Professional Documents
Culture Documents
Saudi Arabia
Page 1 of 8
30MWp Solar Power Project NADEC City, Haradh,
Saudi Arabia
R0 AO Yusuf Yusuf
Prepared Reviewed Approved Approved
Rev. Remark
By By By Date
Clarifications
NON
Page 2 of 8
Table of Contents
1. Introduction..................................................................................................................................................................................4
2. References & Standards & Norms...............................................................................................................................................4
3. Responsibilities............................................................................................................................................................................4
4. Requirements................................................................................................................................................................................6
4.1 Site Preparation...................................................................................................................................................................6
4.2 Official Permissions:...........................................................................................................................................................6
4.3 Tools & testing equipment..................................................................................................................................................6
5. Methodology................................................................................................................................................................................6
5.1 Sandblast or Grit Blast the Surface:....................................................................................................................................6
5.1 Prime the Surface:...............................................................................................................................................................6
Secondary Bonding..........................................................................................................................................................................7
5.2 Apply Chopped Strand Mat:...............................................................................................................................................7
5.3 Apply Surfacing Veil:.........................................................................................................................................................7
5.4 Inspect and Repair the Lining:............................................................................................................................................7
5.5 Apply Topcoat:...................................................................................................................................................................8
6. Health and Safety:........................................................................................................................................................................8
7. Environmental Issues:..................................................................................................................................................................8
Housekeeping...................................................................................................................................................................................8
1. Introduction
Page 3 of 8
This Procedures covers the steps of installation, precautions and HSSE consideration to be taken into
account. During the application of DERAKANE MOMENTUM™ 470-300 Epoxy Vinyl Ester Resin for
oil tank.
3. Responsibilities
3.1 The Site Manager, or who he assigns, shall be responsible for the Quality Procedure to ensure that
construction work is carried out as per Project requirements. His Superintendent/Supervisor shall check that
work is ready for inspection and prepare Internal Inspection Request. The Superintendent/Supervisor shall
inform all parties concerned for any of inspection and the time schedule.
3.2 The Quality Control Manager, or who he assigns, shall be responsible for conducting surveillance and
inspection duties for work and ensuring quality compliance and efficient recording and reporting of results as
required. He shall review all relevant documents, material conformance certificates and non-conformance
reports and shall receive all internal request for inspection from various sections of implementing work and
prepare (RFI) Request for Inspection as per schedule work priorities and proceeds with the Quality inspection
with the client, owner representative as required. He shall also prepare Witness / Hold Point inspection and the
corresponding work releases by reviewing records and results as proof that work inspected conforms to
contract requirements. He shall also be responsible to ensure that an approved detailed IFC/AFC or shop
drawing is available prior to commencement of the work and all materials to be used are in compliance with
the approved project specifications or requirements.
3.3 Civil Engineer, or who he assigns, shall ensure that all related works are carried out in accordance with
approved Issued for Construction drawings, specifications, schedule, quality and safety. Check Design and
Construction details in reference with the project standard and specification. Sees to it that the design
drawings provide adequate information for purchasing and site construction. Reports to Site Manager.
3.4 HSE Manager, or who he assigns, supervises the project activities relating to health, safety and
Page 4 of 8
environmental compatibility. He shall carry out regular inspection at site and workplaces whether work is
being carried out According to the given instructions and those personnel are wearing the necessary
protective equipment (PPE). Perform, in co-operation with the Site Supervisors and Foremen regular
Tool Box meetings. Report any adverse condition to health and safety.
No. of
Position Mobile Number
Personnel
Project Director
1 00962796977374
(MOHAMMAD HAMSHARI)
Site Manager
1 00966541862536
(Muneer Hamshari)
HSE Manager
1 00966569349008
(Ihasn Khan)
Engineering Lead 1 00966541862501
(Yusuf Tahseen)
QA/QC Leader
1 00966569940161
(Ahmed Olaimat)
Electrical Engineer
1 00966569321707
(Sohaib Nabeel)
QA/QC inspector 1
Safety Officer 1
Site Foreman 1
Page 5 of 8
4. Requirements
4.1 Site Preparation
5. Methodology
In the case of concrete, the Portland cement lattice should be removed to expose stone. Several sanding methods are acceptable; however,
grit blasting and sandblasting are preferred. When lining a concrete structure, the concrete should be at least 28 days old and completely
dry. Sandblast as you would a metal surface. After blasting, fill any cracks, pits, etc., with an initiated fumed silica-filled resin putty, allow
to cure, and sand smooth. After all sanding is complete; thoroughly vacuum the surface to remove all dust and dirt.
The surface temperature of the equipment to be relined should not exceed 40 °C (100 °F). Immediately after the dust has been removed,
apply 0.05–0.08 mm (2–3 mil) of initiated Derakane™ 8084 resin with a brush or roller to provide an anchor for the lining.
The primer coat prevents surface corrosion prior to the application of the laminating resin and also provides a bonding surface for the
laminating resin. The primer coat should be allowed to cure under ambient conditions, 15–38 °C (60–100 °F), to a tack-free state before
applying the laminating resin. Once the primer coat is dry to the touch, check the surface with a test patch as explained below:
Secondary Bonding
Secondary bonding can be a concern in many FRP applications. This is particularly true with Derakane™ 470 resin because of its high
degree of reactivity.
Page 6 of 8
Derakane™ Signia™ resins are formulated for excellent secondary bonding, minimizing the need for surface
preparation such as sanding or grinding. To achieve a good secondary bond with Derakane™ and Derakane™ Momentum™ resins, it is
necessary to prepare the surface properly.
The entire surface must be sanded uniformly, giving at least a 0.05 mm–0.08 mm (2–3 mil) anchor pattern. This can be achieved by
grinding the surface with a #16 or #24 sanding disc. When using the sanding disc, check the pad periodically to make sure there is no
buildup of glass fiber and resin. If buildup occurs, it will impair proper sanding and the consequent formation of a good secondary bond.
After you have properly prepared the surface, you must keep it clean and dry until you can start laminating. Dust, moisture or traces of oil
that can come in contact with the surface may act as a mold release or inhibit the cure and prevent a good secondary bond. Laminating
should be done within a couple of hours of the surface preparation.
The addition of the surfactant BYK A515 at 0.1 wt% to Derakane™ or Derakane™ Momentum™ resins can improve their adhesion to
primary laminates. The surfactant properties of the BYK A515 reduce the surface tension of epoxy vinyl ester resins, thus allowing the
resins to flow more easily into laminate surface cavities. For structural walls on spas and hot tubs, the use of BYK A515 at a level of 0.2 wt
% in Derakane™ resin laminates have been shown to improve the resin’s adhesion to the smooth backing of polyacrylic sheets.
Note: Solvent wiping of a primary surface before secondary laminating starts is not necessary. In fact, it can cause poor secondary bond
formation. A solvent wipe is usually done to remove the dust accumulated during sanding. If you use a rag wetted with solvent to wipe off
the primary surface, it is likely to have picked up contaminants that might act as a mold release and prevent a good secondary bond.
Thorough dusting with a dry cloth is sufficient.
If the lining application is delayed, cover the primed surface to protect it from contamination. If the delay is longer than three days and the
primer coat is allowed to develop a hard cure, Sand the surface lightly and apply another primer coat prior to applying the laminating resin.
Note: If you allow any layer of mat or surfacing veil to cure overnight, you must wipe it with clean, dry rags to remove any contaminants before you apply
the next layer. If a layer or an overlap is allowed to cure for more than 72 hours at 20 °C (70 °F), it must be etched by grinding or sandblasting before the
next layer can be applied. When using Derakane™ Signia™resins, grinding may not be needed.
Ensure that the Work Area Is Suitable for Safe Operation (Have a clean, well-lighted work area with adequate
ventilation).
7. Environmental Issues:
CPSC will follow project safety program and manual and to implement the environmental activities. Proper
sanitation practices, waste segregation and the drinking water shall be provided and placed at designated areas.
Housekeeping
A place for everything and everything in its place.
During the course of work, the foreman and the supervisor shall ensure for a tidy and organized.
The work area must be arranged in such a way that, “everything is maintained in its proper place” under
monitoring of EHS officer.
Page 8 of 8