Production Release Indent 6
(Skipper Limited)
PRI No.: SL/TOWER/Udipur/PRI-6
PRI Date: 15 September 2021
Contract No. :- ICB-PMD-MCTLP-016/17-01
Schedule No.1: Plant and Equipment including Mandatory Spares to be supplied from abroad
As per Revised Tower Schedule dated PRI-4 For 4th
14 Sept 2021 PRI-3 Third
PRI-1 First PRI-2 lot
Lot for 6km Remaining
Sl. No Type of Tower WITH WITH Lot Second Lot (70% OF Remarks
Total Emergency Qty.
BASIC NORMAL 2019.10.03 2021.02.04 REMAINING
Quantity 2021.03.05
BODY BODY TOWER)
1.1.2 Tension Tower DB
With DBR Cross arms = 17
a.1) Basic tower 21 49 70 35 - 35 25 Nos (2 DBR cross arm
already reached in lot-3)
PRI of Stub Shall Be Raised
a.2) Stub 84 196 280 - -
Seperately
b) -4.5 m Leg Extension - - - -
c) -3 m Leg Extension 6 6 1 - 5 3
d) -1.5 m Leg Extension 11 11 2 - 9 5
e) +/- 0 m Leg Extension 42 196 238 129 - 109 80
f) +1.5 m Leg Extension 15 - 15 3 - 12 9
g) +3 m Leg Extension - - -
g.1) Combined with Basic Tower Body 10 - 10 8 - 2 1
g.2) Combined with Normal Tower Body (0M Body) 31 31 5 - 26 20
h) +4.5 m Leg Extension 23 23 6 - 17 10
i) +6 m Leg Extension 58 58 32 - 26 20
j) +7.5 m Leg Extension 16 16 6 - 10 6
k) +9 m Leg Extension 68 68 11 - 57 45
Contractor / Purchaser: Pinggao Group Co. Ltd. Manufacturer / Seller: M/S Skipper India Limited
Business Manager: Ms. Li Qi Project Manager: Mr. Kamal Guhathakurata
Dy. Project Manager: Mr. Hikmat B. Ayer Project Manager: Mr. Manish Jain