PT PEMBANGKITAN JAWA BALI SERVICES No. Dok.

SIAP INTEGRATED MANAGEMENT SYSTEM Tgl. Terbit

OVERHOUL CLASS A Revisi 00

PLTU TANJUNG JATI B UNIT 4 Halaman 1

SURAT PERINTAH KERJA


Hari/Tanggal SATURDAY, 19 SEPTEMBER 2020
Bidang PROTECTION
Koordinator RYAN FARIEZTYA
Shift NON SHIFT
Nama Teknisi Jumlah Progress
No Area Equipment Pekerjaan Durasi Tools Material Form Uji No IK Keterangan
PJBS MKP Helper Rencana Realisasi
Check setting and record

Proteksi MV Toshiba MCR- Fluke Multitester, ISA Contact Cleaner, brush


1 Turbin Board B 26 Cleaning the protection panel 4 Dodi, Ari Catur Ridwan, Thaif DRTS 66, Tools Set seal tape IK-TJ.02.001 15% 15%

Function test

Check setting and record

2 Proteksi MV Toshiba MCR- Cleaning the protection panel 4 Dodi, Ari Catur Ridwan, Thaif Fluke Multitester, ISA Contact Cleaner, brush IK-TJ.02.001 15% 15%
Turbin Board A 26 DRTS 66, Tools Set seal tape

Function test

Koordinator Bidang Project Manager


PT PEMBANGKITAN JAWA BALI SERVICES No. Dok.

SIAP INTEGRATED MANAGEMENT SYSTEM Tgl. Terbit

OVERHOUL CLASS A Revisi 00

PLTU TANJUNG JATI B UNIT 4 Halaman 1

SURAT PERINTAH KERJA


Hari/Tanggal SUNDAY, 20 SEPTEMBER 2020
Bidang PROTECTION
Koordinator RYAN FARIEZTYA
Shift NON SHIFT
Nama Teknisi Jumlah Progress
No Area Equipment Pekerjaan Durasi Tools Material Form Uji No IK Keterangan
PJBS MKP Helper Rencana Realisasi
Check setting and record

Proteksi MV Toshiba MCR- Fluke Multitester, ISA Contact Cleaner, brush


1 Turbin Board B 26 Cleaning the protection panel 4 Dodi, Ari Catur Ridwan, Thaif DRTS 66, Tools Set seal tape IK-TJ.02.001 30% 30%

Function test

Check setting and record

2 Proteksi MV Toshiba MCR- Cleaning the protection panel 4 Dodi, Ari Catur Ridwan, Thaif Fluke Multitester, ISA Contact Cleaner, brush IK-TJ.02.001 30% 30%
Turbin Board A 26 DRTS 66, Tools Set seal tape

Function test

Koordinator Bidang Project Manager


PT PEMBANGKITAN JAWA BALI SERVICES No. Dok.

SIAP INTEGRATED MANAGEMENT SYSTEM Tgl. Terbit

OVERHOUL CLASS A Revisi 00

PLTU TANJUNG JATI B UNIT 4 Halaman 1

SURAT PERINTAH KERJA


Hari/Tanggal MONDAY, 21 SEPTEMBER 2020
Bidang PROTECTION
Koordinator RYAN FARIEZTYA
Shift NON SHIFT
Nama Teknisi Jumlah Progress
No Area Equipment Pekerjaan Durasi Tools Material Form Uji No IK Keterangan
PJBS MKP Helper Rencana Realisasi
Check setting and record

Proteksi MV Toshiba MCR- Fluke Multitester, ISA Contact Cleaner, brush


1 Turbin Board B 26 Cleaning the protection panel 4 Dodi, Ari Catur Ridwan, Thaif DRTS 66, Tools Set seal tape IK-TJ.02.001 45% 45%

Function test

Check setting and record

2 Proteksi MV Toshiba MCR- Cleaning the protection panel 4 Dodi, Ari Catur Ridwan, Thaif Fluke Multitester, ISA Contact Cleaner, brush IK-TJ.02.001 45% 45%
Turbin Board A 26 DRTS 66, Tools Set seal tape

Function test

Koordinator Bidang Project Manager


PT PEMBANGKITAN JAWA BALI SERVICES No. Dok.

SIAP INTEGRATED MANAGEMENT SYSTEM Tgl. Terbit

OVERHOUL CLASS A Revisi 00

PLTU TANJUNG JATI B UNIT 4 Halaman 1

SURAT PERINTAH KERJA


Hari/Tanggal TUESDAY, 22 SEPTEMBER 2020
Bidang PROTECTION
Koordinator RYAN FARIEZTYA
Shift NON SHIFT
Nama Teknisi Jumlah Progress
No Area Equipment Pekerjaan Durasi Tools Material Form Uji No IK Keterangan
PJBS MKP Helper Rencana Realisasi
Check setting and record

Proteksi MV Toshiba MCR- Fluke Multitester, ISA Contact Cleaner, brush


1 Turbin Board B 26 Cleaning the protection panel 4 Dodi, Ari Catur Ridwan, Thaif DRTS 66, Tools Set seal tape IK-TJ.02.001 60% 60%

Function test

Check setting and record

2 Proteksi MV Toshiba MCR- Cleaning the protection panel 4 Dodi, Ari Catur Ridwan, Thaif Fluke Multitester, ISA Contact Cleaner, brush IK-TJ.02.001 60% 60%
Turbin Board A 26 DRTS 66, Tools Set seal tape

Function test

Koordinator Bidang Project Manager


PT PEMBANGKITAN JAWA BALI SERVICES No. Dok.

SIAP INTEGRATED MANAGEMENT SYSTEM Tgl. Terbit

OVERHOUL CLASS A Revisi 00

PLTU TANJUNG JATI B UNIT 4 Halaman 1

SURAT PERINTAH KERJA


Hari/Tanggal WEDNESDAY, 23 SEPTEMBER 2020
Bidang PROTECTION
Koordinator RYAN FARIEZTYA
Shift NON SHIFT
Nama Teknisi Jumlah Progress
No Area Equipment Pekerjaan Durasi Tools Material Form Uji No IK Keterangan
PJBS MKP Helper Rencana Realisasi
Check setting and record

Proteksi MV Toshiba MCR- Fluke Multitester, ISA Contact Cleaner, brush


1 Turbin Board B 26 Cleaning the protection panel 4 Dodi, Ari Catur Ridwan, Thaif DRTS 66, Tools Set seal tape IK-TJ.02.001 75% 75%

Function test

Check setting and record

2 Proteksi MV Toshiba MCR- Cleaning the protection panel 4 Dodi, Ari Catur Ridwan, Thaif Fluke Multitester, ISA Contact Cleaner, brush IK-TJ.02.001 75% 75%
Turbin Board A 26 DRTS 66, Tools Set seal tape

Function test

Koordinator Bidang Project Manager


PT PEMBANGKITAN JAWA BALI SERVICES No. Dok.

SIAP INTEGRATED MANAGEMENT SYSTEM Tgl. Terbit

OVERHOUL CLASS A Revisi 00

PLTU TANJUNG JATI B UNIT 4 Halaman 1

SURAT PERINTAH KERJA


Hari/Tanggal THURSDAY, 24 SEPTEMBER 2020
Bidang PROTECTION
Koordinator RYAN FARIEZTYA
Shift NON SHIFT
Nama Teknisi Jumlah Progress
No Area Equipment Pekerjaan Durasi Tools Material Form Uji No IK Keterangan
PJBS MKP Helper Rencana Realisasi
Check setting and record

Proteksi MV Toshiba MCR- Fluke Multitester, ISA Contact Cleaner, brush


1 Turbin Board B 26 Cleaning the protection panel 4 Dodi, Ari Catur Ridwan, Thaif DRTS 66, Tools Set seal tape IK-TJ.02.001 90% 90%

Function test

Check setting and record

2 Proteksi MV Toshiba MCR- Cleaning the protection panel 4 Dodi, Ari Catur Ridwan, Thaif Fluke Multitester, ISA Contact Cleaner, brush IK-TJ.02.001 90% 90%
Turbin Board A 26 DRTS 66, Tools Set seal tape

Function test

Koordinator Bidang Project Manager


PT PEMBANGKITAN JAWA BALI SERVICES No. Dok.

SIAP INTEGRATED MANAGEMENT SYSTEM Tgl. Terbit

OVERHOUL CLASS A Revisi 00

PLTU TANJUNG JATI B UNIT 4 Halaman 1

SURAT PERINTAH KERJA


Hari/Tanggal FRIDAY, 25 SEPTEMBER 2020
Bidang PROTECTION
Koordinator RYAN FARIEZTYA
Shift NON SHIFT
Nama Teknisi Jumlah Progress
No Area Equipment Pekerjaan Durasi Tools Material Form Uji No IK Keterangan
PJBS MKP Helper Rencana Realisasi
Check setting and record

Proteksi MV Toshiba MCR- Fluke Multitester, ISA Contact Cleaner, brush


1 Turbin Board B 26 Cleaning the protection panel 5 Dodi, Ari Catur Ridwan, Thaif DRTS 66, Tools Set seal tape IK-TJ.02.001 100% 100%

Function test

Check setting and record

2 Proteksi MV Toshiba MCR- Cleaning the protection panel 5 Dodi, Ari Catur Ridwan, Thaif Fluke Multitester, ISA Contact Cleaner, brush IK-TJ.02.001 100% 100%
Turbin Board A 26 DRTS 66, Tools Set seal tape

Function test

Koordinator Bidang Project Manager


PT PEMBANGKITAN JAWA BALI SERVICES No. Dok.

SIAP INTEGRATED MANAGEMENT SYSTEM Tgl. Terbit

OVERHOUL CLASS A Revisi 00

PLTU TANJUNG JATI B UNIT 4 Halaman 1

SURAT PERINTAH KERJA


Hari/Tanggal SATURDAY, 26 SEPTEMBER 2020
Bidang PROTECTION
Koordinator RYAN FARIEZTYA
Shift NON SHIFT
Nama Teknisi Jumlah Progress
No Area Equipment Pekerjaan Durasi Tools Material Form Uji No IK Keterangan
PJBS MKP Helper Rencana Realisasi
Check setting and record 4
Generator
Generator Transforers Fluke Multitester, ISA Contact Cleaner, brush
1 Protection Bus Feeder Cleaning the protection panel 2 Dodi, Ari Catur Ridwan, Thaif DRTS 66, Tools Set seal tape IK-TJ.02.008 100% 100%
Relay Panel 1 Beckwith M-
3311
Function test 2

Generator Check setting and record 2


Generator Protection Fluke Multitester, ISA Contact Cleaner, brush
2 Protection Beckwith M- Dodi, Ari Catur Ridwan, Thaif DRTS 66, Tools Set seal tape IK-TJ.02.008 50% 50%
Relay Panel 2 3452 Cleaning the protection panel 2

Koordinator Bidang Project Manager


PT PEMBANGKITAN JAWA BALI SERVICES No. Dok.

SIAP INTEGRATED MANAGEMENT SYSTEM Tgl. Terbit

OVERHOUL CLASS A Revisi 00

PLTU TANJUNG JATI B UNIT 4 Halaman 1

SURAT PERINTAH KERJA


Hari/Tanggal SUNDAY, 27 SEPTEMBER 2020
Bidang PROTECTION
Koordinator RYAN FARIEZTYA
Shift NON SHIFT
Nama Teknisi Jumlah Progress
No Area Equipment Pekerjaan Durasi Tools Material Form Uji No IK Keterangan
PJBS MKP Helper Rencana Realisasi

Generator Generator Check setting and record Gen line voltage 4


Protection Fluke Multitester, ISA Contact Cleaner, brush
1 Protection Beckwith M- Dodi, Ari Catur Ridwan, Thaif DRTS 66, Tools Set seal tape IK-TJ.02.008 50% 50%
Relay Panel 2 3452 Function test 2

Battery 220 Check the deformation of condenser and reactor 3


DC Battery Fluke Multitester, Contact Cleaner, brush
2 Vdc 2500AH Dodi, Ari Catur Ridwan, Thaif IK-TJ.02.012 100% 100%
System Area Unit Measure the voltage and temperature of each battery densitymeter seal tape
cell 3

Koordinator Bidang Project Manager


PT PEMBANGKITAN JAWA BALI SERVICES No. Dok.

SIAP INTEGRATED MANAGEMENT SYSTEM Tgl. Terbit

OVERHOUL CLASS A Revisi 00

PLTU TANJUNG JATI B UNIT 4 Halaman 1

SURAT PERINTAH KERJA


Hari/Tanggal MONDAY, 28 SEPTEMBER 2020
Bidang PROTECTION
Koordinator RYAN FARIEZTYA
Shift NON SHIFT
Nama Teknisi Jumlah Progress
No Area Equipment Pekerjaan Durasi Tools Material Form Uji No IK Keterangan
PJBS MKP Helper Rencana Realisasi
Generator Cleaning the protection panel neutral grounding 2
Generator transfromer
Protection Fluke Multitester, ISA Contact Cleaner, brush
1 Protection Beckwith M- Dodi, Ari Catur Ridwan, Thaif DRTS 66, Tools Set seal tape IK-TJ.02.008 100% 100%
Relay Panel 2 3452 Function test 2

Battery discharge test 3

Battery 220 Battery boosting charging 3 Fluke Multitester,


DC Battery Contact Cleaner, brush
2 System Vdc 2500AH Dodi, Ari Catur Ridwan, Thaif densitymeter, dummy seal tape IK-TJ.02.012 100% 100%
Area Unit Refilling battery electrolyte 2 load tester

Check the specific gravity,level of the electrolyte,cell


cover, poles and links, and slightly greased 2

Check setting and record Gen Line VT1 2


Generator Generator
Protection Protection Fluke Multitester, ISA Contact Cleaner, brush
3 Beckwith M- Cleaning the protection panel 2 Dodi, Ari Catur Ridwan, Thaif DRTS 66, Tools Set seal tape IK-TJ.02.008 50% 50%
Relay Panel 3
3452
Function test 2

Koordinator Bidang Project Manager


PT PEMBANGKITAN JAWA BALI SERVICES No. Dok.

SIAP INTEGRATED MANAGEMENT SYSTEM Tgl. Terbit

OVERHOUL CLASS A Revisi 00

PLTU TANJUNG JATI B UNIT 4 Halaman 1

SURAT PERINTAH KERJA


Hari/Tanggal TUESDAY, 29 SEPTEMBER 2020
Bidang PROTECTION
Koordinator RYAN FARIEZTYA
Shift NON SHIFT
Nama Teknisi Jumlah Progress
No Area Equipment Pekerjaan Durasi Tools Material Form Uji No IK Keterangan
PJBS MKP Helper Rencana Realisasi
Battery poles, cable, and body cleaning 2

DC Battery Battery 220 Check anode and cathode plates for abnormal Fluke Multitester, Contact Cleaner, brush
1 System Vdc 2500AH condition 2 Dodi, Ari Catur Ridwan, Thaif densitymeter, dummy seal tape IK-TJ.02.012 100% 100%
Area Unit load tester
Check the battery with the rectifier switched on 2

Check setting and record Neutral grounding


transformer 2
Generator
2 Protection Beckwith M- Cleaning the protection panel 4 Dodi, Ari Catur Ridwan, Thaif Fluke Multitester, ISA Contact Cleaner, brush IK-TJ.02.008 50% 50%
Relay Panel 3 3425 DRTS 66, Tools Set seal tape

Function test Gen Line Voltage 2

Koordinator Bidang Project Manager


PT PEMBANGKITAN JAWA BALI SERVICES No. Dok.

SIAP INTEGRATED MANAGEMENT SYSTEM Tgl. Terbit

OVERHOUL CLASS A Revisi 00

PLTU TANJUNG JATI B UNIT 4 Halaman 1

SURAT PERINTAH KERJA


Hari/Tanggal WEDNESDY, 30 SEPTEMBER 2020
Bidang PROTECTION
Koordinator RYAN FARIEZTYA
Shift NON SHIFT
Nama Teknisi Jumlah Progress
No Area Equipment Pekerjaan Durasi Tools Material Form Uji No IK Keterangan
PJBS MKP Helper Rencana Realisasi

Generator
Protection Beckwith M- Fluke Multitester, ISA Contact Cleaner, brush
1 3425 Function test Neutral Grounding Transformer 2 Dodi, Ari Catur Ridwan, Thaif DRTS 66, Tools Set seal tape IK-TJ.02.008 100% 100%
Relay Panel 3

Check setting and record transf bus feeder 2


Transformers
Generator
2 Protection Protection Cleaning the protection panel 2 Dodi, Ari Catur Ridwan, Thaif Fluke Multitester, ISA Contact Cleaner, brush IK-TJ.02.008 50% 50%
Relay Panel 4 Beckwith M- DRTS 66, Tools Set seal tape
3310
Function test 2

Koordinator Bidang Project Manager


PT PEMBANGKITAN JAWA BALI SERVICES No. Dok.

SIAP INTEGRATED MANAGEMENT SYSTEM Tgl. Terbit

OVERHOUL CLASS A Revisi 00

PLTU TANJUNG JATI B UNIT 4 Halaman 1

SURAT PERINTAH KERJA


Hari/Tanggal THURSDAY, 1 OCTOBER 2020
Bidang PROTECTION
Koordinator RYAN FARIEZTYA
Shift NON SHIFT
Nama Teknisi Jumlah Progress
No Area Equipment Pekerjaan Durasi Tools Material Form Uji No IK Keterangan
PJBS MKP Helper Rencana Realisasi
Transformers Cleaning the protection panel Neutral grounding 2
Generator transformer
Protection Fluke Multitester, ISA Contact Cleaner, brush
1 Protection Beckwith M- Dodi, Ari Catur Ridwan, Thaif DRTS 66, Tools Set seal tape IK-TJ.02.008 100% 100%
Relay Panel 4 3310 Function test 2

Check setting and record 2


Excitation
Generator Transformers
Protection Transformers Fluke Multitester, ISA Contact Cleaner, brush
2 Cleaning the protection panel 2 Dodi, Ari Catur Ridwan, Thaif DRTS 66, Tools Set seal tape IK-TJ.02.008 100% 100%
Relay Panel 5 Beckwith M-
3310
Function test 2

Generator Unit
2 Protection Transformers A Check setting and record 2 Dodi, Ari Catur Ridwan, Thaif Fluke Multitester, ISA Contact Cleaner, brush IK-TJ.02.008 50% 50%
Relay Panel 6 Beckwith M- DRTS 66, Tools Set seal tape
3310

Koordinator Bidang Project Manager


PT PEMBANGKITAN JAWA BALI SERVICES No. Dok.

SIAP INTEGRATED MANAGEMENT SYSTEM Tgl. Terbit

OVERHOUL CLASS A Revisi 00

PLTU TANJUNG JATI B UNIT 4 Halaman 1

SURAT PERINTAH KERJA


Hari/Tanggal FRIDAY, 2 OCTOBER 2020
Bidang PROTECTION
Koordinator RYAN FARIEZTYA
Shift NON SHIFT
Nama Teknisi Jumlah Progress
No Area Equipment Pekerjaan Durasi Tools Material Form Uji No IK Keterangan
PJBS MKP Helper Rencana Realisasi

Generator Unit Cleaning the protection panel 2


Transformers A Fluke Multitester, ISA Contact Cleaner, brush
1 Protection Beckwith M- Dodi, Ari Catur Ridwan, Thaif DRTS 66, Tools Set seal tape IK-TJ.02.008 100% 100%
Relay Panel 6 3310 Function test 2

Check setting and record 2


Generator Unit
Protection Transformers B Fluke Multitester, ISA Contact Cleaner, brush
2 Beckwith M- Cleaning the protection panel 2 Dodi, Ari Catur Ridwan, Thaif DRTS 66, Tools Set seal tape IK-TJ.02.008 100% 100%
Relay Panel 7
3310
Function test 2

Koordinator Bidang Project Manager


PT PEMBANGKITAN JAWA BALI SERVICES No. Dok.

SIAP INTEGRATED MANAGEMENT SYSTEM Tgl. Terbit

OVERHOUL CLASS A Revisi 00

PLTU TANJUNG JATI B UNIT 4 Halaman 1

SURAT PERINTAH KERJA


Hari/Tanggal SATURDAY, 3 OCTOBER 2020
Bidang PROTECTION
Koordinator RYAN FARIEZTYA
Shift NON SHIFT
Nama Teknisi Jumlah Progress
No Area Equipment Pekerjaan Durasi Tools Material Form Uji No IK Keterangan
PJBS MKP Helper Rencana Realisasi
Check setting and record 5

FGD MV Board Fluke Multitester, ISA Contact Cleaner, brush


1 FGD A MPM100A II Cleaning the protection panel 3 Dodi, Ari Catur Ridwan, Thaif DRTS 66, Tools Set seal tape IK-TJ.02.001 100% 100%

Function test 2

FGD MV Board Fluke Multitester, ISA Contact Cleaner, brush


2 FGD A MPM400A II Check setting and record 5 Dodi, Ari Catur Ridwan, Thaif DRTS 66, Tools Set seal tape IK-TJ.02.001 50% 50%

Koordinator Bidang Project Manager


PT PEMBANGKITAN JAWA BALI SERVICES No. Dok.

SIAP INTEGRATED MANAGEMENT SYSTEM Tgl. Terbit

OVERHOUL CLASS A Revisi 00

PLTU TANJUNG JATI B UNIT 4 Halaman 1

SURAT PERINTAH KERJA


Hari/Tanggal SUNDAY, 4 OCTOBER 2020
Bidang PROTECTION
Koordinator RYAN FARIEZTYA
Shift NON SHIFT
Nama Teknisi Jumlah Progress
No Area Equipment Pekerjaan Durasi Tools Material Form Uji No IK Keterangan
PJBS MKP Helper Rencana Realisasi
Cleaning the protection panel 2
FGD MV Board Fluke Multitester, ISA Contact Cleaner, brush
1 FGD A MPM400A II Dodi, Ari Catur Ridwan, Thaif DRTS 66, Tools Set seal tape IK-TJ.02.001 100% 100%
Function test 2

FGD MV Board Fluke Multitester, ISA Contact Cleaner, brush


2 FGD A MPM200A II Check setting and record 5 Dodi, Ari Catur Ridwan, Thaif DRTS 66, Tools Set seal tape IK-TJ.02.001 50% 50%

Koordinator Bidang Project Manager


PT PEMBANGKITAN JAWA BALI SERVICES No. Dok.

SIAP INTEGRATED MANAGEMENT SYSTEM Tgl. Terbit

OVERHOUL CLASS A Revisi 00

PLTU TANJUNG JATI B UNIT 4 Halaman 1

SURAT PERINTAH KERJA


Hari/Tanggal MONDAY, 5 OCTOBER 2020
Bidang PROTECTION
Koordinator RYAN FARIEZTYA
Shift NON SHIFT
Nama Teknisi Jumlah Progress
No Area Equipment Pekerjaan Durasi Tools Material Form Uji No IK Keterangan
PJBS MKP Helper Rencana Realisasi
Cleaning the protection panel 2
FGD MV Board Fluke Multitester, ISA Contact Cleaner, brush
1 FGD A MPM200A II Dodi, Ari Catur Ridwan, Thaif DRTS 66, Tools Set seal tape IK-TJ.02.001 100% 100%
Function test 2

Check setting and record 4


FGD MV Board Fluke Multitester, ISA Contact Cleaner, brush
2 FGD Dodi, Ari Catur Ridwan, Thaif IK-TJ.02.001 50% 50%
A MPM200D II DRTS 66, Tools Set seal tape
Cleaning the protection panel 2

Koordinator Bidang Project Manager


PT PEMBANGKITAN JAWA BALI SERVICES No. Dok.

SIAP INTEGRATED MANAGEMENT SYSTEM Tgl. Terbit

OVERHOUL CLASS A Revisi 00

PLTU TANJUNG JATI B UNIT 4 Halaman 1

SURAT PERINTAH KERJA


Hari/Tanggal TUESDAY, 6 OCTOBER 2020
Bidang PROTECTION
Koordinator RYAN FARIEZTYA
Shift NON SHIFT
Nama Teknisi Jumlah Progress
No Area Equipment Pekerjaan Durasi Tools Material Form Uji No IK Keterangan
PJBS MKP Helper Rencana Realisasi
1 FGD FGD MV Board Function test 2 Dodi, Ari Catur Ridwan, Thaif Fluke Multitester, ISA Contact Cleaner, brush IK-TJ.02.001 100% 100%
A MPM200D II DRTS 66, Tools Set seal tape

Check setting and record 4

FGD MV Board Fluke Multitester, ISA Contact Cleaner, brush


2 FGD A MPM200C II Cleaning the protection panel 2 Dodi, Ari Catur Ridwan, Thaif DRTS 66, Tools Set seal tape IK-TJ.02.001 100% 100%

Function test 2

Koordinator Bidang Project Manager