Professional Documents
Culture Documents
Kanyariri
Kanyariri
Chairman
PCEA KANYARIRI
P.o Box 480-
KIKUYU
Dear Sir,
PROPOSED ADDITIONS & ALTERATIONS ON PLOT LR. MUGUGA KANYARIRI /683 KIAMBU
COUNTY
We have valued the work completed at site and recommend that the Eigth Interim Certificate
in the amount of Kshs. 252,383.59 be issued to the Main Contractor Messrs Jorinho Builders
Limited in accordance with the details listed below:
CONTRACT SUM : KES 5,000,000.00
Variation 625,677.00
SUB-TOTAL 2 280,426.22
DANIEL K. NJOROGE
CIVITECH LIMITED
PRELIMINARIES
Contract
Ref Item Amount Actual Amount due
1/A Insurance for the works/workmen onsite and perform 500,000.00 100% 500,000.00
1/B Scaffolding and hoist material & workmen 850,000.00 100% 850,000.00
1/C Hoarding around the work area and temporary screen 250,000.00 100% 250,000.00
1/D Consumables ,office overheads,supervision of the works 65,000.00 95% 61,750.00
1/E Material tests and samples for the approvals 30,000.00 100% 30,000.00
1/F Water for the works 100,000.00 100% 100,000.00
1/G Electricity for the works 80,000.00 100% 80,000.00
1/H Safety & protection clothing for the worksmen 75,000.00 100% 75,000.00
1/I Sanitary services 60,000.00 95% 57,000.00
1/J Sign board 50,000.00 0% 0.00
1/K Protection of existing services (access road,undergrou 80,000.00 100% 80,000.00
1/L Cleaning site during progress and after construction 60,000.00 95% 57,000.00
Demolitions
Demolitions 114,000
New works
Walling
Concrete Supertructure
Reinforcement
Formwork
Gazing Variation
Total cost for glass materials +putty/tape +transport 1 Item 494,447 494,447
Add for labour (cutting + fixing + scaffolding) 1 Item 215,000 215,000
Demolitions
Wall Demolitions pg DM/1-a 50,000.00 100% 50,000.00
Ring Beam Demolitions pg DM/1-b 10,000.00 100% 10,000.00
Entrance porch demolitions pg DM/1-c 10,000.00 100% 10,000.00
Doors Ditto pg DM/1-d 5,000.00 100% 5,000.00
Roof demolitions pg DM/1-e 60,000.00 100% 60,000.00
Windows casement demolitions pg DM/2-a 4,200.00 100% 4,200.00
Cut through walls for window opening pg DM/2-b 12,000.00 100% 12,000.00
Floor hacking pg DM/2-c 17,900.00 0% 0.00
Demolition of mabati structures pg DM/2-d 8,000.00 40% 3,200.00 154,400.00
Substructures(Provisional)
Site clearance pg CB/4-a 0.00 0% 0.00
Excavation pg CB/4-B-F 33,000.00 100% 33,000.00
Filling pg CB/4-H 4,800.00 100% 4,800.00
Disposal pg CB/4-G/5-A 6,750.00 20% 1,350.00
Hardcore /blinding pg CB/5-B-C 12,900.00 100% 12,900.00
Anti Termite pg CB/5-D 860.00 100% 860.00
Planking & strutting/water disposal pg CB/5-E-F 6,000.00 100% 6,000.00
Plain concrete pg CB/5-g/h 5,520.00 100% 5,520.00
Vibrated concrete pg CB/6 a-f 87,827.00 100% 87,827.00
Reinforcement pg CB/6 g-j 21,360.00 100% 21,360.00
Fabric Mesh pg CB/6 k 61,050.00 100% 61,050.00
Formwork pg CB/6-l& 7 a-c 7,340.00 100% 7,340.00
Foundation walling pg CB/7 -d 24,750.00 100% 24,750.00
Damproofing pg CB/7 e-f 5,880.00 100% 5,880.00
Plinths pg CB/7 g-h 3,570.00 0% 0.00 272,637.00
REINFORCED CONCRETE
Roof Beams pg CB/ 85,050.00 100% 85,050.00
Columns pg CB/ 18,900.00 100% 18,900.00
Reinforcement various sizes pg CB/ 133,960.00 100% 133,960.00
Formwork pg CB/ 41,520.00 100% 41,520.00
279,430.00
WALLING
External Walling
200mm thick natural stone walling pg CB/ 61,650.00 100% 61,650.00 61,650.00
ROOFING
Rain Water Goods
Gutters/Downpipes pg CB/12 104,800.00 85% 89,080.00 89,080.00
FINISHES
Floor Finishes
Screed pg CB/18 38,880.00 0% 0.00
Tiles pg CB/ 43,800.00 0% 0.00
Terrazzo pg CB/ 224,200.00 0% 0.00
Wall Finishes
Mazeras Cladding pg CB/ 12,750.00 0% 0.00
Backing pg CB/ 2,040.00 0% 0.00
Plaster pg CB/ 81,600.00 90% 73,440.00
Cornices Plaster pg CB/ 20,350.00 0% 0.00
External wall finishes
Plaster to walls/concrete pg CB/ 7,680.00 85% 6,528.00
Key pg CB/ 19,920.00 85% 16,932.00 96,900.00
SUMMARY
PRELIMINARIES 70,250.00
DEMOLITIONS 154,400.00
SUBSTRUCTURES 272,637.00
CIVITECH LIMITED
P.O. Box 3825 - 00100 REINFORCED CONCRETE 279,430.00
NAIROBI - KENYA
WALLING 61,650.00
ROOFING(DRAINAGE) 89,080.00
WINDOWS 779,139.00
FINISHES 96,900.00
REINFORCED CONCRETE
Beams & Ring beams pg CB/31 81,900.00 15% 12,285.00
Slab pg CB/31 80,997.00 15% 12,149.55
Staircase pg CB/31 11,654.00 0% 0.00
Columns pg CB/31 12,600.00 15% 1,890.00
Reinforcement various sizes pg CB/31 195,800.00 15% 29,370.00
Formwork pg CB/32 166,320.00 15% 24,948.00
80,642.55
WALLING
External Walling
200mm thick natural stone walling pg VB/34 150,780.00 15% 22,617.00 22,617.00
ROOFING
Rooof pg VB/3 0.00 0% 0.00 0.00
WINDOWS
Windows pg VB/ 608,667.00 15% 91,300.05 91,300.05
FINISHES
Floor Finishes
Screed pg VB/44 33,360.00 0% 0.00
Tiles pg VB/44 190,750.00 0% 0.00
Wall Finishes
Backing pg V B/44 11,400.00 0% 0.00
Plaster pg V B/45 78,720.00 15% 11,808.00
Ceiling Plaster pg V B/45 14,160.00 15% 2,124.00
External wall finishes
Plaster to walls/concrete pg CB/ 7,680.00 15% 1,152.00
Key pg CB/ 31,800.00 15% 4,770.00 19,854.00
SUMMARY
SUBSTRUCTURES 86,937.00
CIVITECH LIMITED
P.O. Box 3825 - 00100 REINFORCED CONCRETE 80,642.55
NAIROBI - KENYA
WALLING 22,617.00
WINDOWS 91,300.05
FINISHES 19,854.00
FOUL DRAINAGE
Omit
Roof covering
Add
19 Timber batterns 50 x 50mm - for decra see delivery notes paid 348,000.00
#REF!
MATERIALS ON SITE
Materials on site
Item Description Unit Qty Rate Amount % Amount
Complete Complete
SUBSTRUCTURES (VARIATIONS
Substructures
Note the depth allowed in the Bill of quantities for mass excavation is 300mm
deep. While actual is 1100mm deep. Thus extra depth of 800mm was
excavated to reach firm ground
Disposal
B Return fill & ram 47 m3 30 1,410 100% 1,410
C Load Wheel and deposit on site as directed 141 m3 100 14,100 100% 14,100
Superstructures
Block opening with masonary wall including plastering SM 8 650 5,200.0 100%
F and paint work 5,200.00
Fix new steel and relocate window to a new position No. 3 2000 6,000.0 100%
G complete making good the area 6,000.00
CIVITECH LIMITED
P.O. Box 3825 - 00100
NAIROBI - KENYA
Item Description Qty Unit Rate Amount Amount
Complete
STUDIO (VARIATIONS
4 Architraves 36 Lm 30 1,080
Steel doors
SUMMARY VARIATIONS
Fix only
Windows-grills
LABORATORY WORKS
Cut thro masonary walls to make door & window openings and make good the area
1.0 >10sm Item 6,500.0
1.1 Block opening with masonary wall including plastering and paint work SM 8 500 4,000.0
1.2 Fix new steel & timber doors and relocate window to a new position complete No. 3 2000 6,000.0
making good the area
1.4 Drainage works to carry effluent from laboratory to soakpit (excavation ,lay Item 20,000.0
pipework,connect,testing & backfill and construction of inspection chambers & gully
traps
Cabinets
1.6 Prepare ,cut and construct bench cabinets and doors complete with framing,locks No. 20 1500 30,000.0
and paint with approved colour
1.8 Drainage works to carry effluent from laboratory to soakpit (excavation ,lay Item 20,000.0
pipework,connect,testing & backfill and construction of inspection chambers & gully
traps
TOTAL #REF!
Item Description Unit Qty Rate Amount
SUBSTRUCTURES (VARIATIONS
Substructures
Note the depth allowed in the Bill of quantities for mass excavation is 300mm deep. While actual
is 1100mm deep. Thus extra depth of 800mm was excavated to reach firm ground
Disposal
B Return fill & ram 47 m3 30 1,410
Superstructures
Hack existing concrete slab to adjoin with new slab 600mm wide x
D 9000mm long Item 15,000
Cut thro masonary walls to make door & window openings and make
6,500
E good the area >10sm Item
F Block opening with masonary wall including plastering and paint work SM 8 650 5,200
Fix new steel and relocate window to a new position complete making No. 3 2000 6,000
G good the area
12,500
H Excavate/Hack for PPR pipes to connect laboratory to tank point Item