ACCOMPLISHMENT REPORT NO.5


JULY 18 - JULY 23,2022

Name of Practicumer: ASUNCION, ALYSSA MARIE R. Program: BS Civil Engineering Student No: 201912244
Company Name: Ybalai Builders Name of Project: Proposed 2-Storey Residential Renovation
Company Address: 1254 Don Pedro St., Brgy. 759, Santa Ana Manila, 1004 Project Address: 102 Apitong, Ayala Alabang

DESCRIPTION OF SUPERVISOR’S
INCLUSIVE DATES DETAILS OF THE ACTIVITY PERSONAL REMARKS
ACTIVITY ASSIGNED REMARKS
Intern learn the meaning of
quotation and its purpose.
Supervisor ask the intern to
Also intern have an idea how
ask the requirements for
Quotation for Ceiling to talk to suppliers, for
July 18,2022 quotation of ceiling N/A
Materials example is the basic
materials to the supplier via
information of the project
email.
and company that will be
needed by the supplier.
Supervisor gave a task to Intern was able to make a
interns wherein they have summary of payments using
to make a summary of excel for an easy monitoring
Monitoring of
payments per subcon. of their contracts. Intern was
payments per subcon,
Supervisor taught interns able to inspect the spacing of
CHB Laying
July 19,2022 how to inspect the CHB. Horizontal and Vertical bars N/A
Inspection, checking
Interns was tasks to check and was able to understand
of openings, Checking
the openings and lightings why is there a requirement of
lighting layout
layout at the balcony, spacing on it. Intern was able
library, and the whole 2F for to double check the lightings
lighting. layout for 2F.
Intern was able to call some
suppliers that are offering the
Architect task intern to find
products and was able to
a supplier of power track
Quotation for Power report the prices to the
and power dock and ask for
July 20,2022 track and power dock. architect and ask for a N/A
a quote. Project Engineer
Cutting list quotation. Intern was able to
tasks intern to do a cutting
understand on how to do a
list in a specific site.
cutting list and how to do it in
CAD.
Prepared by: Checked by:

ALYSSA MARIE R. ASUNCION ENGR. JOYCE C. VILLAMAR


Electronic Signature Date: 23-Jul-2022 Electronic Signature Date: 23-Jul-2022
Intern was able to estimate
Estimation of Masonry
the rebars needed, stirrups,
wall and Bond Beam. Supervisor tasks intern to
concrete, formworks for
Estimation of do an estimation of Bond
bond beam. Intern was able
plastering & CHB beam and CHB wall at guest
July 21,2022 to estimate the plastering N/A
laying. Estimate house office. And estimate
and CHB of the masonry wall.
Cement, Sand, Gravel the Concrete for bond
Intern was able to get the
for Bond beam and beam and masonry wall.
materials needed for
Masonry wall.
Cement, Sand, and Gravel.
Intern was able to estimate
Supervisor tasks interns to
the plastered and CHB of GF
Estimation of CHB do an estimation of
and 2F by getting the area.
Laying and Plastering, plastering and CHB of
Intern was able to estimate
Estimation of Plas Ground Floor and 2F.
the cement, gravel, and sand
wall, Estimation of Supervisor tasks interns to
for the plas wall at dining and
July 22,2022 Extension of Slab, do an estimation of cement, N/A
for the extension of slab by
Acceptance of sand, and gravel of Plas wall
understanding the estimate
opening, Floor at dining and extension of
of Max Fajardo. Intern was
Mapping, Pictures for slab. Supervisor task the
able to take pictures of all the
progress report. interns to do the pictures
progress that happened in
for the progress report.
the site for this week.
July 23,2022 N/A
Prepared by: Checked by:

ALYSSA MARIE R. ASUNCION ENGR. JOYCE C. VILLAMAR


Electronic Signature Date: 23-Jul-2022 Electronic Signature Date: 23-Jul-2022