợp đồng.
QA/QC Non Conformance Report (NCR)/ Báo cáo không phù hợp
Project:/Dự án VINHOME CENTRAL PARK
Contract No:/Số hợp đồng Ref No. VHCP-C4-MV-ME-NCR-0000 Rev 0
Client:/Chủ đầu tư: PMU.05 Date:
QA/QC Manager:/Giám đốc dự án R. DISMUS Subject:
Contractor:/Nhà thầu
Location:
Nonconformance Description/Mô tả Occurrence day: Ngày xảy ra sự cố
Consultant
Closed
Consultant
Closed as noted
Rejected
Note:/Ghi chú
1. Any approval does not relieve the Contractor from it's contractual responsibilities and obligations./ Dù có bất cứ phê duyệt nào cũng
không làm giảm bớt trách nhiệm và nghĩa vụ của Nhà thầu theo hợp đồng.
Note
2. This is not a Variation Document. If the Contractor considers any part of this response as a Variation to its cost or time of performance, it is
required to notify the Project Manager in accoradance with the Contract.
Đây không phải là hồ sơ phát sinh. Nếu Nhà thầu nhận thấy bất cứ hạng mục nào là vấn đề phát sinh về thời gian hoặc chi phí, hãy thông
báo cho Giám đốc dự án theo hợp đồng.