You are on page 1of 1

Provision of EPCC for

Surveillance Record Phase 1- 100KBOPD Field


Surface Facility Project
Iraq-Branch B9

No:HSE-003

Inspected Dept. HSSE Date 2023-02-15

Location OGM-1 flowline Responsible person Qian Hongliang

Use a bucket as a placement while welding.


Inspection

Inspector:Hussein Hisham Date: 2023-02-15


preventive measures
suggestions and
Handling

Inspector: Responsible person: 23 2 15

Using a flat base and not using rounded parts to fix on the wood plank to take the desired angle for welding
work.
Correction

Person in charge of correction:Qian Hongliang 23 2 15


Review conclusion

Reviewer: Y M D