Method Statement Submittal Form

RSG-CN-FRM-0012

RED SEA PROJECT

General Information
Non-Residential Assets
R03-
Program Name R03- The Turtle Bay Project Code Project Name Design and Build Villag
C02C02
Neighborhood Centers.
Contract ref. R03-C02C02-8100 Package 05
Submittal No. R03-C02C02-AAP-MTS-CI-0007 Version 00 Date 05-Dec-2023
Contract No. R03-C02C02-8100
Contract Description Village Center, Professional Neighborhood and Non-Professional Neighborhood Center

Contractor
Method Statement for
Contractor Name Abdul Mohsen A.H Al Tamimi Subject Reinforcement & Concrete Works

Specification No. N/A Drawing Ref. N/A


Other (please
Discipline Civil
specify)
Planned Date of Work Submitted For: ☒ Approval ☐ Information
Contractor Authorized Representative

Anas Fathi 05-Dec-2023


Name Signature Date

Design Consultant - Comments


Comments:

Date
Name Signature Date

Engineer’s - Comments
Comments:

Date
Name Signature Date

Status Code

RSG-CN-FRM-0012
Rev. 00, 16 Nov 2022 Page 1 of 2
Engineer’s - Comments

☐ Accepted ☐ Accepted with Comments ☐ Revise and Resubmit

☐ Rejected ☐ Review not Required

RSG-CN-FRM-0012
Rev. 00, 16 Nov 2022 Page 2 of 2
Owner:

Owner’s Engineer

Contractor

Package 5 - Village Center, Professional & Non- Professional


Neighborhood Center
Package:
Main Contractor Building Work- R03-C02C02-8100

FOR APPROVAL

00 For Review Mahmoud Hagag Eslam Elmwafy Anas Fathi 05-12-2023

REV DESCRIPTION PREPARED CHECKED APPROVED DATE

Title:
Method Statement for Reinforcement & Concrete Works

DOCUMENT No.: R03-C02C02-AAP-MTS-CI-0007 Rev 00

1|Page
PROJECT:

Package 5 - Village Center, Professional & Non-Professional Neighborhood Center


Owner: Contractor Consultant: Rev:00

Page
2 / 2

Revision Record

Version Date Section Page Description of Modification

00 05-12-2023 All All First submission

2|Page
Table of Contents
1. INTRODUCTION.................................................................................................................................................. 4
2. SCOPE OF WORK. ............................................................................................................................................... 4
3. ABBREVIATIONS. ................................................................................................................................................ 5
4. REFERENCE DOCUMENTS. ................................................................................................................................. 5
5. RESPONSIBILITIES. .............................................................................................................................................. 6
5.1 Project Manager:.................................................................................................................................. 6
5.2 Construction Manager: ........................................................................................................................ 6
5.3 QA/QC Manager: ................................................................................................................................. 7
5.4 Site Engineer: ....................................................................................................................................... 7
5.5 QA/QC Engineer: .................................................................................................................................. 8
5.6 HSE Manager: ...................................................................................................................................... 8
5.7 Environmental Engineer: ..................................................................................................................... 8
6. Equipment & tools required: .............................................................................................................................. 8
7. Manpower Required: ......................................................................................................................................... 9
8. Methodology: .................................................................................................................................................... 9
8.1 Survey Works: ..................................................................................................................................... 9
8.2 Blinding concrete Works: .................................................................................................................. 10
8.3 Installation & Application of Water proofing: .................................................................................. 10
8.4 Formwork & Rebars Installation Works: ........................................................................................... 10
8.5 Formwork & Rebars Installation Works: ........................................................................................... 11
8.6 Cast in Placement of Concrete:......................................................................................................... 11
8.7 Construction Joint: ............................................................................................................................ 12
8.8 Surface Finishing: .............................................................................................................................. 12
8.9 Curing & Protection: ......................................................................................................................... 12
8.10Clean up: ........................................................................................................................................... 12
9. ATTACHMENTS. ............................................................................................................................................... 12

3|Page
1. INTRODUCTION.

This Method Statement is for the “Concrete works” on Package 5 of the TBV Mixed Use - Village Centre,
Professional Neighborhood Centre, Non-Professional Neighborhood Centre.

The Method Statement is to ensure the activity is carried out according to the relevant H&S, Environmental,
QA/QC procedures, and the specific product manufacturer’s recommendations.

The document shall detail all the information, precautions, preparation material, tools, equipment,
manpower and supervision necessary to ensure a safe and compliant execution of the Concrete activity.

The Turtle Bay Village location is shown in the plan below: -

TURTLE BAY LOCATION

2. SCOPE OF WORK.

The scope of this Method Statement is for the Concrete works under all buildings in the Village Centre,
Professional Neighborhood Centre, Non-Professional Neighborhood Centre.

It covers the requirements for material, training, equipment, protection, preparations, execution, and final
inspection related to the concrete works.

4|Page
MIXED USE FACILITIES WITHIN THE TURTLE BAY VILLAGE MASTERPLAN

3. ABBREVIATIONS.

Term Expansion

RSG Red Sea Global


SC Saud Consult
AMT Abdul Mohsen Al Tamimi Construction Co.
ITP Inspection & Test Plan
PPE Personal Protective Equipment
QA/QC Quality Assurance/ Quality Control
GPS Global Positioning System
HSE Health, Safety and Environment

4. REFERENCE DOCUMENTS.

 RSG Employer's Requirements - TBV Package 5

 RSG QA/QC.

 Project Specification

 Emergency Preparedness and Response Procedure: RSG-HS-ADM-0007

 Health and Safety Incident Reporting and Investigation: RSG-HS-ADM-0008

5|Page
 Pre-Task Planning Risk and Opportunity Management: RSG-HS-ADM-0009

 Temporary Works: RSG-HS-COS-0021

 RSG Contractor Health and Safety Requirements: RSG-HS-GEN-0003

 Health and Safety Management System Manual: RSG-HS-MNL-0001

 Working at Height: RSG-HS-COS-0002

 Scaffolds and Portable Ladders: RSG-HS-COS-0008

 CESMP: R03-C02C02-AAP-PLN-EN-0001

 Environmental Waste & Metrics Procedure RSG-ENV-PRO-0004

5. RESPONSIBILITIES.

The Contractor shall: -

 Contact and coordinate with all concerned authorities to obtain the required work permit

 Supply the material as per the formal approval.

 Supply all necessary, tools, equipment, etc.

 Prepare and have approved a task specific Method Statement

 Manage the works in compliance with the Method Statement.

Specifically;

5.1. Project Manager:

 Shall determine all the requirements needed to comply with Quality, Health & Safety standards
and regulations as required and that they are available at the task location.

 Shall ensure that the detail of this Method Statement is understood and implemented

 Shall coordinate with the Site Engineer and/or Construction Manager to ensure that the
necessary resources to implement the approved Method Statement have been allocated to the
task and are available at the task location.

5.2. Construction Manager:

 Shall be responsible for the organization and coordination of the work detailed in this method
6|Page
statement.

 Shall establish and maintain a direct line of communication with the Employers team.

 Shall be fully conversant with all the relevant Health, Safety and Environment requirements for
the task.

 Shall ensure that all senior site staff are fully conversant with the relevant requirements of
current requirements and the “Health, Safety and Environment Management Plan” and that all
are assigned appropriate duties and responsibilities to assist in its effective implementation.

 Shall identify all risks and implement all necessary plans and procedures to mitigate the risk to
the maximum practicable extent.

 Shall ensure all arrangements are implemented to ensure the task is executed in full compliance with
the Project “Health, Safety & Environment Management plan.

5.3. QA/QC Manager:

 Shall ensure that the concrete activities are conducted according to the approved Method
Statement and project contract documents.

 Shall be responsible for the implementation of this procedure.

 Shall be responsible for the inspection, preparation of all documents and compiling them for the
inclusion in the final documentation packaged

5.4. Site Engineer:

Under the guidance and supervision of the Construction manager the site engineer is responsible
for:
 Shall ensure that activities are conducted according to the approved Method Statement and project
contract documents.

 The execution of the works detailed in this method statement.

 Ensuring that at all times that the concrete work will be carried out under the control of
competent works supervisor. Assigned supervisor shall have extensive experience in
construction works undertaken.

 Pre task briefing shall be provided to the relevant supervisor, Forman & all operators prior to
start of work activity and to be recorded.

 Identify Equipment to be operated within the defined limits and tolerances.

 Reviewing the Drawings, prepare the required reports, other deliverables, and quantities
calculations.

7|Page
5.5. QA/QC Engineer:

 QA/QC staff shall be independent of construction, with authority commensurate with the post
responsibility for overall quality control/assurance.

 QA/QC staff shall be responsible to assist/advise the construction team to ensure all works
comply with specified requirements and to monitor implementation of the controls as required.

 Shall monitor the quality of the work according to work plan and send report to his line manager.

5.6. H&S Manager:


 Safety staff shall be independent of construction, with authority commensurate with the post
responsibility for overall quality control/assurance.

 Shall ensure that all the activities related to the specified task are being followed safely.

 All workers are wearing PPE. Identify and take control measure for the risks associated with the
hazard.

5.7. Environmental Manager:

 Shall stop work immediately if an unacceptable impact on the environment is occurring or likely
to occur.

 Shall be Responsible for ensuring the preparation of site specific environmental and regulatory
documentation and for regular review and improvement of such documentation, as appropriate.

 Where a control measure used to limit environmental harm is found to be inadequate, or a


potential incident is likely, he shall request remedial works to be carried out.

 Ensure materials being used on the site are environmentally friendly and safe.

 Responsible for ensuring that appropriate levels of environmental resources are available to
conduct environmental management functions.

6. Equipment & tools required:

 Concrete Mixer Truck

 Concrete Pump

 Concrete Vibrator

 Measuring Tape

 Sprit Level
8|Page
 Concrete Leveling Rod

 Hand Shovel

 Wheel Borrow

 Surface Finishing Tools

 Cylinders for concrete sampling

7. Manpower Required:

 Project Manager.

 Construction Manager.

 QC Manager.

 H&S Manager.

 Environmental Manager

 Surveyor.

 Site Engineer

 QC Engineer

 Labors

 Approved third party technicians.

8. Methodology:

8.1 Survey Works:

 Initially survey works shall be properly established and secured throughout the entire duration
of works.

 The Survey data shall be recorded and approved by the supervision Consultant.

 Based on these established data, control points Surveyor with the supervision of Site Engineer
shall locate the exact coordinates & Level of the area for raft foundation base on the approved
drawing.

 For verification of Survey coordinates have to be raise WIR to Supervision Consultant for
approval.

9|Page
8.2 Blinding concrete Works:

 The area shall be marked by the surveyor as per the approved drawing.

 Unti-termite to be applied on compacted soil and FDT should be pass.

 Polyethylene sheet shall be provided prior to pouring blinding concrete thickness as mentioned
in approved drawing.

 After the formwork is installed, it shall be inspected by consultant surveyor.

 Third party technician will be available during casting blinding concrete.

 Surface finishing for blinding Concrete as per the RSG specification

8.3 Installation & Application of Water proofing:

 AMT will Submit the Separate Method Statement of Waterproofing Installation & Application as
per the RSG Specification & Drawings.

 AMT shall verify that the Concrete Surface shall be dry free of oil, dust, and debris and all sharp
protrusions shall be ground smooth and all hollows & honeycombs voids

8.4 Formwork & Rebars Installation Works:

 After the waterproofing, geotextile (If Applicable), AMT shall start the installation of
reinforcement for raft foundation.

 Only approved materials shall be used and fabricated for the steel reinforcement of the
foundation and other cast in concrete structure.

 All reinforcement will be stored under cover on timber over concrete or steel crib support
suitably spaced and of sufficient height to keep the steel at least 200mm above ground level.

 Reinforcement will be protected from all aggressive elements, including chlorides and moisture,
by covering with suitable protection material. It will be neatly separated in sizes and clearly
marked with its diameter.

 Clean reinforcement to remove loos rust and mill scale, earth and other materials which reduce
or destroy bond with the concrete.

 The reinforcement bars will be cut and bent accurately to the dimensions and shapes as per the
approved drawings for foundation.

 Reinforcement bars will be shifted and fixed in place for foundation.

10 | P a g e
 Construct formwork for the raft foundation to the exact size, shapes, lines and dimensions as
per the drawing as required to obtained accurate alignment, location, grades, & Levels.

 Fabricate formwork for raft foundation for easily removing without hammering or praying
against the concrete surface.

 Formwork installation & keep concrete cover as per the approved SDWs.

 The formwork and reinforcement to be inspected by supervision consultant team as per trades
(Survey, Civil, Mech, Electrical) checked & verify to proceed the Concrete Placement.

8.5 embedded item Installation Works:

 All embedded item for civil & MEP activities shall be placed/inspected by QC inspectors ensuring
materials comply with specification.

 Installation of the anchor bolts according to the approved SDWs, setting out and level by land
surveyor.

 The anchorages will be attached with the reinforcement steel in below of columns and a
template will be installed above to prevent the displacement of the anchorages during
concreting (Not welded on structural rebar)

 The WIRs to be submitted to Supervision Consultant Shall Inspect formwork, rebar steel,
embedded metal (Base Plate) and anchor bolts prior to concrete placement. Construction & QC
Team has to make sure approval of these WIRs prior to concrete.

8.6 Cast in Placement of Concrete:

 Before placing of concrete all quality checks are to be completed and the “approval to concrete”
instruction issued by contractor. Once delivered to site the concrete will be placed in Direct.

 AMT shall provide proper access for Concrete Mixer or Pump to Easley poring the Concrete.

 Proper PPE as per work requirement to be provided to all workers and ensured its use during
work. Check there start concrete pouring: the roughness and cleanliness of the surface.

 Do not drop concrete freely for more than 1.5 m, nor allow it to drop freely through congested
rebar areas which could cause segregation.

 Concreting once started shall be continuous until the pour is completed. Concrete shall be
placed in successive horizontal layers of uniform thickness ranging of 200 mm.

 When the casting is going on, the site foreman should be arranged to check the displace of the
formwork, if any change, the concrete should be stopped and the treatment should be
11 | P a g e
completed before the initial setting time, the steel fixer should be arranged to check the location
of the rebar, and the surveyor should be arranged to check the location of the embedded Items.

 After setting out of concrete, Curing shall be done frequently.

 Third party technician will be available during casting concrete to note the temperature & slump
value.

 AMT QC shall witness the temperature & Slump test to make sure the concrete is as per the
approved mix design.

 Concrete mixer truck drivers shall not be allowed to wash the truck at site, it should be washed
in the designated washing area.
8.7 Construction Joint:

 The position and detail of the construction joints shall be subject to the approved Drawings
Section & Specification.

8.8 Surface Finishing:

 All finishing work shall be carried out in accordance with RSG General Specification.

 AMT Will apply the Rough Formed Finish concrete surfaces to not exposed to view in the finished
Work or concealed by other construction.

8.9 Curing & Protection:

 Freshly placed concrete shall be protected from rain, dust storms, chemical attack, and the
harmful effects of heat, wind, flowing water, vibrations and shocks.

 This protection shall continue until the concrete is sufficiently set such that it is no longer
damaged.

 Curing compound to be applied according to RSG specification and plastic sheet to prevent any
evaporation of water content of concrete

8.10 Clean up:

 Upon completion of work, leave project site clear of debris and surplus materials resulting from
work. All debris and surplus materials shall be disposed of, off plant limits in a manner meeting
all local authority requirements.

9. ATTACHMENTS.

 JSA & Risk Assessment


12 | P a g e
Job Safety Analysis
RSG-HS-FRM-0001

RED_SEA_GLOBAL

Instructions for completing Job Safety Analysis (JSA) form

Section I -Enter general information about the site and job task.

Section II - Determine whether any of these operations apply to the job task to be performed. Make note of any special training, permit, certification, and risk assessment requirements.

Section III - Identify any human/organizational factors that could impact the ability to perform the work safely.

Break the job down into steps - Be as specific as possible. Write each job step in a new row of column A (Activity/Step). It’s a good idea to leave an extra row between steps in case you
1 need them later. Add additional rows to the table as needed, or if completing the JSA on paper, print additional copies of the sheet to accommodate all job steps.
Determine the hazards associated with each job step and write them in column B (Hazards). Use the examples of hazards provided below to trigger your thinking about different types of
2 hazards and energy sources.
List any control measures that will be taken to ensure that step is done safely in column C (Control Measures). Use the control measure examples and hierarchy provided to trigger your
thinking about different types of controls and their effectiveness at reducing risk. Controls toward the top of the table tend to be more effective at minimizing the severity and/or likelihood
3 of an event than the controls toward the bottom of the table. If this job involves a Life Crucial Operation, continue to step 4. Otherwise, repeat steps 2-3 for each of the job steps identified,
Considering the hazards involved and the control measures that will be in place, determine the worst credible severity of an incident that could result from this job step. Use the severity
4 table provided. Write the severity number in column D (Severity).
Considering the hazards involved and the control measures that will be in place, determine the likelihood that an incident will result from this job step. Use the likelihood table provided.
5 Write the likelihood number in column E (Likelihood).

Multiply the severity number by the likelihood number and enter the product in column F (Risk).
6

Consider the risk rating against the thresholds provided in the Overall Risk Ratings.
7

P Very low and low risk ratings of 1-2. This level is generally considered acceptable provided that all control measures are applied.

Medium risk ratings of 3-9. Medium risk requires a planned approach to control the hazard and applies additional controls if required. Action taken must be documented on the
P
risk assessment form.
High and Very High-Risk ratings of 10-25. For all high and very high risk, Column G (Additional control measures) must be implemented to further reduce the risk to a medium or
P low level. Such activities shall not be proceeded until applying additional control measures. The Construction Director/Manager or facility Manager must personally review the
activities with a High or Very High residual risk score and approve additional control measures by signing off the JSA
Repeat steps 2-7 for each of the job steps identified.
8
Section IV - Provide the name, company, and title of those who prepared and reviewed/approved this form in the signature box provided. The Construction Director/Manager or facility Manager must
review and approve the additional control measures that have a High or Very High-Risk rating before proceeding the task. Additional space is also provided for crew members to sign the JSA if desired.

Reference Table in completing Section III – Job Safety Analysis (Column B – Hazard)

Biological & Electrical Chemical Gravity/Height Mechanical & Motion


Environmental Arc Flash Air Emissions Equipment Tipping/Collapsing Being Thrown Off/Under Equipment
Altitude Buried Utilities Chemical Products; Excavation/Trench Disintegration of Moving Components
Animal Bite/Sting Damage to Leads/Cables •Carcinogenic Falling Objects Driving/Vehicle Traffic
Blood-Borne Pathogens Damage to Switches •Combustible/Flammable Floor Openings/Edges Ejection of Workpiece/Debris
Contaminated Food/Water Energized Circuits/Conductors •Explosive Grating Removed Entanglement
Insect-Borne Disease Inadvertent Energization •Toxic Inadequate Support Friction
Pests Lack of Isolation/Grounding •Corrosive Lack of Access Ladders/Stairs Movement/Shifting
Poisonous Plants Missing/Damaged Insulation •Reactive Suspended Load Moving Parts
Precipitation Overhead Lines Client/Process Chemicals Unstable/Insecure Materials Pinch/Crush Points
Temperature/Humidity Overload of Circuits Lack of Containment Work Above/Below Others Projectiles
Unsanitary Conditions Stored Energy (Batteries/Capacitors) Leakage/Spills Work at Height/Fall Hazards Rotating Equipment
Weather Water Near Electrical Conductors Material Incompatibility Walking/Working Surface; Sharp Edges, Corners, or Points
Produced/Disturbed by Work; •Slippery Shearing
•Asbestos •Uneven Stored Energy (Springs/Accumulators)
•Lead •Obstructed Striking
•Silica •Steep Trapped Between Equipment and Fixed
•Welding Fumes •Moving/Swaying/Pitching Structures
•Dust •Insufficient/Unstable Unexpected/Uncontrolled Movement
Water Discharges
Wastes Generated;
•Hazardous
Pressure Work Environment
•Non-Hazardous
Abrasive Blasting Cluttered
Compressed Gases Confined Space
High Pressure Fluid Damaged Tools/Equipment
Pressure Testing Entrapment
Pressure Washing/Blasting Erosion
Hazardous Atmosphere;
•Oxygen Rich/Deficient
•Contaminants
Ignition Sources
Inadequate Ventilation
Poor Lighting/Glare

Job Safety Analysis


Rev.00, 30 March 2023 Page 1 of 10
Job Safety Analysis
RSG-HS-FRM-0001

RED_SEA_GLOBAL

Radiation Poor Lighting/Glare Sound Ergonomic


Intense Light Restricted Access/Egress Continuous Noise Awkward Postures/Movement
Lasers Runoff Intermittent Noise Excessive Force/ Exertion
Microwaves Extreme Noise Heavy/Awkward Load
Naturally Occurring Impact Noise Repetitive Motion
Radioactivity Radioactive Same Position
Material Vibration
X-Rays

Job Safety Analysis


Rev.00, 30 March 2023 Page 2 of 10
Job Safety Analysis
RSG-HS-FRM-0001

RED_SEA_GLOBAL

Reference Table in completing Section III – Job Safety Analysis (Column C – Control Measure)

Controls Examples
Elimination
Make connections at ground level before erecting a structure to eliminate work at height
(Remove the hazard altogether)
Remove a dangerous machine from service
Provide power outlets to avoid trailing cords

Substitution
(Replace the material/process with a less
Use latex rather than oil-based paints
hazardous one)
Reduce energy, such as speed, force, amperage, pressure, and temperature
Use water-based detergents instead of organic solvents

Engineering/Isolation
Ventilation Isolate hazardous energy sources Secondary containment
(Design effective control measures to protect
people and the environment)
Machine guarding Interlocks Barriers

Enclosures Platforms and guardrails Improve lighting


Warning
(Alert people to the hazards)
Circuit breakers Exclusion zones

Signs Horns Labels High visibility paint

Backup alarms Beepers Tags

Administrative
Work rotation to minimize exposure Good housekeeping practices
(Provide training, procedures, etc.)

Inspect safety equipment Training and supervision

PPE
Safety glasses Fall harness and lanyards Respiratory protection
Less (Personal Protective Equipment)
Effective
Hearing protection Gloves High visibility vests

Reference Table in completing Section III – Job Safety Analysis (Column E –


Reference Table in completing Section III – Job Safety Analysis (Column D –Severity)
Likelihood)

Impact On Chances of
Severity Level Likelihood Level Probability
Occurrence
People Equipment / Property

Extensive losses of high value


equipment/property Likely to occur within the next 1
Almost year.
Major 5 Single / Multiple fatalities 5 0 in 100
Loses exceeding SAR 3,750,000; or Certain More than 80% chance of
Major unplanned impact on budget and occurring
schedule

Losses of equipment/property that


cannot be readily replaced; or Likely to occur within the next 2
Injury or illness resulting in
years.
Significant 4 permanent total or partial Likely 4 0 in 1,000
Losses exceeding SAR 375,000; or More than 60% and less than 80%
disability
Significant unplanned impact on project chance of occurring
budget

Loss of equipment that can be readily


Likely to occur and may do so
Injury or illness resulting in replaced; or
within the next 3 years.
Modrate 3 medical treatment or temporary Possible 3 1 in 10,000
More than 40% and less than 60%
disability/loss of function Losses exceeding SAR 37,500; or
chance of occurring
Minor impact on the budget

Unlikely to occur and may do so


Loss of equipment that can be readily
Injury or illness requiring first-aid within the next 5 years.
Minor 2 replaced, or Rare 2 1 in 100,000
treatment only More than 20% and less than 40%
Losses less than SAR 37,500
chance of occurring.

Extremely unlikely to occur within


Near Miss/no impact or damage to the next 5 years.
Negligible 1 Near Miss/no harm Unlikely 1 1 in 1,000,000
equipment or property Less than 20% chance of
occurring

Job Safety Analysis


Rev.00, 30 March 2023 Page 3 of 10
Job Safety Analysis
RSG-HS-FRM-0001

RED_SEA_GLOBAL

Reference Table in completing Section III – Job Safety Analysis (Column F – Risk)
Risk Matrix
Very Low Low Medium High Very High
Severity
Likelyhood 1 2 3-9 10-16 20-25
1-Negligible 2-Minor 3–Moderate 4-Significant 5-Major
Medium Hgh High High High High and Very High-Risk ratings of 10-25.
5 – Almost Certain
(5) (10) (15) (20) (25)
Additional control measures must be implemented to further reduce the High
Medium Medium High High High
4 – Likely and very high risk to acceptable level.
(5) (5) (12) (16) (20)
Medium Medium High High Note: The Construction Director/Manager or Facility Manager must personally
3 – Possible -5
(5) (5) (12) (15) review the activities with a High or Very High residual Risk score and approve
Low Medium Medium Medium High
2- Rare suitable additional control measures by signing the JSA.
(2) (5) (5) (8) (10)
Very Low Low Medium Medium Medium
1 – Unlikely
(1) (2) (5) (4) (5)

Job Safety Analysis


Rev.00, 30 March 2023 Page 4 of 10
Job Safety Analysis
RSG-HS-FRM-0001

RED_SEA_GLOBAL

Section I – General Information


Emergency Procedure

Energency Contact Name Energency Contact Phone Number

Primary Contact Mahmoud Hagag Primary Contact 550817360

Secondary Contact Syed Saddam Secondary Contact 545823228

Details

Company Name
Program / Facility / Operations Turtle Bay Village TBV / Red sea Global Abdul Mohsen Al Tamimi Contracting Company

Date
Project Name / Facility Details RO3-CO2CO2 TURTLE BAY-Package 05 5/12/2023

Category
JSA /Risk Assessment Title Reinforcement & Concrete Works New Revised

Building
Specific Location Village Center, Professional & Non-Professional Neighbourhood Centers. NA
Concrete Mixer, Concrete Pump, Concrete Viberator, Power Tools,Concrete surface finishing
Area --
Plant Tools & Equipment Requiredtools, Survey equipments.

Work Scope/Description Reinforcement & Concrete Works

Section II – Does this job require any of the following operations?

ü Requires formal/special training n Requires certification or Competent/Qualified Person designations

 Requires a permit/form/report ∆ Life Crucial Operations = Requires full Risk Assessment

Details YES Details YES

Aerial Lifts ü ∆ Cranes - Critical lift   n ∆

Confined Space ü  n ∆ Hot Work  


Loading/Unloading
Dismantling and Demolition n ∆
Material
Electrical Hazards ü  n ∆ Noise Exposure 
Powered Industrial
Excavation/Trenching ü  n ∆  n ∆
Trucks
First Line Breaks ü  n ∆ Radiation Area Work   n
Grating/Floor Plate/ Guardrail
 ∆ Respiratory Hazards 
Removal
Hazardous Energy Control ü  n ∆ Roof Work   n ∆
Hazardous Materials
ü  n Scaffolding  n ∆
Asbestos & Lead Work
Hazardous Materials
ü n Site/Vehicle Traffic ∆
Crystalline Silica & Cadmium
Hazardous Waste Operations ü  Steel Erection n ∆

Heavy Equipment ü n ∆ Work at Height (> 6 ft)  n ∆

Rigging, & Cranes ü n ∆ Other

Section III– Job Safety Analysis

(D) (E) (F) (G) (H) (I) (J)


(B) Severity Likelihood Risk Additional Control Measures Severity Likelihood Risk
(A) Hazards (C)
Activity Step Control Measures

Job Safety Analysis


Rev.00, 30 March 2023 Page 5 of 11
Job Safety Analysis
RSG-HS-FRM-0001

RED_SEA_GLOBAL

Ensure the Implementation of "No permit, No


Lack of communication. work" system.
Lack of competency. Obtain a general permit under _RSG-HS-FRM-
Secure the required permit(s) 2 1 2 0 0 0
Lack of information, training & 0093.
instruction. Obtain Hot Work Permit under_ RSG-HS-FRM-
0045.

Pre-Task Planning must be followed under_


Follow the speed limit. RSG-HS-ADM-0009.
Driver must have a valid driving license. Ensure the provision of appropriate signages
Over speeding.
Use proper manual handling techniques while to navigate the driver.
Lack of competency.
handling the survey equipments. For safe manual handling techniques RSG-HS-
Manual handling
Use manual handling aids for moving COS-0006, section 5.3 must be followed.
Sharp edges.
equipments from one place to another. RSG-HS-PLC-0002_ Mobile devices usage policy
Mobilization of Machinery, Topographic Collision with vehicle / pedesrtians.
Ensure the proper PPE's to handle the materials 2 2 4 must be followed. 2 1 2
tools. Equipment, personnel, & materials. Lack of competency of driver.
with sharp edges. Ensure the provision of seperate pedestrians
Lack of information, instruction.
The use of phone shall be prohibited during way to prevent the vehicle collision with
Slips; Trips; Fall.
driving. peoples.
Ensure the provision of seperate pedestrians Remove any trailing cables ot objects to
way to prevent the vehicle collision with prevent the tripping.
peoples.

Check the work area thoroughly for any


venomous insects & reptiles.
INSECT BITE Ensure the provision & use of proper PPE's for Ensure the provision of manual handling aids
(It may cause paralyze to the worker, marking material (lime powder, spray paint to prevent the fatigue.
or fatality of worker), bottle). For safe manual handling techniques RSG-HS-
Ergonomics. Ensure the use of Right tool for Right job. COS-0006, section 5.3 must be followed.
Survey & Marking Lack of competency. The rebars using for marking must be protected 2 2 4 Ensre the provision of manual handling 2 1 2
DUST, LIME POWDER DUST by (Rebar caps/mashroom caps). training to the workers.
(Lung Diseases, Breathing problem, The worker must be competent to perform the The activity must be carried out under the
Eye allergy). task safFollow proper manual handling supervision.
Slip, trip & fall. techniques (avoid twisting, stooping, bending, Snake bite kit must be available at the site.
over-reaching) while carrying the survey
equipment & other marking materials.

Job Safety Analysis


Rev.00, 30 March 2023 Page 6 of 11
Job Safety Analysis
RSG-HS-FRM-0001

RED_SEA_GLOBAL

Hazardous Substance:
Skin irritants Carcinogens
Respiratory sensitizers
Health Hazards
Ensure that sprayer machine is in a safe
Acute health effects, the adverse
Safety training about chemical handling. operating condition.
effects appear after a single or short-
Refresher training through toolbox talks. Ensure that the operator of sprayer machine is
term exposure to the agent, and the
Store minimal quantities in the workplace competent.
response is invariably rapid or
Replace caps when they are not required to be Provide proper PPE’s e.g., hand gloves,
immediate.
removed. coverall, etc.
Chronic health effects usually result
Waste materials stored in a lidded container and RSG-HS-OCH-0001_Control of Substances
from prolonged or repeated
not allowed to overspill onto the floor. Hazardous to Health (COSHH) must be
exposure to the agent
Spillages to be addressed in a timely manner followed.
Adverse effect on a worker’s health
Ensure appropriate PPE is used- overall and Only certified and experienced operator shall
because of direct contact with / or
Applica on of Soil An Termite Control Gloves, respiratory protective equipment (RPE), 2 2 4 operate the equipment. 2 1 2
exposure to the chemical through
gloves. Ensure proper procedure during
inhalation, skin contact or ingestion,
Good hygiene practices to be observed manual/mechanical handling of activity to be
entry through a cut or wound
Atmosphere monitoring done prior to work.
Dizziness-The vapors, if inhaled,
No lone working Conduct awareness training prior of its use on
enter the bloodstream and some can
Use appropriate PPE how to safely operates the sprayer machine.
cause short-term effects (dizziness)
Good welfare arrangements to allow hand Additional use of PPE’s is mandatory
and
washing, etc. requirement during the operation of the
Brain damage-Long-term effects
Monitor the workplace temperature – increase sprayer machine like respirator, etc.
Skin burns
of vapor potential and maybe flammability. HSE Dept. will verify the ID certificates of
Toxic- If ingested they may also have
operatives prior to deployment at site
toxic effects.
Neurotoxins- Organic solvents
(trichloroethylene) are well-known
neurotoxins.

Ensure only appropriate tools are used for


intended activity.
The task must be carry out by competent
Physical Injury. Further, no altering of tool or substitution for
person(s).
Damage to property. that matter.
Maintain good housekeeping to prevent any
Slip, trip & fall. Steel erection must work must be followed
tripping.
Un-inspected tools. under the reference of RSG-HS-COS-0025
Hand tools must not be shattered.
Ergonomics. requirements.
Use right tool for right job.
Work Related Upper limb disorder. Ensure there must be frequent rest breaks
Formwork & Rebars Installation Works The activity must be carry out under the close 2 2 4 2 1 2
Poor posture. during the job.
supervision.
Sharp edges. For safe manual handling techniques RSG-HS-
Defective hand and power tools shall
Pinch point. COS-0006, section 5.3 must be followed.
not be used and shall be immediately
Lack of competency. Ensure the provision of mechanical aids to
removed from the site.
Lack of supervision. reduce the exposure of manual handling.
Do not make direct contact with sharp edges
Provide the suitable PPE's under SG-HS-COS-
without appropriate PPE's.
0001 requirements.

The access must be clear to place the concrete


pump.
Pre-Task Planning Risk and Opportunity
Out rigger must be properly extended to avoid
Management RSG-HS-ADM-0009 must be
any accident / insident.
Strucked by. followed.
Pre-use check of machinery before starting the
Over turning. The task must be carry out by competent
work.
Collision with vehichle / objects / person.
Keep good maintenance to avoide any hydraulic
peoples. There must be a secondary contamination
failure.
Placement of Concrete Pump Hydraulic system failure, 2 2 4 containement system. 2 1 2
The machine must be 3rd party certified, and
Lack of competency. Ensure the provision of Flag man for guidance
have a valid test card.
Lack of instruction & supervision. and safe traffic system.
Pre-use inspected must be held prior to start the
Un-inspected equipment. All sole plates shall be of adequate strength
work.
Contaminated parts. and size to support and distribute the loads
The operator must be 3rd party certificate, and
likely to be applied.
have a valid driving license.

Job Safety Analysis


Rev.00, 30 March 2023 Page 7 of 11
Job Safety Analysis
RSG-HS-FRM-0001

RED_SEA_GLOBAL

Pre-Task Planning Risk and Opportunity


Ensure the provision of Flag-man to avoid any
Collision of vehicle. Management: RSG-HS-ADM-0009
traffic accident.
Soil contamication. Ensure the provision of Flag-man to avoid any
The task must be carry out by competent person.
Lack of competency, road accidents.
Transfer the concrete from the concrete Provide the sheet to containe any contamition
Lack of supervision. 2 2 4 Provide the secondary contamination 2 1 2
truck mixer to the concrete pump truck. for permits k hawaly se.
Spilage. contained system, for any lrakagr ot concrete
Maintain good housekeeping to avoid any
Slip, trip and fall. leakage.
tripping.
Personal Protective Equipment (RSG-HS-COS-
0001).

Miscommunication;
Mishandling; sole plates shall be used
Falls (from the truck); Electrocution; under the stabilizer base plates to spread the
Pipeline blockage. Remote controlling must be performed by loading from the machine.
Weather Condition; competent person (Only). Ensure the provision of guarding devices on
Traffic Hazards; Ensure the provision of a qualified signaller. rotatory / moving parts of machine.
Ergonomics Hazards (i.e. awkward personnel in the Vicinity of the Concrete Pump Concrete pouring task must be performed
position and repetitive strain) must be prohibited. under the instructions of RSG-HS-COS-0022.
Dropped Objects; Flying particles Ensure the safe limit of wind speed prior to start Section 4.5.
Hand and Finger Injury the work and also during the work. Concrete shall be prevented from falling out of
Pouring / Cast in Place of concrete 2 2 4 2 1 2
Heavy Equipment Overturning i.e. Stop pumping immediately in case of any the delivery hose when the boom is being
Concrete Pump, Transit Mixer blockage. maneuvered over personnel or
Spillage of concrete on the ground Reverse the pump until the pressure is released property. Where necessary, a Blanking Device,
and to humans; (DO NOT increase the pressure to clear the fitted in accordance with the manufacturer’s
Slip, trip or fall blockage as an instructions, shall be used.
Crush, pinch points; alternative to the following procedure) Provide appropriate PPE's for concrete
Poor visibility due to darkness; handling. (Rubber gloves, Rubber shoes,
Collapse of form works and Disposible Coverall).
shoringSpills and Leaks
Dust Environmental hazards

Good welfare arrangements to allow hand


Pre-Task Planning Risk and Opportunity
washing etc.
Management_ RSG-HS-ADM-0009
Monitor the workplace temperature – increase
Safety training about chemical handling.
of vapors potential and maybe flammability.
Refresher training through tool box talks.
A qualified fire watch must be present at the
Store minimal quantities in the workplace.
place during the job.
Replace caps when they are not required to be
Safety Data Sheet (SDS) readily available.
removed.
Environmental team will ensure proper
Ensure the provision of suitable fire extinguisher
disposal of chemical empty materials.
in place.
Provide suitable Fire extinguishers with each
Waste materials stored in a lidded container and
equipment.
Sharp edges. not allowed to overspill onto the floor.
Use right-tool for right-job.
Ergonomics. Spillages to be addressed in a timely manner.
Use manual handling techniques for handling
Lack of competency. Ensure appropriate PPE is used overall and
the loads.
Manual Handling. Gloves, respiratory protective equipment (RPE),
Installation & Application of Water Use manual handling aids to reduce the
Fire & Explosion. gloves. 2 2 4 2 1 2
proofing muscle stress, muscle strain.
Hot surfaces. Good hygiene practices to be observed.
Ensure the workers take sufficient rest breaks
Burn. Permit to work system must be followed.
during the job.
Fumes. Ventilation / adequate venting of confined
Manual handling training session must be held
Skin irritant. spaces.
with the workers to improve the competency
No lone working
and reduce the rate of injury at workplace.
Pre-job briefing must be held before starting the
Frequent rest breaks during the job.
job.
Check for any loose connection of LPG cylinder
Only trained and competent person shall
and torch.
commence the activity.
Suitable fire extinguisher must be placed at
Ensure barricading in place to prevent
suitable position.
unauthorized persons away.
A fire watch must be present at site.
Avoid awkward positioning (twisting, bending,
Local/ Homemade tools shall not be used.
over-reaching & stooping) while handling load.
Use appropriate PPE must be provided under
Do not direct contact with the sharp edges
SG-HS-COS-0001.
without hand protection.

Job Safety Analysis


Rev.00, 30 March 2023 Page 8 of 11
Job Safety Analysis
RSG-HS-FRM-0001

RED_SEA_GLOBAL

Ensure the provision of proper containment


system to avoide the soil contamination by
cincrete. Reduce the waste generation.
Ensure the hands washing properly after Waste shall be handle and control under RSG-
Damage to environment. handling the hazardous waste. ENV-PRO-0004_ Section 8.
Soil contamination. Ensure the availability of SDS of the present Substitute the high hazardous chemical with
Primary & Secondary dermatitis. camicals. less hazardous chemicals.
Waste Handling & Storage Inhalable dust. Ensure the proper signages to identify the type 2 2 4 Ensure the proper segregation of waste. 2 1 2
Lack of competency. of waste. Ensure the provision of spill kits and
Lack of resources. Collected waste will be transfered to the contamination containment system in place.
designated skips. Ensure the provision of suitable fire
extinguishers and sand buckets.
Provision of advance PPE's.

Heat stress awareness training just before and Conduct mandatory Heat Stress Awareness
during the hot summer months to all applicable training to all employees prior of deployment
personnel (who work outdoors) and those who at site.
manage personnel and have responsibilities for Provide rest shelter and water on site prior of
establishing heat stress mitigation measures. activity at site.
Ensure required rest period, and minimum water HSE Dept. to monitor on daily basis for the
needed. weather condition at site.
Temperature and Humidity monitor to ensure HSE Dept. to identify the Heat Index danger
timely determination of weather condition. category on daily basis.
Exposure to extreme Hot weather. Danger category color coding shall be per the A standby qualified first aider/site Nurse and
heat index. first aid kit must be available at site.
Heat strees. Take appropriate action upon developing Ensure supply of water daily, to provide
Adverse Weather Conditions 3 2 6 2 1 2
Heat Exaustion. symptoms of heat cramps, heat exhaustion or abundant supply of water at site.
Dehydration. heat stroke. Ensure site with proper monitoring and using
Muscle cramps Ensure designated rest shelter have sufficient kestrel equipment heat stress program.
drinking water station.
Administrative controls like acclimatization,
temperature, and humidity monitoring, flagging
system etc. should be in place.

Ensure all workers follow the use of clothing Ensure appropriate PPE’S to be use when
when temperature working to outside temperature working to outside.
Exposure to extreme Cold weather. Administrative controls like acclimatization,
temperature, and humidity monitoring, flagging 3 2 6 Ensure site with proper monitoring and using 2 1 2
Frost bite. system etc. should be in place kestrel equipment heat stress program.
Hypothermia.

Work is strictly prohibited during lightning and Ensure all workers working at site with proper
project personnel are not allowed to stay shelter in place.
outdoor. Stop work immediately if Lighting
If safe building structures are not accessible, /thunderstorm and notify the transport
employers should guide workers to hard-topped foreman for the standby of BUS as shelter at
metal vehicles with rolled up windows. Remain site.
Lighting /thunderstorm in the vehicle for at least 30 minutes after 3 2 6 In any case of emergency, a standby vehicle at 2 1 2
hearing the last sound of thunder. site radio or cell phone to contact directly.
After hearing thunder, do not use corded All emergency contact list must provide to all
phones, except in an emergency. Cell phones driver/s.
and cordless phones may be used safely.

Ensure work is strictly prohibited during heavy Ensure all workers working at site with proper
rains and project personnel are not allowed to shelter in place during the rain.
work/stay outdoor. Always be vigilant of the flooding in the area,
If water accumulated or the area is flooding due look for the high location if flooded or call for
to rain, wait to subside before resuming the an emergency.
work. Ensure on any presence of water in excavated
If water is present in the excavation, de-watering area don’t allow any worker/s to resume the
Heavy Rain 3 2 6 2 1 2
shall be performed by installing submersible works.
pumps or equivalent should land survey work is Provide appropriate protection for the
urgent. excavation to prevent erosion of excavated
If raining, sandbag shall be positioned on the works.
surrounding of the excavation to prevent
rainwater flowing in the excavated area.

Job Safety Analysis


Rev.00, 30 March 2023 Page 9 of 11
Job Safety Analysis
RSG-HS-FRM-0001

RED_SEA_GLOBAL
Work is strictly prohibited during sandstorm and Ensure all workers working at site with proper
project personnel are not allowed to stay shelter in place during sandstorm.
outdoor. Provide appropriate wearing of face mask
Wear medical facemasks or use wet towel or during sandstorm at site otherwise stop the
gauze during sandstorms outdoors. work and wait for further notice to proceed.
Wear eyeglasses preferably airtight goggles or Provide appropriate use of safety glasses,
face shield to protect your eyes from blowing contact lenses are not allowed during working
dust or sand. at site.
Avoid wearing contact lenses in areas prone to Ensure all workers to stay indoor (car or office
sandstorm. building) unless it is necessary to go out.
Avoid rubbing eyes to prevent eye infection. Conduct maintenance of office and
Sandstorm If eyes become irritated, rinse with water. 3 2 6 accommodations to sealed properly and 2 1 2
Stay indoor (car or office building) unless it is prevent sands enter inside the room/office,
necessary to go out. Drive with caution or stop on the shoulder of
Ensure office and accommodations if sandstorm the road until the sandstorm remain calm.
proof (properly sealed). Be vigilant of another vehicle near you during
When driving, drive slowly with caution when the zero visibility on roads at site.
visibility is very low. Ensure you parked in right place during this
Pull over completely to a safe place off the paved sandstorm to prevent any collision with other
portion of the roadway during low visibility. oncoming vehicles.

Collect empty paint spray bottle, etc. and Ensure all unwanted materials to be disposed
dispose of properly. properly on designated location skip bins.
Proper planning and look ahead by Discipline Prioritize the housekeeping scheduled on or
Supervisor/Foreman. before the activity on daily basis on site.
Prior to commencing work, as part daily Construction Team shall be accountable for all
progress, he shall plan for: the materials and pre-arranged staging
Housekeeping resources - hauling equipment location area to prevent any materials
(loader / dump truck / forklift) and dedicated scattered on the surroundings.
Poor Housekeeping. crew.
Housekeeping Lack of proper planning Regular collection of rubbish, every end of shift 2 2 4 2 1 2
Lack of resources at minimum
Waste skips / covered metal trash bins /
disposable trash bags, etc.
Temporary staging area of scrap materials
Pre-arranged staging area for construction
materials, tools / equipment
Access for personnel and equipment
Barricades / signs required

Proper planning and look ahead by Discipline


Supervisor. Prior to his activities he shall:
Familiarize himself and his team with the site-
specific emergency procedure.
Know the actual locations of nearest safe
assembly areas. Conduct toolbox talk with his
crew on emergency procedure.
See to it that safe access route is available from
work area towards the nearest safe assembly
Ensure proper planning and look ahead by
area. Be familiar with the prevailing wind against
construction team of any activity at site.
the locations of nearest safe assembly points. At
Ensure to comply with RSG-HS-ADM-0007
least 2 safe assembly points in opposite
(Emergency Preparedness and Response) of
directions shall be known to the crew from each
any emergency protocol.
work location.
Follow the STOP Work or Evacuation Alarm, as
Be familiar with site specific Emergency
Lack of proper an instruction from Site ERT / HSE, of any
Response Plan (ERP) and requirements of this
planning / emergency emergency protocol.
document. Understand / comply with RSG-HS-
readiness / Conduct emergency training drills in
Emergency Preparedness ADM-0007 (Emergency Preparedness and 2 2 4 2 1 2
awareness of safe coordination with RED SEA/SC for the
Response). Upon hearing site STOP Work or
evacuation procedure. awareness by all workers on site.
Evacuation Alarm, or receipt of an instruction
Lack of resources Ensure emergency contact list to be posted at
from Site ERT / HSE, Discipline Supervisor shall
site and keep up to date the contact list.
lead his crew to ensure following actions are
Provide training to all workers on how to
taken: Stop work, Alarm others, Shutdown all
contact the details in the emergency contact
machines e.g., generator, welding machines,
list.
etc.. Check wind direction
Ensure the provision of Emergency contact list
Proceed to nearest safe assembly area in cross
available at site.
wind direction. Participate in the headcount,
report missing person (if any)
Stay at safe assembly area, remain attentive, do
not engage in any unauthorized activity, wait for
further instruction. All site personnel to
participate in training drills. Conduct emergency
training drills in coordination with RED SEA/SC.

Section IV – Approval and Signatures


Prepared by Company Position
Syed Saddam AMT Health & Safety Manager

Abid Ali Khan AMT Environmental Manager

Initial Review and Approval by Company Position


Eslam Elmawafi AMT QC Manager

Note: All High and Very High residual risk ratings (10-25) require review and approval by Construction Director/Manager/Facility or Operations Manager before starting work to ensure that the additional
controls are adequate to execute the task safely.
Job Safety Analysis
Rev.00, 30 March 2023 Page 10 of 11
Job Safety Analysis
RSG-HS-FRM-0001

RED_SEA_GLOBAL
controls are adequate to execute the task safely.

Final Review and Approval by Company Position Date


Construction Director/Manager / Facility
Mahmoud Hagag AMT
/Operations Manager

Reviewed by Crew Company Position

Job Safety Analysis


Rev.00, 30 March 2023 Page 11 of 11