PROJECT SCHEDULE

PROJECT NAME START DATE

Agrasen DHF-04 Friday, December 17, 2021

PROJECT PERSONNEL END DATE

Mr. Rajesh Kumar, Mr. Amit Mehta, Rohit Tailor Monday, January 31, 2022

TIMELINE PROJECT NOTES

ACTUAL
START END DURATION ACTUAL
PHASE TITLE START RESOURCES ISSUES COMMENTS
DATE DATE in days END DATE
DATE

cable box mounting, all cable laying and labelling work including compensating cable, sensors mounting, 29-Dec-21 8-Jan-22 11 Mr. Govid and team

3" valve's transparent toughened sight glass, n2 & lpg


pipe line work finish,methanol connection with pump, n2 & lpg regulator mounting, Oxy probe and cabinet assembly 7-Jan-22 7-Jan-22 1 Mr. Pramod and team methanol connection with pump pending
regulator did not get yet

furnace pipe color code changing as per compnay standard, including finishing touch on gas and water pipeline 7-Jan-22 9-Jan-22 3 Agrasen painter Mr. Ramesh

earthing pit digging work 7-Jan-22 9-Jan-22 3 Mr.Ravindra

tank plateform work, pit ladder and railing work 8-Jan-22 11-Jan-22 4 Mr. Pooran Singh and team

earthing and cable connections of equipents and traceability stickers 8-Jan-22 14-Jan-22 7 Mr. Govid and team

Methanol crackerunit commissioning and test, all conveyor dry run retest 10-Jan-22 10-Jan-22 1 Mr. Pramod and team with HT Team

Ducting work planning 15-Jan-22 15-Jan-22 1

Quenching oil filling in tank and methanol vaporiser thermic fluid filling 15-Jan-22 15-Jan-22 1 Agrasen HT Team

leakage test perform 17-Jan-22 17-Jan-22 1 Mr. Pramod team with HT team

PROGRAMMING OF FURNACE AND TESTING 18-Jan-22 19-Jan-22 2

DRY RUN WITHOUT ATMOSPHERE 19-Jan-22 19-Jan-22 1 HT Team

ALL UTILITY POINTS CHECKING 20-Jan-22 20-Jan-22 1 Mr. Pramod and HT team

HEATING TEST AS PER MANUAL 20-Jan-22 24-Jan-22 5 HT Team

COOL DOWN AND 2ND LEAKAGE TEST 24-Jan-22 26-Jan-22 3 HT Team

WHOLE EQUIPMENT INSPECTION 27-Jan-22 27-Jan-22 1 Mr. Pramod team with HT team

SAT AND TUS 28-Jan-22 29-Jan-22 2

PRODUCTION TRIAL 31-Jan-22 31-Jan-22 1 HT Team

DELIVERY TIMELINE

10-Dec-21 15-Dec-21 20-Dec-21 25-Dec-21 30-Dec-21 4-Jan-22 9-Jan-22 14-Jan-22 19-Jan-22 24-Jan-22 29-Jan-22 3-Feb-22 8-Feb-22
cable box mounting, all cable laying and labelling work including compensating cable, sensors mounting,
pipe line work finish,methanol connection with pump, n2 & lpg regulator mounting, Oxy probe and cabinet assembly
furnace pipe color code changing as per compnay standard, including finishing touch on gas and water pipeline
earthing pit digging work
tank plateform work, pit ladder and railing work
earthing and cable connections of equipents and traceability stickers
Methanol crackerunit commissioning and test, all conveyor dry run retest
Ducting work planning
Quenching oil filling in tank and methanol vaporiser thermic fluid filling
leakage test perform
PROGRAMMING OF FURNACE AND TESTING
DRY RUN WITHOUT ATMOSPHERE
ALL UTILITY POINTS CHECKING
HEATING TEST AS PER MANUAL
COOL DOWN AND 2ND LEAKAGE TEST
WHOLE EQUIPMENT INSPECTION
SAT AND TUS
PRODUCTION TRIAL