Professional Documents
Culture Documents
RD EE Room and Pump Room
RD EE Room and Pump Room
This is to certify that MDC Buildplus, Inc. is handling over to MDC Architectural the unit stated below.
JERRYSON S. NEGRETE
MDCBP- Project Superintendent
Date: 8/8/2021
This is to certify that we have fully inspected/surveyed the above-mentioned area being handed over to us.
MONICA MALAZARTE-ADOLFO
MDC Architectural Supervisor
8/9/2021
Date:
Approved by:
8/9/2021
JONATHAN MANZANO
MDC Project Manager
`
Name: Signature:
Company: Designation:
PACKAGE/STRUCTURE/ITEM :
The following items are to be corrected to comply with the contract documents: COMPLETION
ITEM DATE DATE CERTIFIED
DESCRIPTION
NO. REQUIRED COMPLETED BY
REWORKS