Status of MMLPs

(As of 15.07.2022)

SN Site Status Recent update during last week


1 Mappedu,  Rly alignment is frozen,  DPR under scrutiny with
Chennai estimates along with DPR is RVNL
shared with RVNL  RVNL has proposed Mr. B.K.
 ‘In Principle’ for Railways Reddy as Director in the
approval received with MMLP Chennai SPV.
conditions.  SPV related documents of Mr.
 The last for bid submission B.K. Reddy has been received
for MMLP tender is in physical copy.
09.06.2022.  Standing Finance Committee
 SFC meeting was held on (SFC) MoM finalized and
09.05.2022 for approval of circulated.
MMLP Chennai project.  Foundation Stone for MMLP
Chennai laid by Hon’ble PM
on 26.05.2022.
 ESP modifications made by
consultant are under review.
2 Muddalingana  Rly alignment is frozen.  VC held with Rail Expert of
halli,  NHLML published MMLP Consultant for finalization of
Bengaluru tender on 5th Feb, 2022. rail alignment. Modified Rail
 Application for “In Principal alignment under preparation
approval” done through by the consultant.
online mode but a hard copy  PATSC (Project Appraisal and
with codal charges is being Technical Scrutiny
processed by the consultant. Committee) held on
08.06.2022.
 SFC appraisal held on
18.06.2022
 MMLP Bangalore Prebid held
on 05.07.22
 Railway proposal Online
submission made on FBD
portal as directed by SWR.

3 Machal,  Joint site visit held on  Draft feasibility report


Indore 08.02.2022 with NHLML & received from the consultant
MP Industrial Development on 26th May 2022 to NHLML.
Corporation MP Govt. has  Rail DPR yet to be received.
finalized another land
parcel at village Jamodi,
Kheda and Akolia, Tehsil
Pithampur, Dist. Dhar.
 Rly alignment under
discussion.
5 Pune Site finalized at Nigde by Maharashtra Industrial
Maharashtra Industrial Development Corporation (MIDC)
Development Corporation has proposed a new Site at
(MIDC) and informed to NHLML. Pawlevadi next to the earlier
Nigde Site.
Demarcation and coordinates

Page 1 of 3
SN Site Status Recent update during last week
received from MIDC.
 Site visit to be held on
08.07.22.

6 Coimbatore Consultant has submitted the The consultant submitted a


proposal for land selection. The revised land proposal for land
copy of the same is also shared selection on 26th May 2022.
with RVNL.
Based on the above report, Site
visit done on 16th and 17th May,
2022 to finalise the suitable site
from various 3 options.
Informed consultant to check
the possibility of further
additional area in Option-1 and
submit the report.
7 Hyderabad Site under finalisation. TSIIC (Telangana state industrial
NHLML is perusing with Govt. of infrastructure corporation) has
Telangana identified a site in Zaheer Abad.
DO letter sent to CS, Govt of
Telangana on 28.04.2022 Site visit held on 20.06.2022 at
Zaheer Abad Site. Alternate sites
to be identified.
8 Mumbai Bhayandar site is suggested. Pros & Cons of the site are being
evaluated.
NHLML has informed consultant Two land parcels were
to start the work shortlisted. Mira Bhayandar and
Bhiwandi.

9 Samba, Site finalized at Samba Invitation of RFP for a feasibility


Jammu study in process.
DPR is being invited for
preparation of Feasibility
Bids invited for Feasibility
Report
studies.
Rail alignment can be
developed towards the southern
edge of the site.
A 10 m elevation difference is
observed between the Rail
alignment and the lowest part
of the site.
A consultation with the
adjacent Industrial area is
suggested regarding the HFL
and the appropriate measures
taken to mitigate flooding.

Draft MoU shared with J&K


SIDCO and RVNL.
10 Cochin, Kochi Initial discussions started. No change
Port Trust Based on the discussions, it was
Land, agreed that the construction of
Wellington rail siding for the considered
Page 2 of 3
SN Site Status Recent update during last week
Island site in Cochin, Kochi Port Trust
Land, Wellington Island is
feasible.

Rail siding from the existing


line can be extended to the site
as the marshy land will not
need extensive additional
interventions.
Cost-benefit analysis of the
operations due to train
movement is suggested to be
reviewed during detailed
engineering assessment and the
internal layout planning in the
further stages.
11 Aurangabad, Site finalization by MIDC in Invitation of RFP for feasibility
Maharashtra Shendra Bidkin area. study in process.

Site visit is being planned in 1 st


week of June for the site
identified and communicated by
MIDC.
Bids for DPR studies invited.
12 Kanpur Rooma industrial area, a Bids invited for Feasibility
tentative site for MMLP. studies

Page 3 of 3