Professional Documents
Culture Documents
Mr. Rajesh Kumar, Mr. Amit Mehta, Rohit Tailor Monday, January 31, 2022
ACTUAL
START END DURATION ACTUAL
PHASE TITLE START RESOURCES ISSUES COMMENTS
DATE DATE in days END DATE
DATE
cable box mounting, all cable laying and labelling work including compensating cable, sensors mounting, 29-Dec-21 8-Jan-22 11 Mr. Govid and team
furnace pipe color code changing as per compnay standard, including finishing touch on gas and water pipeline 7-Jan-22 9-Jan-22 3 Agrasen painter Mr. Ramesh
tank plateform work, pit ladder and railing work 8-Jan-22 11-Jan-22 4 Mr. Pooran Singh and team
earthing and cable connections of equipents and traceability stickers 8-Jan-22 14-Jan-22 7 Mr. Govid and team
Methanol crackerunit commissioning and test, all conveyor dry run retest 10-Jan-22 10-Jan-22 1 Mr. Pramod and team with HT Team
Quenching oil filling in tank and methanol vaporiser thermic fluid filling 15-Jan-22 15-Jan-22 1 Agrasen HT Team
leakage test perform 17-Jan-22 17-Jan-22 1 Mr. Pramod team with HT team
ALL UTILITY POINTS CHECKING 20-Jan-22 20-Jan-22 1 Mr. Pramod and HT team
WHOLE EQUIPMENT INSPECTION 27-Jan-22 27-Jan-22 1 Mr. Pramod team with HT team
DELIVERY TIMELINE
10-Dec-21 15-Dec-21 20-Dec-21 25-Dec-21 30-Dec-21 4-Jan-22 9-Jan-22 14-Jan-22 19-Jan-22 24-Jan-22 29-Jan-22 3-Feb-22 8-Feb-22
cable box mounting, all cable laying and labelling work including compensating cable, sensors mounting,
pipe line work finish,methanol connection with pump, n2 & lpg regulator mounting, Oxy probe and cabinet assembly
furnace pipe color code changing as per compnay standard, including finishing touch on gas and water pipeline
earthing pit digging work
tank plateform work, pit ladder and railing work
earthing and cable connections of equipents and traceability stickers
Methanol crackerunit commissioning and test, all conveyor dry run retest
Ducting work planning
Quenching oil filling in tank and methanol vaporiser thermic fluid filling
leakage test perform
PROGRAMMING OF FURNACE AND TESTING
DRY RUN WITHOUT ATMOSPHERE
ALL UTILITY POINTS CHECKING
HEATING TEST AS PER MANUAL
COOL DOWN AND 2ND LEAKAGE TEST
WHOLE EQUIPMENT INSPECTION
SAT AND TUS
PRODUCTION TRIAL