PROJECT STATUS REPORT

Project Name "Dreams Unlocked - Scholarship Spectacular"

For Week Ending November 10,2023

Project Status
Green

Status Description As per the project plan execution phase is in progress. Currently we are
procuring and setting up the auction area. Overall project is moving as
per the defined schedule.

Activities – During the Past Week


Procure auction items.

Set up auction area

Activities – Planned for Next Week


Prepare educational materials.

Create social media content.

Project Issues
Content creation for educational material and social media is time consuming.

Project Changes
Looking for appropriate vendor empanelment options for procurement and content creation.