Professional Documents
Culture Documents
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A General Requirements
Radiographic procedure approved by Inspection department is available SAEP-1143,
A1 to verify the RT requirements and Techniques applied. Para 5.1
Personnel performing radiography are certified to a minimum of Level II
per the certifying organization's written practice/ requirements of SAEP-1143
A2 ANSI/ASNT CP-189. Para. 5.2
(Refer to SAIC-RT-2002 for personnel qualifications)
Radiographic personnel have passed the Radiation Safety examination
administered by the Saudi Aramco Loss Prevention Department and are SAEP-1143
A3 in possession of a current Saudi Aramco Radiographer Permit issued by Para. 4.3
the Inspection Department.
Protective measures are taken by radiographic personnel to insure that
no individual is exposed to radiation in excess of the prescribed limits (as SAEP-1143
A4
mandated in SAEP-1141 and GI-0150.003). Para. 6.2.2
Lead letter "B" is attached to the back of each film holder during each
exposure to determine if backscatter radiation is exposing the film. SAEP-1143
A7
(Note: The dimensions of letter "B" shall be 13mm (0.5 inch) of Para. 5.4
height and 1.5mm (0.0625 inch) thickness)
Page 1 of 7
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
In-Process Verification of Techniques and Procedure
SAIC-RT-2007 25-May-05 NDE-
Implementation of Radiographic Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
0 0 0
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Location markers are identified on the surface of the specimen being
radiographed.
SAEP-1143
B2 (NOTE: Regardless of the technique used, the area of interest of the
Para. 8.3.3
radiograph shall be accurately traceable to its location on the part until
acceptance. )
Location markers are placed on the part being examined and not on the
SAEP-1143
B3 exposure holder/cassette. Location markers shall not intrude into the
Para. 8.3.1
area of interest.
The starting point and the direction of numbering shall be identified SAEP-1143
B4
adjacent to the weld. Para. 8.3.1.1
C Exposure Techniques
Single wall exposure technique described below is used for radiography
whenever practical.
Single Wall Exposure - Single Wall Viewing (SWE/SWV) Technique - the SAEP-1143
C1
radiation passes through only one wall of the weld (material), which is Para. 7.1
viewed on the radiograph for acceptance.
Page 2 of 7
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
In-Process Verification of Techniques and Procedure
SAIC-RT-2007 25-May-05 NDE-
Implementation of Radiographic Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
0 0 0
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Double wall techniques described below shall be used when it is not
practical to use a single wall technique.
1. Double Wall Exposure - Single Wall Viewing (DWE/SWV)
technique. Radiation passes through two walls and only the
weld (material) on the film side wall is viewed for acceptance
on the radiograph. For full weld coverage of circumferential
welds at least 3 exposures taken 120º apart shall be taken.
2. Double Wall Exposure - Double Wall Viewing (DWE/DWV)
Technique radiation passes through two walls and both walls
are viewed for acceptance on the radiograph. These
techniques shall only be used for materials and welds in piping
3.5 inch NPS or less.
SAEP-1143
C2
Para. 7.1
For the elliptical DWE/DWV technique the radiation beam shall be offset
at the weld at an angle sufficient to separate the images of the source
side and film side portions of the weld. SAEP-1143
C3
(NOTE: The elliptical technique requires at least 2 exposures 90º to Para. 7.4.2
each other to achieve complete coverage of the weld.)
Page 3 of 7
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
In-Process Verification of Techniques and Procedure
SAIC-RT-2007 25-May-05 NDE-
Implementation of Radiographic Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
0 0 0
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
The voltage for examinations with x-ray tubes shall be selected to insure SAEP-1143
D2
that the required IQI wire is visible on the radiograph. Para. 8.1.1
Gamma Radiation i.e Ir-192, Se-75 and Co-60 (together with the
SAEP-1143
D3 radiographic technique used) shall be selected to produce the required
Para. 8.1.2
radiographic sensitivity.
Radiographic film used shall be either Type I or Type II.
Type I film shall be used for radiography of pipe diameters of 8 inch
SAEP-1143
D4 nominal pipe size (NPS) or less.
Para. 6.2.1
Note: Film shall be selected to produce radiographs possessing
acceptable sensitivity, density, and contrast.
Lead intensifying screens are used and the minimum thickness of the
front lead screen is.
1. 0.13 mm (0.005 inch) for Ir-192 and Se-75. SAEP-1143
D5
2. 0.25 mm (0.010 inch) for Co-60 or the linear accelerator. Para. 6.3
Note: Lead screens which are an integral part of "ready pack"
(i.e., Pb contact pack) film are acceptable.
SAEP-1143
E1
Para. 6.4
IQIs shall be from either the same alloy material group or grade or from
SAEP-1143
E2 an alloy material group or grade with less radiation absorption than the
Para. 6.4.3
material being radiographed.
Page 4 of 7
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
In-Process Verification of Techniques and Procedure
SAIC-RT-2007 25-May-05 NDE-
Implementation of Radiographic Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
0 0 0
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Penetrameters (IQI) shall be selected to insure that the designated wire
required by Table 7 shall be included in the penetrameter pack used.
SAEP-1143
E3
Para. 8.5.1
SAEP-1143
E4 IQIs are not damaged, e.g., bent wires.
Para. 6.4.2
Selection of the penetrameter shall be based on the nominal thickness of
the base material plus the estimated weld reinforcement (not to exceed
the maximum permitted by the referencing code section). In general, the
following applies:
1. SWE/SWV or DWE/SWV techniques - the required wire size is
based on the wall thickness plus one reinforcement where such
reinforcement is not ground off.
2. DWE/DWV elliptical technique - the required wire size is based on
two wall thickness plus one reinforcement where such
reinforcement is not ground off.
3. DWE/DWV superimposed technique - the required wire size is
SAEP-1143
E5 based on two wall thickness plus two reinforcements were such
Para. 8.5.2
reinforcement is not ground off.
Note:
1. Welds without Reinforcement - Nominal single wall thickness for
SWE/SWV and the nominal double wall thickness for DWE/DWV
technique shall be the basis for penetrameter selection.
2. Internal protrusion of single bevel welds, backing rings or strips
shall not be considered as part of the thickness in penetrameter
selection.
(Refer to item for definitions of S,D,W,E,V used above)
Page 5 of 7
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
In-Process Verification of Techniques and Procedure
SAIC-RT-2007 25-May-05 NDE-
Implementation of Radiographic Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
0 0 0
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Penetrameters placed on the Film side are installed as follows:
a) The penetrameters is in contact with the part being examined.
b) A lead letter "F", as least as high as the penetrameter SAEP-1143
E7
identification numbers, is placed adjacent to or on each Para 8.6.2
penetrameter.
When configuration or size prevents placing the penetrameter(s) on the
part or weld, the penetrameter(s) may be placed on a separate block of SAEP-1143
E8 radiographically similar material. The block shall be placed as close as Para. 8.6.3
possible to the item being examined.
Only a source side penetrameter are used for the double wall viewing SAEP-1143
E11
technique (DWV techenique). Para.7.4.1
F Geometric Unsharpness
Page 6 of 7
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
In-Process Verification of Techniques and Procedure
SAIC-RT-2007 25-May-05 NDE-
Implementation of Radiographic Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
0 0 0
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Calculated Geometric unsharpness, Ug, of the radiograph shall not
exceed the values listed in Table below. The minimum source to object
distance, D, shall be great enough to insure that Ug does not exceed the
limit.
Geometrical Unsharpness (Per Table 5, SAEP-1143)
Material Ug
Thickness, mm (Inches) Maximum,mm(Inch)
Under 50.8 (2 in.) 0.500 (0.020 in.)
50.8 - 76.2 (2 in. through 3 in.) 0.760 (0.030 in.)
Over 76.2 - 101.6 (> 3 in. through 4 in.) 1.010 (0.040 in.)
SAEP-1143
F1 Greater than 101.6 mm (> 4 in.) 1.780 (0.070 in.)
Para. 8.2.2
Note: The minimum source to object distance, D, (necessary to insure
that the Ug does not exceed the values listed in Table) can be
determined by.
D = (Ft/Ug) + t
Where:
D=Source to weld distance, F=Source size, Ug=Geomatric unsharpness
t=Distance from source side of the Object to the film.
NOTES:
1. Items indicated as "Best Practice" shall be agreed upon by Contractor, SAPMT and Inspection. These will then be
incorporated in the project requirement and in the Project Quality Plan and will be mandatory for implementation.
REMARKS:
REFERENCE DOCUMENTS:
1. SAEP-1143, Radiographic Examination, (29 May, 2002)
2. SAEP-1141, Industrial Radiation Safety, (31 December, 1996)
Page 7 of 7