MEASUREMENT SHEET
Sl. No. Item Unit No. L B D Qty
Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees
girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and
stacking of serviceable material to be used or aunctioned, including removal and disposal of top organic soil
1
not exceeding 150 mm in thickness.
(i) By manual means
(a) In area of light jungle
PWD 2021-22, Vol 3, I. 2.4, Pg. 7
1 2.00 2.00 4.00
Sqm Total = 4.00
Ha Total = 0.00
Earthwork excavation by means for drains, canals, wate weir, draft, approach channels, key trench, foundation
of bridge and such similar works, as per drawing and technical specifications, including setting out, shoring,
strutting, barricading, caution lights, excavated surface levelled and sides neatly dressed disposing off or
2
levelling the excavated stuff or sorting and stacking the selected stuff for reuse in radius of 50m and lift 1.5 m
including cost of labour, tools, usage and other appurtenances required to the complete the work.
Depth exceeding 3m , but not exceeding 4.5m
Providing and laying in position plain cement concrete for levelling course for all works on foundation.The
granite/tarp/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine
mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead
3 & lifts, cost of all materials of quality, labour, usage charges of machineries, curing, all the other
appurtenances required the work as per technical specifications. ( The cost of steel reinforcement & formwork
shall be paid separately)
Mix 1:3:6 (M10) Using 40 mm nominal size graded crushed coarse aggregates
Providing brick work with common burnt clay modular bricks of class desingation 3.5 in foundation and plinth
4 in cement mortar 1:4 (1 cement: 4 Coarse sand) including cost of all materials, labour, scaffolding and usage
charges of machinery and other incidental charges complete as per the direction of engineer in charge of work
Refilling avaliable earth around trench/pipelines, cables in layers not exceeding 20cms in depth, compacting
12 each deposited layer by ramming after watering with lead upto 50m, lift upto 1.5m. Including cost of all labour
complete as per specifications
16 mm
Main bar B 256 100 4375 1800 230 6505 6249 34000 150 1 228 2279.64
Stem D
C
10 mm A
Dist. bar 33850 33850 33850 6175 120 1 53 1112.31
Stem
16 mm
Main bar B
128 150 4352 1465 5966.7956 5838.796 34000 150 1 228 2129.99
Stem
Earth side D
C
BBS for Retaining wall
Shape Cut Spacing Total Total
c/c
Dia Shape Bend A B C D length length length Set no. of weight
(mm)
(mm) (mm) (mm) bars (kg)
10 mm A
Dist. bar 33850 33850 33850 5816.796 120 1 50 1049.35
Stem
B
16 mm A C
Main bar 128 230 2890 230 3350 3222 34000 150 1 228 1175.39
Raft
10 mm A
Dist. bar 33850 33850 33850 2890 120 1 26 545.66
Raft
Total = 8292.34
ABSTRACT
Sl. No. Item Unit Qty Rate (Rs) Amount (Rs)
Providing Thermo-Mechanically
Treated bars of grade Fe-550 Steel
reinforcement for R.C.C. work
including straightening,cutting,
bending, placing in position, binding
and anchoring to adjacent
13 members whereever necessary kg 0.87 60,000.00 52,461.22
complete as per Design including
cost of material, labour, usage
charges complete as per
specifications. (The
laps and wastages shall not be
measured separately)
Total = 119,334.73
Rate Analysis
Sl.
Particulars Unit Rate(Rs.)
No.
Clearing and grubbing road land including uprooting rank
vegetation, grass, bushes, shrubs, saplings and trees girth
up to 300 mm, removal of stumps of trees cut earlier and
disposal of unserviceable materials and stacking of
1 serviceable material to be used or aunctioned, including Ha 168,300.00
removal and disposal of top organic soil not exceeding 150
mm in thickness.
(i) By manual means
(a) In area of light jungle
PWD 2021-22, Vol 3, I. 2.4, Pg. 7
Area weightage @ 5% 8,415.00
Total = 176,715.00
Earthwork excavation by means for drains, canals, wate
weir, draft, approach channels, key trench, foundation of
bridge and such similar works, as per drawing and
technical specifications, including setting out, shoring,
strutting, barricading, caution lights, excavated surface
2 levelled and sides neatly dressed disposing off or levelling Cum 452.00
the excavated stuff or sorting and stacking the selected
stuff for reuse in radius of 50m and lift 1.5 m including
cost of labour, tools, usage and other appurtenances
required to the complete the work.
Depth exceeding 3m , but not exceeding 4.5m
PWD 2021-22, Vol 1, I. 1.5.1, Pg. 6
Area weightage @ 5% 22.60
Total = 474.60
Providing and laying in position plain cement concrete for
levelling course for all works on foundation.The
granite/tarp/basalt crushed graded coarse aggregates and
fine aggregates as per relevant IS Codes machine mixed,
laid in layers not exceeding 150 mm thickness, well
compacted using plate vibrators, including all lead & lifts,
3 Cum 5,752.00
cost of all materials of quality, labour, usage charges of
machineries, curing, all the other appurtenances required
the work as per technical specifications. ( The cost of steel
reinforcement & formwork shall be paid separately)
Mix 1:3:6 (M10) Using 40 mm nominal size graded
crushed coarse aggregates
PWD 2021-22, Vol 1, I. 2.1.3, Pg. 15
Area weightage @ 5% 287.60
Total = 6,039.60
Providing brick work with common burnt clay modular
bricks of class desingation 3.5 in foundation and plinth in
cement mortar 1:4 (1 cement: 4 Coarse sand) including
4 Cum 7,464.00
cost of all materials, labour, scaffolding and usage charges
of machinery and other incidental charges complete as per
the direction of engineer in charge of work
PWD 2021-22, Vol 2, I. 6.4, Pg. 13
Area weightage @ 5% 373.20
Total = 7,837.20
Providing and laying vitrified floor tiles in different sizes
(thickness to be specified by the manufacturer) with water
aborbtion less than 0.08% and confirming to IS: 15622, of
approved make, in all colors and shades, laid on 20mm
5 thick cement mortar 1:4 (1 cement:4 Coarse sand), joining Cum 1,023.00
with grey cement slurry @ 3.3Kg/m2 including grouting
the joints with white cement and matching pigments etc.,
complete,
i) Size of tile 500 x 500 mm
PWD 2021-22, Vol 2, I. 9.12.1, Pg. 60
Area weightage @ 5% 51.15
Total = 1,074.15
Providing skirting, dadoing, rises of steps with colour
galzed tiles 6mm thick on 10mm thick cement plaster 1:3
6 Sqm 2,075.00
and joined with white cement slurry over existing rough
plaster surface using plaster surface using glazzed tiles of
approved
PWD 2021-22,make
Voland
2, I. size
9.39, including
Pg. 65 cost of materials,
albour, complete
Area weightage @ as per specifications 5% 103.75
Total = 2,178.75
Wall painting with ayrylic emulsion paint of approved
brand and manufacture to give an even shade: Two coats
on new work after throroughly brooming the surface to
8 remove dirt, duct, mortar drops and foreign matter Sqm 95.00
including preparing the surface even and sand paper
smooth, cost of materials, labour complete as per
specifcation and as per directions of Engineer-in-charge.
PWD 2021-22, Vol 2, I. 8.39, Pg. 48
Area weightage @ -
Total = 95.00
Painting with oil type wood preservative of approved
breand and manufacture: New work (two coat) to give at
even shade including preparing the surface after
9 thoroughly cleaning oil, grease, dirt, and foreign matter, #REF! 34.00
sand papering and knotting, cost of materials, labour
complete as per specification and as per directions of
Engineer-in-charge
PWD 2021-22, Vol 2, I. 8.38, Pg. 48
Area weightage @ 5% 1.70
Total = 35.70
10 White viteous china orissa pattern W.C. pan of size Each 4,246.00
580x440 m integral type foot rests.
PWD 2021-22, Vol 2, I. 14.1.1, Pg. 123
Area weightage @ 5% 212.30
Total = 4,458.30
Providing and fising factory made ISI marked steel glazed
doors, windows and ventilators, side/top/center hung, with
beading and all members such as F7D, F4B, K11 and K12B
etc., complete of standrad rolled steel sections, joints
mitred and flash butt welded and sash bars tenoed and
riveted, including providing and fising of henges, pivots,
including priming coat of approved steel primer, but
11 Sqm 87.00
excluding the cost of other fittings, complete all as per
approved design, (sectional weight of only steel members
shall be measured for payment). Fixing with carbo steel
galvanised dash fastener of required dia and size (to be
paid for separately) including cost of materials, labour,
usage charges of machinery complete as per specifications
and as per directions of the engineer-in-charge.
PWD 2021-22, Vol 2, I. 11.11.2, Pg. 78
Area weightage @ 5% 4.35
Total = 91.35
Refilling avaliable earth around trench/pipelines, cables in
layers not exceeding 20cms in depth, compacting each
12 deposited layer by ramming after watering with lead upto Sqm 122.00
50m, lift upto 1.5m. Including cost of all labour complete
as per specifications
PWD 2021-22, Vol 1, I. 1.10, Pg. 7
Area weightage @ 5% 6.10
Total = 128.10