KAZO 

DPR Work Responsibility Target Remarks

Highways
Alignment design Philemon and Danish 03.12.2020 On 08th Philemon works on NAR Road Safety
Profile design Philemon and Danish 05.12.2020 Philemon, Danish told to be conversant with passing 
Cross sections Danish 06.12.2020 to 12.12.2020 sight distance analysis, swept path analysis etc. from 
Schedules for costing (non RS, RM) Philemon and Danish 06.12.2020 to 12.12.2020 Biswajit / Anuj… based on software / plugins 
Junctions, Swept path analysis etc… Philemon (guided by Biswajit / Anuj)  12.12.2020 availability... 
Passing Sight distance analysis Danish (guided by Anuj)  14.12.2020 Danish to be familiar with Uganda design manual 
RM and RS related schedules Philemon and Danish (guided by Anuj) 15.12.2020 provisions...
Layout plan of RM and RS Anuj (suported by CAD) 18.12.2020 Anuj to be involved in road marking, road sign 
Signs design using KEYSIGNS software Philemon and Anuj 18.12.2020 related works incl. layout plan, keysigns etc...

Hydrology and Hydraulics
Reconfirmation of hydrology and proposed structure sizes Vishal 14.12.2020
Drainage design, P/P, Kerb inlet, gutter etc. Vishal 15.12.2020 to 19.12.2020
HY‐8 analysis Ajay (check by Vishal) 21.12.2020 to 22.12.2020 Vishal is busy with NAR and Karenga works upto 
Hydrology and Hydraulics Report Vishal 21.12.2020 to 22.12.2020 13.12.2020

Structures
Inventory updation, GADs of pipe culverts with reinf. detailing, 
report revisions (partial)...  Ajay 04.12.2020 to 06.12.2020
Study Eurocodes and sheets for box culvert design Ajay (with Tapas) 07.12.2020 to 17.12.2020
Box culvert designs  Ajay 18.12.2020
BoQ inputs and finalisation of drawings, reports Ajay 19.12.2020 onwards…