Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-C-2010

Project Name Date: 24 Feb 2011


Contract Number Page 1 of 5
Revision 1

SPECIFICATION – ROCK RIP-RAP

This specification has been revised as indicated below and described in the revision record on the following
page. Please destroy all previous revisions.

Revision Date Originator's Reviewed/Checked By Pages


No. Name & Initials Name & Initials
A 8/18/2010 Greg Luttrull 3
0 11/24/2010 Brooke Shondelmyer Joey Ramos 5
1 2/24/2011 Brooke Shondelmyer Joey Ramos 5

APPROVALS SIGNATURES DATE

Lead Engineer Greg Luttrull 2/24/2011


Project/Engineering
Manager: Ed Haney 2/24/2011
Client Approval:

ISSUED FOR : Construction X Other Approved


Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-C-2010
Project Name Date: 24 Feb 2011
Contract Number Page 2 of 5
Revision 1

SPECIFICATION – ROCK RIP-RAP

Record of Revisions
Revision Date Description
No.

A 8/18/2010 Issued for Approval, Table of Contents Only

0 11/24/2010 Issued for Review/Approval

1 2/24/2011 Issued Approved


Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-C-2010
Project Name Date: 24 Feb 2011
Contract Number Page 3 of 5
Revision 1

SPECIFICATION – ROCK RIP-RAP

Table of Contents

1.0 GENERAL................................................................................................................................................... 4
1.1 Summary....................................................................................................................................... 4
A. Scope of Specification..................................................................................................... 4
2.0 PRODUCTS ................................................................................................................................................ 4
2.1 Riprap............................................................................................................................................ 4
2.2 Geotextile Fabric.......................................................................................................................... 4
3.0 EXECUTION .............................................................................................................................................. 5
3.1 Subgrade ....................................................................................................................................... 5
4.0 ATTACHMENTS....................................................................................................................................... 5
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-C-2010
Project Name Date: 24 Feb 2011
Contract Number Page 4 of 5
Revision 1

SPECIFICATION – ROCK RIP-RAP

Note: Notes, including this one, are to be reconciled and removed when this document is issued as a
Project Specification. This document prescribes a uniform format. The Lead Civil Engineer has
the responsibility to modify, add, or delete the following standard provisions in order to meet
project requirements.

Note: Make sure we know what kind of materials are available in the area of the project. Sometimes the
cost for a particular stone isn't worth it to the project. Contract local sources for availability.

1.0 GENERAL

1.1 Summary

A. Scope of Specification

This specification prescribes the requirements for the supply and installation of riprap to the
lines, grades, and dimensions shown on the drawings.

B. Related Specification

Not Applicable

2.0 PRODUCTS

2.1 Riprap

Riprap shall consist of durable, hard field stone or rough, unhewn quarry stone of approximately
rectangular shape. The stones shall be reasonably free from cracks, seams, and other defects that
may cause deterioration and they shall be reasonably free from earth and other foreign materials.
The riprap shall be well graded with at least 50 percent of the gradation between the maximum
stone size and the median stone size. The size of an individual stone shall be determined by
measuring its long dimension.

The riprap shall be classified as follows: [Verify “class” in state D.O.T. standard as this varies state
to state]

Riprap Size Class 1 Class 2 Class 3


Maximum Stone Size 8 inches 12 inches 18 inches
Median Stone Size 5 inches 8 inches 12 inches
Minimum Layer Thickness 12 inches 18 inches 27 inches

2.2 Geotextile Fabric

Geotextile fabric shall be Mirafi 140N or an approved substitute.


Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-C-2010
Project Name Date: 24 Feb 2011
Contract Number Page 5 of 5
Revision 1

SPECIFICATION – ROCK RIP-RAP

3.0 EXECUTION

3.1 Subgrade

A. Excavate and prepare the subgrade of areas to receive riprap to the lines, grades, and
cross sections shown on the drawings.
B. Geotextile fabric, if required, shall be installed beneath riprap as shown on the
drawings.
C. Place the riprap to conform to the class, thicknesses, slopes, lines, and grades shown
on the drawings. Stone may be placed by mechanical methods, augmented by hand
placing where necessary, provided that when the riprap is completed it forms a
properly graded, dense, neat layer of stone. At locations where riprap is required for
channel changes and drainage ditches, it shall be placed prior to diverting the water
into the channel changes and drainage ditches.
D. At locations where riprap is required at the outlets of pipe culverts, place the riprap
immediately after completing the pipe culvert installation.
E. Place riprap from the bottom of a slope upward, with the larger stones being placed
in the lower courses. Fill open joints with spalls, and thoroughly ram them into
place.
4.0 ATTACHMENTS

Not applicable

End of Specification