from Ch.154+210 to Ch.158+675 (North Bound) and from Ch.155+940 to Ch.160+282 (South Bound)
including Construction of Twin Tube Tunnel (Package-I) in the UT of Jammu & Kashmir on EPC Mode
Schedule A
(See Clause 2.1 and 8.1)
SITE OF THE PROJECT
1 The Site
1.1 Site of the Four-Lane Project Highway shall include the land, buildings, Structures and road
works as described in Annex-I of this Schedule-A.
1.2 The dates of handing over the Right of Way to the Contractor are specified in Annex-II of
this Schedule-A.
1.3 An inventory of the Site including the land, buildings, structures, road works, trees and any
other immovable property on, or attached to, the Site shall be prepared jointly by the
Authority Representative and the Contractor, and such inventory shall form part of the
memorandum referred to in Clause 8.2.1 of this Agreement.
1.4 The alignment plans of the Project Highway are specified in Annex-III of this Schedule-A,
which has to be followed by the Contractor as a minimum. The Contractor may, however,
improve upon the alignment plans and profiles and raise the Finished Roadway Level (FRL)
with approval from the Authority’s Engineer within the available Right of Way.
1.5 The status of the environment clearances is given in Annex-IV of this Schedule-A.
Annex-I
(Schedule-A)
1. Site
The site of Construction of four laning of part of project highway comprises development of
twin tube (2X2) tunnel including approaches from Marog to Digdol From Design
Ch.154+210 to Design Ch.158+675(North Bound) and from Design Ch.155+940 to Design
Ch.160+282(South Bound) of Ramban to Banihal Section of NH-1A (Now NH-44), in the
Union Territory of Jammu & Kashmir which is a hilly /steep terrain. The land, carriageway
and structures comprising the site are described below. An index map of the project highway
is given in Appendix A-I.
For a better understanding since the existing kilometer stones are not traced on ground, the
Existing ongoing contract design chainage is referred as “Existing Chainage” for the North
Bound (NB) and South Bound (SB) carriageways and Revised Design Chainage as “Design
Chainage for the North Bound (NB) and South Bound (SB) carriageways.
2. Land
The Site of the Project Highway comprises the land as described below based along project
road:
Design Chainage Width of
S. No. Length (m) Existing ROW
From (Ch.) To (Ch.) (m) Remarks
5. Major Bridges
The Site includes the following Major Bridges:
Width (m)
Existing
S. No.
Foundation
Chainage Remarks
(Ch.) Sub- Super-
structure structure
Width (m)
length (m)
with span
S. Existing
Sub- Super- Remarks
No. Chainage (Ch.) Foundation
structure structure
157+520 Abandoned
1 Choked Choked Slab 1x7.0 8 due to
(NB) Realigned
155+170 Under
2 RCC Box RCC Box RCC Box 2x8.2 12
(NB) Construction
Under
159+985 (NB) RCC Box RCC Box RCC Box 1x12.1 12
Construction
3
161+765 (SB) Under
RCC Box RCC Box RCC Box 1x12.1 12
Construction
Nil
13. Truck Lay byes
The details of truck lay byes are as follows:
Existing Chainage Right Hand Side
S. No. Length (m) Left Hand Side
(Ch.)
Nil
14. Road Side Drains
The details of the roadside drains are as follows:
Existing Chainage Type
S.
From Masonry/cc Remarks
No. To (Ch.) Earthen (Kutcha)
(Ch.) (Pucca)
Nil
Appendix A-I
Annex-II
(Schedule-A)
Details of the Proposed Extra Right of Way (PROW) are tabulated below. The ROW mentioned
below are minimum specified and shall be as per plan & profile.
Annex-III
(Schedule-A)
Alignment Plans
The alignment plan of the Project Highway is available on E - Tendering portal of NHAI.
The existing alignment of the Project Highway shall be modified in the following sections as per the
alignment plan indicated below:
The alignment of the Project Highway is enclosed in alignment plan. Finished road level indicated
in the alignment plan shall be followed by the contractor as minimum FRL. In any case, the
finished road level of the project highway shall not be less than those indicated in the alignment
plan. The contractor shall, however, improve/upgrade the Road profile as indicated in Annex-III
of Schedule-A based on site/design requirement.
Traffic Signage plan of the Project Highway showing numbers & location of traffic signs is
enclosed. The contractor shall, however, improve/upgrade upon the traffic signage plan based on
site/design requirement as per IRC: SP: 84 & IRC: 67
Following drawings are enclosed in digital form in CD marked as Annex-III.
Alignment Plan & Longitudinal Profile
GAD of Structures
Traffic Signage Plan
Utility Plan
Drainage Plan and Profile
Annex-IV
(Schedule-A)
Environment Clearances
Projects requiring Prior Environmental Clearance is given in the “SCHEDULE” of EIA Notification
2006. As per the Schedule categorization of the highway project is as follow:
Project
Category ‘A’ Category ‘B’ Conditions if any
Activity
Highways i) New National High ways; and i) All New State Highway General Condition
7(f) ii) Expansion of National Highways Projects shall apply
greater than 100 km involving ii) State Highway Expansion Note:
additional right of way or land projects in Hilly terrain Highways include
acquisition greater than 40m on (above 1,000 m MSL) and or expressways
existing alignments and 60m on re- Ecologically Sensitive Areas.
alignments or by-passes
Conclusion: The proposed project is the expansion of an existing national highway having length less
than 100 km. Hence, Environment Clearance is not required.