TOILET BLOCK

MEASUREMENT SHEET
Sl. No. Item Unit No. L B D Qty
Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees
girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and
stacking of serviceable material to be used or aunctioned, including removal and disposal of top organic soil
1
not exceeding 150 mm in thickness.
(i) By manual means
(a) In area of light jungle
PWD 2021-22, Vol 3, I. 2.4, Pg. 7
1 2.00 2.00 4.00
Sqm Total = 4.00
Ha Total = 0.00

Earthwork excavation by means for drains, canals, wate weir, draft, approach channels, key trench, foundation
of bridge and such similar works, as per drawing and technical specifications, including setting out, shoring,
strutting, barricading, caution lights, excavated surface levelled and sides neatly dressed disposing off or
2
levelling the excavated stuff or sorting and stacking the selected stuff for reuse in radius of 50m and lift 1.5 m
including cost of labour, tools, usage and other appurtenances required to the complete the work.
Depth exceeding 3m , but not exceeding 4.5m

PWD 2021-22, Vol 1, I. 1.5.1, Pg. 6


Cum 1 2.00 0.67 0.67 0.90
For chambers 2 1.10 1.10 0.80 1.94
For Brick mansonry 1 8.00 0.70 5.60
For pipe laying (external) 1 6.06 0.60 0.60 2.18
Total = 10.62

Providing and laying in position plain cement concrete for levelling course for all works on foundation.The
granite/tarp/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine
mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead
3 & lifts, cost of all materials of quality, labour, usage charges of machineries, curing, all the other
appurtenances required the work as per technical specifications. ( The cost of steel reinforcement & formwork
shall be paid separately)
Mix 1:3:6 (M10) Using 40 mm nominal size graded crushed coarse aggregates

PWD 2021-22, Vol 1, I. 2.1.3, Pg. 15


For Brick mansonry Cum 1 8.00 0.70 0.15 0.84
For chambers 2 1.10 1.10 0.15 0.36
For water proofing purpose 1 4.00 1.82 0.12 0.87
For pipe laying (external) 1 6.06 0.60 0.15 0.55
Total = 2.62

Providing brick work with common burnt clay modular bricks of class desingation 3.5 in foundation and plinth
4 in cement mortar 1:4 (1 cement: 4 Coarse sand) including cost of all materials, labour, scaffolding and usage
charges of machinery and other incidental charges complete as per the direction of engineer in charge of work

PWD 2021-22, Vol 2, I. 6.4, Pg. 13


Cum 4 2.00 2.00 0.20 3.20
Total = 3.20
Providing and laying vitrified floor tiles in different sizes (thickness to be specified by the manufacturer) with
water aborbtion less than 0.08% and confirming to IS: 15622, of approved make, in all colors and shades, laid
5 on 20mm thick cement mortar 1:4 (1 cement:4 Coarse sand), joining with grey cement slurry @ 3.3Kg/m2
including grouting the joints with white cement and matching pigments etc., complete,
i) Size of tile 500 x 500 mm
PWD 2021-22, Vol 2, I. 9.12.1, Pg. 60
Flooring
For W/c Sqm 1 2.00 2.00 4.00
Total = 4.00
Providing skirting, dadoing, rises of steps with colour galzed tiles 6mm thick on 10mm thick cement plaster 1:3
6 and joined with white cement slurry over existing rough plaster surface using plaster surface using glazzed
tiles of approved make and size including cost of materials, albour, complete as per specifications
PWD 2021-22, Vol 2, I. 9.39, Pg. 65
Dadooing
For W/c Sqm 1 2.00 2.00 4.00
Total = 4.00
Wall painting with ayrylic emulsion paint of approved brand and manufacture to give an even shade: Two
coats on new work after throroughly brooming the surface to remove dirt, duct, mortar drops and foreign
8
matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per
specifcation and as per directions of Engineer-in-charge.
PWD 2021-22, Vol 2, I. 8.39, Pg. 48
Sqm
Exterior paint for toilet block 2 2.00 2.00 8.00
Paint for interior wall 4 2.00 2.00 16.00
Ceiling 2 2.00 2.00 8.00
Total = 32.00
Painting with oil type wood preservative of approved breand and manufacture: New work (two coat) to give at
even shade including preparing the surface after thoroughly cleaning oil, grease, dirt, and foreign matter, sand
9
papering and knotting, cost of materials, labour complete as per specification and as per directions of
Engineer-in-charge
PWD 2021-22, Vol 2, I. 8.38, Pg. 48
Sqm 1 2.13 1.06 2.26
Total = 2.26
10 White viteous china orissa pattern W.C. pan of size 580x440 m integral type foot rests.
PWD 2021-22, Vol 2, I. 14.1.1, Pg. 123
Each 1 1.00
Total = 1.00
Providing and fising factory made ISI marked steel glazed doors, windows and ventilators, side/top/center
hung, with beading and all members such as F7D, F4B, K11 and K12B etc., complete of standrad rolled steel
sections, joints mitred and flash butt welded and sash bars tenoed and riveted, including providing and fising
of henges, pivots, including priming coat of approved steel primer, but excluding the cost of other fittings,
11
complete all as per approved design, (sectional weight of only steel members shall be measured for payment).
Fixing with carbo steel galvanised dash fastener of required dia and size (to be paid for separately) including
cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of
the engineer-in-charge.
PWD 2021-22, Vol 2, I. 11.11.2, Pg. 78
Sqm 1 0.60 0.90 0.54
Total = 0.54

Refilling avaliable earth around trench/pipelines, cables in layers not exceeding 20cms in depth, compacting
12 each deposited layer by ramming after watering with lead upto 50m, lift upto 1.5m. Including cost of all labour
complete as per specifications

PWD 2021-22, Vol 1, I. 1.10, Pg. 7


Cum 1.64
Total = 1.64
Providing Thermo-Mechanically Treated bars of grade Fe-550 Steel reinforcement for R.C.C. work including
straightening,cutting, bending, placing in position, binding and anchoring to adjacent
13 members whereever necessary complete as per Design including cost of material, labour, usage charges
complete as per specifications. (The
laps and wastages shall not be measured separately)
11.32/VOL2 (2nd quarter Issue rate dt7.7.2022),Page no.84
Footing
Main bar 16 mm Φ
16 mm Φ 1.58 kg /rmt 4 17 2.30 156.40
156.40 1.58 247.11
Main bar 16 mm Φ
16 mm Φ 1.58 kg /rmt 4 17 2.30 156.40
156.40 1.58 247.11
Columns
Main bar 16 mm Φ
16 mm Φ 1.58 kg /rmt 4 6 3.60 86.40
86.40 1.58 136.51
Ties 8 mm Φ
8 mm Φ 0.395 kg/rmt 4 27 1.36 149.06
149.06 0.3950 58.88
Beams
Main bar 16 mm Φ
16 mm Φ 1.58 kg /rmt 4 4 2.30 36.80
36.80 1.58 58.14
Stirrups 8 mm Φ
8 mm Φ 0.395 kg/rmt 4 27 1.36 149.06
149.06 0.3950 58.88
Slabs
Main bar 16 mm Φ
12 mm Φ 1.58 kg /rmt 1 17 3.10 52.70
52.70 0.89 46.90
Distribution bars 8 mm Φ
8 mm Φ 0.395 kg/rmt 1 17 3.10 52.70
52.70 0.3950 20.82
kg 874.35
ton 0.87
BBS for Retaining wall
Shape Cut Spacing Total Total
c/c
Dia Shape Bend A B C D length length length Set no. of weight
(mm)
(mm) (mm) (mm) bars (kg)
A

16 mm
Main bar B 256 100 4375 1800 230 6505 6249 34000 150 1 228 2279.64
Stem D
C

10 mm A
Dist. bar 33850 33850 33850 6175 120 1 53 1112.31
Stem

16 mm
Main bar B
128 150 4352 1465 5966.7956 5838.796 34000 150 1 228 2129.99
Stem
Earth side D
C
BBS for Retaining wall
Shape Cut Spacing Total Total
c/c
Dia Shape Bend A B C D length length length Set no. of weight
(mm)
(mm) (mm) (mm) bars (kg)

10 mm A
Dist. bar 33850 33850 33850 5816.796 120 1 50 1049.35
Stem

B
16 mm A C
Main bar 128 230 2890 230 3350 3222 34000 150 1 228 1175.39
Raft

10 mm A
Dist. bar 33850 33850 33850 2890 120 1 26 545.66
Raft

Total = 8292.34
ABSTRACT
Sl. No. Item Unit Qty Rate (Rs) Amount (Rs)

Clearing and grubbing road land


including uprooting rank vegetation,
grass, bushes, shrubs, saplings and
trees girth up to 300 mm, removal of
stumps of trees cut earlier and
disposal of unserviceable materials
1 and stacking of serviceable material Ha 0.00 176,715.00 70.69
to be used or aunctioned, including
removal and disposal of top organic
soil not exceeding 150 mm in
thickness.
(i) By manual means
(a) In area of light jungle

PWD 2021-22, Vol 3, I. 2.4, Pg. 7

Earthwork excavation by means for


drains, canals, wate weir, draft,
approach channels, key trench,
foundation of bridge and such similar
works, as per drawing and technical
specifications, including setting out,
shoring, strutting, barricading,
caution lights, excavated surface
levelled and sides neatly dressed
2 Cum 10.62 474.60 5,038.17
disposing off or levelling the
excavated stuff or sorting and
stacking the selected stuff for reuse
in radius of 50m and lift 1.5 m
including cost of labour, tools, usage
and other appurtenances required to
the complete the work.
Depth exceeding 3m , but not
exceeding 4.5m

PWD 2021-22, Vol 1, I. 1.5.1, Pg. 6


Providing and laying in position plain
cement concrete for levelling course
for all works on foundation.The
granite/tarp/basalt crushed graded
coarse aggregates and fine
aggregates as per relevant IS Codes
machine mixed, laid in layers not
exceeding 150 mm thickness, well
compacted using plate vibrators,
including all lead & lifts, cost of all
3 Cum 2.62 6,039.60 15,836.16
materials of quality, labour, usage
charges of machineries, curing, all
the other appurtenances required
the work as per technical
specifications. ( The cost of steel
reinforcement & formwork shall be
paid separately)
Mix 1:3:6 (M10) Using 40 mm
nominal size graded crushed coarse
aggregates

PWD 2021-22, Vol 1, I. 2.1.3, Pg. 15

Providing brick work with common


burnt clay modular bricks of class
desingation 3.5 in foundation and
plinth in cement mortar 1:4 (1
cement: 4 Coarse sand) including
4 cost of all materials, labour, Cum 3.20 7,837.20 25,079.04
scaffolding and usage charges of
machinery and other incidental
charges complete as per the
direction of engineer in charge of
work
PWD 2021-22, Vol 2, I. 6.4, Pg. 13

Providing and laying vitrified floor


tiles in different sizes (thickness to
be specified by the manufacturer)
with water aborbtion less than
0.08% and confirming to IS: 15622,
of approved make, in all colors and
shades, laid on 20mm thick cement
5 Sqm 4.00 1,074.15 4,296.60
mortar 1:4 (1 cement:4 Coarse
sand), joining with grey cement
slurry @ 3.3Kg/m2 including
grouting the joints with white
cement and matching pigments etc.,
complete,
i) Size of tile 500 x 500 mm

PWD 2021-22, Vol 2, I. 9.12.1, Pg.


60
Providing skirting, dadoing, rises of
steps with colour galzed tiles 6mm
thick on 10mm thick cement plaster
1:3 and joined with white cement
slurry over existing rough plaster
6 Sqm 4.00 2,178.75 8,715.00
surface using plaster surface using
glazzed tiles of approved make and
size including cost of materials,
albour, complete as per
specifications

PWD 2021-22, Vol 2, I. 9.39, Pg. 65

Wall painting with ayrylic emulsion


paint of approved brand and
manufacture to give an even shade:
Two coats on new work after
throroughly brooming the surface to
8 remove dirt, duct, mortar drops and Sqm 32.00 95.00 3,040.00
foreign matter including preparing
the surface even and sand paper
smooth, cost of materials, labour
complete as per specifcation and as
per directions of Engineer-in-charge.

PWD 2021-22, Vol 2, I. 8.39, Pg. 48

Painting with oil type wood


preservative of approved breand and
manufacture: New work (two coat)
to give at even shade including
preparing the surface after
9 thoroughly cleaning oil, grease, dirt, Sqm 2.26 35.70 80.60
and foreign matter, sand papering
and knotting, cost of materials,
labour complete as per specification
and as per directions of Engineer-in-
charge

PWD 2021-22, Vol 2, I. 8.38, Pg. 48

White viteous china orissa pattern


10 W.C. pan of size 580x440 m integral Each 1.00 4,458.30 4,458.30
type foot rests.
PWD 2021-22, Vol 2, I. 14.1.1, Pg.
123
Providing and fising factory made ISI
marked steel glazed doors, windows
and ventilators, side/top/center
hung, with beading and all members
such as F7D, F4B, K11 and K12B
etc., complete of standrad rolled
steel sections, joints mitred and flash
butt welded and sash bars tenoed
and riveted, including providing and
fising of henges, pivots, including
priming coat of approved steel
11 primer, but excluding the cost of Sqm 0.54 91.35 49.33
other fittings, complete all as per
approved design, (sectional weight
of only steel members shall be
measured for payment). Fixing with
carbo steel galvanised dash fastener
of required dia and size (to be paid
for separately) including cost of
materials, labour, usage charges of
machinery complete as per
specifications and as per directions
of the engineer-in-charge.

PWD 2021-22, Vol 2, I. 11.11.2, Pg.


78
Refilling avaliable earth around
trench/pipelines, cables in layers not
exceeding 20cms in depth,
compacting each deposited layer by
12 Cum 1.64 128.10 209.62
ramming after watering with lead
upto 50m, lift upto 1.5m. Including
cost of all labour complete as per
specifications
PWD 2021-22, Vol 1, I. 1.10, Pg. 7

Providing Thermo-Mechanically
Treated bars of grade Fe-550 Steel
reinforcement for R.C.C. work
including straightening,cutting,
bending, placing in position, binding
and anchoring to adjacent
13 members whereever necessary kg 0.87 60,000.00 52,461.22
complete as per Design including
cost of material, labour, usage
charges complete as per
specifications. (The
laps and wastages shall not be
measured separately)

11.32/VOL2 (2nd quarter Issue rate


dt7.7.2022),Page no.84

Total = 119,334.73
Rate Analysis

Sl.
Particulars Unit Rate(Rs.)
No.
Clearing and grubbing road land including uprooting rank
vegetation, grass, bushes, shrubs, saplings and trees girth
up to 300 mm, removal of stumps of trees cut earlier and
disposal of unserviceable materials and stacking of
1 serviceable material to be used or aunctioned, including Ha 168,300.00
removal and disposal of top organic soil not exceeding 150
mm in thickness.
(i) By manual means
(a) In area of light jungle
PWD 2021-22, Vol 3, I. 2.4, Pg. 7
Area weightage @ 5% 8,415.00
Total = 176,715.00
Earthwork excavation by means for drains, canals, wate
weir, draft, approach channels, key trench, foundation of
bridge and such similar works, as per drawing and
technical specifications, including setting out, shoring,
strutting, barricading, caution lights, excavated surface
2 levelled and sides neatly dressed disposing off or levelling Cum 452.00
the excavated stuff or sorting and stacking the selected
stuff for reuse in radius of 50m and lift 1.5 m including
cost of labour, tools, usage and other appurtenances
required to the complete the work.
Depth exceeding 3m , but not exceeding 4.5m
PWD 2021-22, Vol 1, I. 1.5.1, Pg. 6
Area weightage @ 5% 22.60
Total = 474.60
Providing and laying in position plain cement concrete for
levelling course for all works on foundation.The
granite/tarp/basalt crushed graded coarse aggregates and
fine aggregates as per relevant IS Codes machine mixed,
laid in layers not exceeding 150 mm thickness, well
compacted using plate vibrators, including all lead & lifts,
3 Cum 5,752.00
cost of all materials of quality, labour, usage charges of
machineries, curing, all the other appurtenances required
the work as per technical specifications. ( The cost of steel
reinforcement & formwork shall be paid separately)
Mix 1:3:6 (M10) Using 40 mm nominal size graded
crushed coarse aggregates
PWD 2021-22, Vol 1, I. 2.1.3, Pg. 15
Area weightage @ 5% 287.60
Total = 6,039.60
Providing brick work with common burnt clay modular
bricks of class desingation 3.5 in foundation and plinth in
cement mortar 1:4 (1 cement: 4 Coarse sand) including
4 Cum 7,464.00
cost of all materials, labour, scaffolding and usage charges
of machinery and other incidental charges complete as per
the direction of engineer in charge of work
PWD 2021-22, Vol 2, I. 6.4, Pg. 13
Area weightage @ 5% 373.20
Total = 7,837.20
Providing and laying vitrified floor tiles in different sizes
(thickness to be specified by the manufacturer) with water
aborbtion less than 0.08% and confirming to IS: 15622, of
approved make, in all colors and shades, laid on 20mm
5 thick cement mortar 1:4 (1 cement:4 Coarse sand), joining Cum 1,023.00
with grey cement slurry @ 3.3Kg/m2 including grouting
the joints with white cement and matching pigments etc.,
complete,
i) Size of tile 500 x 500 mm
PWD 2021-22, Vol 2, I. 9.12.1, Pg. 60
Area weightage @ 5% 51.15
Total = 1,074.15
Providing skirting, dadoing, rises of steps with colour
galzed tiles 6mm thick on 10mm thick cement plaster 1:3
6 Sqm 2,075.00
and joined with white cement slurry over existing rough
plaster surface using plaster surface using glazzed tiles of
approved
PWD 2021-22,make
Voland
2, I. size
9.39, including
Pg. 65 cost of materials,
albour, complete
Area weightage @ as per specifications 5% 103.75
Total = 2,178.75
Wall painting with ayrylic emulsion paint of approved
brand and manufacture to give an even shade: Two coats
on new work after throroughly brooming the surface to
8 remove dirt, duct, mortar drops and foreign matter Sqm 95.00
including preparing the surface even and sand paper
smooth, cost of materials, labour complete as per
specifcation and as per directions of Engineer-in-charge.
PWD 2021-22, Vol 2, I. 8.39, Pg. 48
Area weightage @ -
Total = 95.00
Painting with oil type wood preservative of approved
breand and manufacture: New work (two coat) to give at
even shade including preparing the surface after
9 thoroughly cleaning oil, grease, dirt, and foreign matter, #REF! 34.00
sand papering and knotting, cost of materials, labour
complete as per specification and as per directions of
Engineer-in-charge
PWD 2021-22, Vol 2, I. 8.38, Pg. 48
Area weightage @ 5% 1.70
Total = 35.70
10 White viteous china orissa pattern W.C. pan of size Each 4,246.00
580x440 m integral type foot rests.
PWD 2021-22, Vol 2, I. 14.1.1, Pg. 123
Area weightage @ 5% 212.30
Total = 4,458.30
Providing and fising factory made ISI marked steel glazed
doors, windows and ventilators, side/top/center hung, with
beading and all members such as F7D, F4B, K11 and K12B
etc., complete of standrad rolled steel sections, joints
mitred and flash butt welded and sash bars tenoed and
riveted, including providing and fising of henges, pivots,
including priming coat of approved steel primer, but
11 Sqm 87.00
excluding the cost of other fittings, complete all as per
approved design, (sectional weight of only steel members
shall be measured for payment). Fixing with carbo steel
galvanised dash fastener of required dia and size (to be
paid for separately) including cost of materials, labour,
usage charges of machinery complete as per specifications
and as per directions of the engineer-in-charge.
PWD 2021-22, Vol 2, I. 11.11.2, Pg. 78
Area weightage @ 5% 4.35
Total = 91.35
Refilling avaliable earth around trench/pipelines, cables in
layers not exceeding 20cms in depth, compacting each
12 deposited layer by ramming after watering with lead upto Sqm 122.00
50m, lift upto 1.5m. Including cost of all labour complete
as per specifications
PWD 2021-22, Vol 1, I. 1.10, Pg. 7
Area weightage @ 5% 6.10
Total = 128.10