Jubail 3A Project

Comment Sheet No. CRS Rev. CRS Status Issued Date


LEGEND:
REJ = Rejected
J3A-DRA-EAIC-JFZ-030-0001_CS_JWDC 0B REJ 01/07/2021 APP = Approved
FI = For Information
AWC = Approved with Comment

Drawing / Document No. Rev. Drawing / Document title


GENERAL ARRANGEMENT DRAWING OF FIRE WATER TANK (DIA-12 M x H-
J3A-DRA-EAIC-JFZ-030-0001 00
9.58M)

Reviewed by O/OE Replied by EPC Contractor


Doc/Dwg Doc/Dwg
Received Date Replied Date Doc. Status CRS Status Received Date Replied Date Doc. Status
Rev.No Rev.No
00 17/06/2021 01/07/2021 IFA REJ

1. O/OE Comments Rev.0 EPC Contractor’s Reply


Provide separate sheets for the following details (Similar to potable
water tank drawing submission – refer screenshot below. )

Remarks: Comments given in this Comment Sheet are for technical clarification only, and have no commercial impact.
The approval of the document does not release the EPC Contractor from his Contract obligations.
Page 1 of 6
Jubail 3A Project

Comment Sheet No. CRS Rev. CRS Status Issued Date


LEGEND:
REJ = Rejected
J3A-DRA-EAIC-JFZ-030-0001_CS_JWDC 0B REJ 01/07/2021 APP = Approved
FI = For Information
AWC = Approved with Comment

Drawing / Document No. Rev. Drawing / Document title


GENERAL ARRANGEMENT DRAWING OF FIRE WATER TANK (DIA-12 M x H-
J3A-DRA-EAIC-JFZ-030-0001 00
9.58M)

2. O/OE Comments Rev.0 EPC Contractor’s Reply


The drawing is incomplete. Various details are indicated as on hold or
to be provided by the client. Please submit final drawing with all
necessary information/design.

Remarks: Comments given in this Comment Sheet are for technical clarification only, and have no commercial impact.
The approval of the document does not release the EPC Contractor from his Contract obligations.
Page 2 of 6
Jubail 3A Project

Comment Sheet No. CRS Rev. CRS Status Issued Date


LEGEND:
REJ = Rejected
J3A-DRA-EAIC-JFZ-030-0001_CS_JWDC 0B REJ 01/07/2021 APP = Approved
FI = For Information
AWC = Approved with Comment

Drawing / Document No. Rev. Drawing / Document title


GENERAL ARRANGEMENT DRAWING OF FIRE WATER TANK (DIA-12 M x H-
J3A-DRA-EAIC-JFZ-030-0001 00
9.58M)

3. O/OE Comments Rev.0 EPC Contractor’s Reply


All the items which are galavansed must be Hot Dip Galvanised. EPC to
confirm and include in the notes.
4. O/OE Comments Rev.0 EPC Contractor’s Reply
Please clarify the basis f selecting the operating temperature
mentioned in the drawing. The calculation and drawing indicates
different values.

Remarks: Comments given in this Comment Sheet are for technical clarification only, and have no commercial impact.
The approval of the document does not release the EPC Contractor from his Contract obligations.
Page 3 of 6
Jubail 3A Project

Comment Sheet No. CRS Rev. CRS Status Issued Date


LEGEND:
REJ = Rejected
J3A-DRA-EAIC-JFZ-030-0001_CS_JWDC 0B REJ 01/07/2021 APP = Approved
FI = For Information
AWC = Approved with Comment

Drawing / Document No. Rev. Drawing / Document title


GENERAL ARRANGEMENT DRAWING OF FIRE WATER TANK (DIA-12 M x H-
J3A-DRA-EAIC-JFZ-030-0001 00
9.58M)

5. O/OE Comments Rev.0 EPC Contractor’s Reply


Please specify the Radiography and PWHT requirement as per API 650;

6. O/OE Comments Rev.0 EPC Contractor’s Reply


DN 200 Vent size shall be confirmed through calculation.
7. O/OE Comments Rev.0 EPC Contractor’s Reply
Please mark the nozzle below on the tank.

Remarks: Comments given in this Comment Sheet are for technical clarification only, and have no commercial impact.
The approval of the document does not release the EPC Contractor from his Contract obligations.
Page 4 of 6
Jubail 3A Project

Comment Sheet No. CRS Rev. CRS Status Issued Date


LEGEND:
REJ = Rejected
J3A-DRA-EAIC-JFZ-030-0001_CS_JWDC 0B REJ 01/07/2021 APP = Approved
FI = For Information
AWC = Approved with Comment

Drawing / Document No. Rev. Drawing / Document title


GENERAL ARRANGEMENT DRAWING OF FIRE WATER TANK (DIA-12 M x H-
J3A-DRA-EAIC-JFZ-030-0001 00
9.58M)

8. O/OE Comments Rev.0 EPC Contractor’s Reply


Access ladders/platforms to be provided for accessing the roof nozzles.
9. O/OE Comments Rev.0 EPC Contractor’s Reply
Include details of the cathodic protection for the tanks.
10. O/OE Comments Rev.0 EPC Contractor’s Reply
Corrosion allowance as per OTS to be considered. EPC to comply with
OTS requirement
11 O/OE Comments Rev.0 EPC Contractor’s Reply
Earthing bosses shall be welded to the tank shell as per 5.8.11.3 of API
650.
12 O/OE Comments Rev.0 EPC Contractor’s Reply
Material specification stated for shell, base plate, annular plate, ring
plate roof structures, etc., should be comply as per API 650 and OTS as
well. EPC to confirm
13 O/OE Comments Rev.0 EPC Contractor’s Reply
Tank bottom underside shall be painted, and suitable paint system
shall be proposed.
Painting specification should be complied for internal and external: EPC

Remarks: Comments given in this Comment Sheet are for technical clarification only, and have no commercial impact.
The approval of the document does not release the EPC Contractor from his Contract obligations.
Page 5 of 6
Jubail 3A Project

Comment Sheet No. CRS Rev. CRS Status Issued Date


LEGEND:
REJ = Rejected
J3A-DRA-EAIC-JFZ-030-0001_CS_JWDC 0B REJ 01/07/2021 APP = Approved
FI = For Information
AWC = Approved with Comment

Drawing / Document No. Rev. Drawing / Document title


GENERAL ARRANGEMENT DRAWING OF FIRE WATER TANK (DIA-12 M x H-
J3A-DRA-EAIC-JFZ-030-0001 00
9.58M)

to ensure
14 O/OE Comments Rev.0 EPC Contractor’s Reply
All stairway, platform walkway, grating, handrail, ladder etc. shall be
Hot Dip Galvanized with C5M coating.
Coating for the air vent to be advised
15 O/OE Comments Rev.0 EPC Contractor’s Reply
The Tank redundancy and capacity of tank shall be subject to HCIS
approval. Please confirm
16 O/OE Comments Rev.0 EPC Contractor’s Reply
Tank Name, font size and direction shall be agreed with Owner at site
17 O/OE Comments Rev.0 EPC Contractor’s Reply
Tank inlet pipe shall be shown in the sectional view
18 O/OE Comments Rev.0 EPC Contractor’s Reply
Tank external bottom to be protected by impressed current MMO
ribbon anode grid system
19 O/OE Comments Rev.0 EPC Contractor’s Reply

Remarks: Comments given in this Comment Sheet are for technical clarification only, and have no commercial impact.
The approval of the document does not release the EPC Contractor from his Contract obligations.
Page 6 of 6