DIARY SHEET

NAME: Engr. Jose Nazario T. Daquigan


Project: Upgrading of Palayan-Dagupan-Bonifacio Road

DATE TASK
January 16, 2023 1. Absent
January 17, 2023 1. Site Supervision at Upgrading of CVR Nagsabaran-Ampakleng-Decabacan Road (Excavation prior to Supply and Installation of
Stone Masonry at Site 5. Supply and Installation of Concrete Shoulder at Site 6. Documentation of Electrical Post for relocation)
January 18, 2023 1. Site Supervision at Upgrading of CVR Nagsabaran-Ampakleng-Decabacan Road (Excavation prior to Supply and Installation of
Stone Masonry at Site 5. Supply and Installation of Stone Masonry at Site 2 and Site 3Supply and Installation of Line Canal
at Site 6)
January 19, 2023 1. Site Supervision at Upgrading of CVR Nagsabaran-Ampakleng-Decabacan Road (Supply and Installaton of Stone Masonry along
Site 2, Site 4 and Site 5. Supply and Installation of Line Canal at Site 6)
January 20, 2023 1. Site Supervision at Upgrading of CVR Nagsabaran-Ampakleng-Decabacan Road (Supply and Installaton of Stone Masonry along
Site 2, Site 4 and Site 5. Supply and Installation of Line Canal at Site 6)
January 23, 2023 1. Reporting at PEO
1. Site Supervision at Upgrading of CVR Nagsabaran-Ampakleng-Decabacan Road (Supply and Installaton of Stone Masonry along
Site 2, Site 4 and Site 5. Supply and Installation of Line Canal at Site 6)
January 24, 2023 1. Site Supervision at Upgrading of CVR Nagsabaran-Ampakleng-Decabacan Road (Supply and Installaton of Stone Masonry along
Site 2 and Site 5. Supply and Installation of Line Canal at Site 6)
January 25, 2023 1. Site Supervision at Upgrading of CVR Nagsabaran-Ampakleng-Decabacan Road (Supply and Installaton of Stone Masonry along
Site 2 and Site 5. Supply and Installation of Line Canal at Site 6. Supply and Installation of Concrete Shoulder at Site 6)
January 26, 2023 1. Site Supervision at Upgrading of CVR Nagsabaran-Ampakleng-Decabacan Road (Supply and Installaton of Stone Masonry along
Site 2 and Site 5. Supply and Installation of Line Canal at Site 6)
January 27, 2023 1. Site Supervision at Upgrading of CVR Nagsabaran-Ampakleng-Decabacan Road (Supply and Installaton of Stone Masonry along
Site 2 and Site 5. Supply and Installation of Line Canal at Site 6)
January 30, 2023 1. Reporting at PEO
2. Site Supervision at Upgrading of CVR Nagsabaran-Ampakleng-Decabacan Road (Supply and Installaton of Line Canal Parapet
along site 6 and Supply and Installation of Stone Masonry along Site 5)
January 31, 2023 1. Site Supervision at Upgrading of CVR Nagsabaran-Ampakleng-Decabacan Road (Supply and Installaton of Line Canal Parapet
and Concrete Shoulder along site 6)

I HEREBY CERTIFY that the foregoing entries are honestly executed to the best of my personal
knowledge.

JOSE NAZARIO T. DAQUIGAN


Engineer I

BEST CONTRIBUTION FOR THE DAY ( TO YOURSELF / TO THE WORK )

CHECKED BY: NOTED BY:

DANILO L. TOLENTINO NESTOR P. VELASCO


Engineer IV Provincial Engineer