SITE ARRANGEMENT PLAN

LAMIPAK PROJECT – CIKANDE


BANTEN - 2022

Propose By Check By Approved By


( CSCODS ) ( BEAREU VARIETAS INDONESIA ) ( LAMIPAK )

( Rokken Zhao ) ( Yopie Pramuditia ) ( Andi Kurniawan )


( Main Contractor ) ( Construction Management ) ( Owner )
1. TEMPORARY WORK SITE PLAN

SITE OFFICE & FENCE

LABOUR MESS
Start 26/09/22 – Finish 26/10/22

DEEP WELL

SITE OFFICE
Start 20/09/22 – Finish 20/10/22

LIGHTING ROD

DEEP WELL

TEMPORARY FENCE
Start 1/09/22 – Finish 26/09/22

LIGHTING ROD
2.CONSTRUCTION ROAD & FACILITY
STEP - 1

Data Center & Waste Water Material Laydown


Data Center & Waste Water Fabrication

4 Paper Straw Material Laydown


Paper Straw Fabrication
Temporary Construction Acces Road

Temporary Construction Acces Road


Start 26/09/22 – Finish 03/10/22
3.CONSTRUCTION ROAD & FACILITY
STEP - 2

Temporary Construction Acces Road


Ware HouseFabrication
Ware House Material Laydown

Production Workshop Material Laydown

Production Workshop Fabrication

Temporary Construction Acces Road


Start 4/10/22 – Finish 20/10/22
4.CONSTRUCTION ROAD & FACILITY
STEP - 3

Temporary Construction Acces Road


Start 21/10/22 – Finish 2/11/22

Temporary Construction Acces Road

Production Workshop Material Laydown

Production Workshop Fabrication

Office Building Laydown

Office Building Fabrication

Dormitory Laydown

Dormitory Fabrication

Laydown Office