TT Lot, Phu Tan Industrial Park, Hoa Phu Ward, Thu Dau Mot City, Binh Duong province, Vietnam
DESIGN, CONSTRUCTION, COMMISSION AND MAINTENANCE FOR SEWAGE TREATMENT PLANT
Công ty Cổ phần Đầu tư Xây dựng Công nghiệp Nam Kim
Lô TT, Khu công nghiệp Phú Tân, Phường Hoà Phú, Thành phố Thủ Dầu Một, Tỉnh Bình Dương, Việt Nam
Thiết kế, Thi công, Đưa và vận hành và Bảo trì cho Nhà Máy Xử Lý Nước Thải
FINAL SUMMARY
BẢNG TỔNG HỢP
FINAL SUMMARY
BẢNG TỔNG HỢP
Already be included
Bill 04 OTHER SYSTEM / EQUIPMENT (PROPOSED BY TEND - in Bill03-Division01
(B3D1)
CÁC HỆ THỐNG / THIẾT BỊ KHÁC (ĐỀ XUẤT BỞI NHÀ THẦU)
Name: …………………………………………
Date: ………………………………….
Note: ………………………………….
NAM KIM INDUSTRIAL INVESTMENT & CONSTRUCTION JSC
TT Lot, Phu Tan Industrial Park, Hoa Phu Ward, Thu Dau Mot City, Binh Duong province, Vietnam
DESIGN, CONSTRUCTION, COMMISSION AND MAINTENANCE FOR SEWAGE TREATMENT PLANT
Công ty Cổ phần Đầu tư Xây dựng Công nghiệp Nam Kim
Lô TT, Khu công nghiệp Phú Tân, Phường Hoà Phú, Thành phố Thủ Dầu Một, Tỉnh Bình Dương, Việt Nam
Thiết kế, Thi công, Đưa và vận hành và Bảo trì cho Nhà Máy Xử Lý Nước Thải
GENERALLY
INSURANCES
CONTRACTOR’S EQUIPMENT
OVERTIME
The Contractor shall include in his price for any costs ITEM
associated with overtime working necessary to complete
the Works the Time for Completion
REMOVAL OF RUBBISH
The Contractor shall arrange and pay all fees for ITEM
disposing of all rubbish, unwanted building debris, earth,
rubble, chemicals, noxious or polluting matter, etc. from
the site both at regular intervals and on completion.
TEMPORARY HOARDINGS
Contractor to provide temporary fencing to protect his Item
own works.
STORAGES
Provide and maintain any necessary watertight ITEM
temporary storage for Contractor’s tools, plant etc. Alter,
shift and adapt from time to time as necessary.
Storages used for the storage of cement, lime and other NOTE
perishable materials shall have raised floors.
Total Carried to Collection -
All petroleum, explosives and flammable materials shall NOTE
be stored in fire-proof buildings and precautions taken
with regard to siting and fire risks.
AS-BUILT DRAWINGS
As-built drawings shall be prepared and presented in a ITEM
format approved by the Employer.
1.1 Provide New Letters For Signage Board lot 1 35,555,556 35,555,556
1.4 Remove The Peeled Off Painting Layer And Repaint The lot 1 5,666,667 5,666,667
1.7 Clean The Road And Road Kerb lot 1 31,666,667 31,666,667
1.8 Paint The Road Kerb In Front Of The Entrance Gate lot 1 3,000,000 3,000,000
1.9 Replace The Existing Manhole Cover At The Entrance lot 1 3,000,000 3,000,000
1.10 Repaint The Steel Frame Around The Manhole lot 1 333,333 333,333
1.11 Repaint The Existing Front Fencing & Replace The Steel lot 1 126,783,333 126,783,333
1.13 Build New Side & Rear Fencing lot 1 1,452,000,000 1,452,000,000
1.14 Replace And Repair The Damaged Internal Road lot 1 83,106,493 83,106,493
1.15 Engage Third Party To Check And Issue Certificate For Th lot 1 7,777,778 7,777,778
1.17 Provide Cctv (30-Day Recorder) On The Boundary lot 1 104,000,000 104,000,000
1.1 Repaint The Main Door And Windows lot 1 4,388,889 4,388,889
1.4 Replace The Toilet Floor & Wall Tiles lot 1 7,733,333 7,733,333
1.5 Replace Sanitary Wares In The Toilet (Refer To Design Gu lot 1 13,144,444 13,144,444
1.6 Replace The Neon Light & All Switches (Refer To Design lot 1 4,266,667 4,266,667
1.7 Replace The Air Conditioner (Refer To Design Guideline) lot 1 16,055,556 16,055,556
1.8 Replace The Fan In The Office (Refer To Design Guideli lot 1 12,888,889 12,888,889
BILL 02 - BUILDER WORKS Division 03 - External Office building & Other room works
CÁC CÔNG TÁC XÂY DỰNG Các công tác cho khu vực ngoài văn phòng & các phòng khác
1.1 Replace New Tiles 300X600Mm For The Walkway lot 1 22,719,444 22,719,444
1.3 Replace The Lamps On The Ceiling Of Each Room lot 1 4,500,000 4,500,000
1.5 Repair The Crack On The Storage & Mud Treatment Roo lot 1 2,166,667 2,166,667
Repaint The External Wall And Manhole Covers lot 1 71,333,333 71,333,333
1.2 Paint The Internal Wall (1M Depth From The Top) lot 1 51,733,333 51,733,333
1.3 Remove 0.5M Top Of The Landscape R.C Tank lot 1 17,777,778 17,777,778
1.4 Painting For Internal Wall & Top Of Antiseptic Tank lot 1 91,688,889 91,688,889
(*) Noted: This above price is not included water proof
work for existing tanks.
1.7 Provide New Window 1M X 2M With Safety Steel Bars lot 1 11,194,444 11,194,444
1.12 Repaint The Meterbox On The Electric Pole lot 1 444,444 444,444
II Equipment 4,132,584,667
VI Piping 371,143,333
9.3 Labor for remove electrical items of existing system lot 1 31,333,333 31,333,333
Maker: Organo Vietnam
Origin: Vietnam
1.1 Transmitter of COD, TSS, pH, Temperature, Ammonium nos 1 82,476,000 82,476,000
- Model: Liquiline CM444
- Maker: Endress + Hauser
- Origin: Germany
- Specification:
+ 9m high steel post
+ Pillar base (cement, sand, stone, steel, foundation
construction personnel)
+ Lightning needle
+ Lightning surge protective device
+ Copper cable
+ Bare copper cable
+ Lightning drainage well compartment
+ Ground piles
Already be included
1 Contractor to Design & Build nos 1 - in Bill03-Division01
(B3D1)
to breakdown based on the technical proposal
Already be included
1 Water leveling measurement system nos - in Bill03-Division01
(B3D1)
Already be included
2 Mechanical leveling measurement system nos - in Bill03-Division01
(B3D1)
Already be included
3 pH measurement system nos - in Bill03-Division01
(B3D1)
Already be included
4 DO measurement system nos - in Bill03-Division01
(B3D1)
Already be included
5 ORP measurement system nos - in Bill03-Division01
(B3D1)
Already be included
6 Screen to display pH, DO, ORP nos - in Bill03-Division01
(B3D1)
Already be included
7 CB box nos - in Bill03-Division01
(B3D1)
Other
Already be included
4 Training for operation and handover lot in Bill03-Division01
(B3D1)
Already be included
5 Bacteria seeding for starting up the system lot in Bill03-Division01
(B3D1)
Already be included
7 Testing & Comissioning lot in Bill03-Division01
(B3D1)