Global Wind Power ltd.

PREVENTIVE MAINTENANCE PLAN CUM CHECK LIST


Machine Name : Transfer Trolly Period : 2019-2020 Doc No: GWPL/MAINT/D/08
Rev : 1
Machine No: Date : 15.07.2019

Sl Check Details
Description Frequency
No Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

1 P
Clean the trolley with dry
compressed air.Tighten all Monthly A
terminal screw .
Sign
2 P
Check repair/replace power
input cable. Check the cable Monthly A
condition.
Sign
3 P
Check operation of limit
switches, push buttons and Monthly A
selector switch.
Sign
4 P
Check greasing between gear
Monthly A
and pinion.
Sign
5 P
Tighten the fasteners of
wheel bearing cover & Monthly A
gearbox base bolts.
Sign
6 P
Check abbrasion on wheel
Monthly A
rim.
Sign
7 P
Check visual damage. Check
for abnormal sound while Monthly A
trolley operation.
Sign

Format No: GWPL/MAINT/F/01 Rev : 1 Date: 15.07.2019


DIFD INDUSTRIES PVT LTD
PREVENTIVE MAINTENANCE PLAN CUM CHECK LIST
Machine Name : Oxy-Fuel CNC cutting machine Doc No: DIFD/MAINT/D/00
0
Machine No: Date :

Sl No. Description Frequency


Jul Aug Sep Oct Nov Dec Jan Feb Mar

Clean the overall machine


with low pressure Monthly
compressed air.

2
Check Flash Back Arrester,
Oxygen Regulator/ DA
Monthly
Regulator, Check and clean
contact of all relay.

3
Check all plug connection
outside of the cabinet,
Tighten all terminal screw, Monthly
Check function of all push
button and selector switch.

4 Open rail axis both side


motors. Disengage the
motors and check the
Monthly
freeness of motor hinges.
Lubricant the moving part of
the hinge.

5
Open side covers of main
wheels of master and slave
side and clean the Monthly
same.Check belt tenstion &
set if required.

6 Check the torch height using


the measuring instrument
provided with the machine. If
Monthly
need to adjust torch height,
adjust it using special tools
providedwith the machine.

P : Plan ; A : Actual

Format No: DIFD/MAINT/F/00 Rev : 1 Date: 15.07.2019