Professional Documents
Culture Documents
Function test
2 Proteksi MV Toshiba MCR- Cleaning the protection panel 4 Dodi, Ari Catur Ridwan, Thaif Fluke Multitester, ISA Contact Cleaner, brush IK-TJ.02.001 15% 15%
Turbin Board A 26 DRTS 66, Tools Set seal tape
Function test
Function test
2 Proteksi MV Toshiba MCR- Cleaning the protection panel 4 Dodi, Ari Catur Ridwan, Thaif Fluke Multitester, ISA Contact Cleaner, brush IK-TJ.02.001 30% 30%
Turbin Board A 26 DRTS 66, Tools Set seal tape
Function test
Function test
2 Proteksi MV Toshiba MCR- Cleaning the protection panel 4 Dodi, Ari Catur Ridwan, Thaif Fluke Multitester, ISA Contact Cleaner, brush IK-TJ.02.001 45% 45%
Turbin Board A 26 DRTS 66, Tools Set seal tape
Function test
Function test
2 Proteksi MV Toshiba MCR- Cleaning the protection panel 4 Dodi, Ari Catur Ridwan, Thaif Fluke Multitester, ISA Contact Cleaner, brush IK-TJ.02.001 60% 60%
Turbin Board A 26 DRTS 66, Tools Set seal tape
Function test
Function test
2 Proteksi MV Toshiba MCR- Cleaning the protection panel 4 Dodi, Ari Catur Ridwan, Thaif Fluke Multitester, ISA Contact Cleaner, brush IK-TJ.02.001 75% 75%
Turbin Board A 26 DRTS 66, Tools Set seal tape
Function test
Function test
2 Proteksi MV Toshiba MCR- Cleaning the protection panel 4 Dodi, Ari Catur Ridwan, Thaif Fluke Multitester, ISA Contact Cleaner, brush IK-TJ.02.001 90% 90%
Turbin Board A 26 DRTS 66, Tools Set seal tape
Function test
Function test
2 Proteksi MV Toshiba MCR- Cleaning the protection panel 5 Dodi, Ari Catur Ridwan, Thaif Fluke Multitester, ISA Contact Cleaner, brush IK-TJ.02.001 100% 100%
Turbin Board A 26 DRTS 66, Tools Set seal tape
Function test
DC Battery Battery 220 Check anode and cathode plates for abnormal Fluke Multitester, Contact Cleaner, brush
1 System Vdc 2500AH condition 2 Dodi, Ari Catur Ridwan, Thaif densitymeter, dummy seal tape IK-TJ.02.012 100% 100%
Area Unit load tester
Check the battery with the rectifier switched on 2
Generator
Protection Beckwith M- Fluke Multitester, ISA Contact Cleaner, brush
1 3425 Function test Neutral Grounding Transformer 2 Dodi, Ari Catur Ridwan, Thaif DRTS 66, Tools Set seal tape IK-TJ.02.008 100% 100%
Relay Panel 3
Generator Unit
2 Protection Transformers A Check setting and record 2 Dodi, Ari Catur Ridwan, Thaif Fluke Multitester, ISA Contact Cleaner, brush IK-TJ.02.008 50% 50%
Relay Panel 6 Beckwith M- DRTS 66, Tools Set seal tape
3310
Function test 2
Function test 2