SECTION (7)
TEST ON COMPLETION AT SITE
CONTENT
7.RELIABILITY TESTS ...................................................................................................... 171
7.1Efficiency Tests ............................................................................................................ 171
7.2RE-TESTING: .............................................................................................................. 172
7.3ADJUSTMENT OF PLANT: ....................................................................................... 172
7.4PERFORMANCE TEST .............................................................................................. 172
7.5GOVERNING TESTS ETC. ........................................................................................ 172
7.6REJECTION OF PLANT: ............................................................................................ 172
7.7TEST RESULTS AT END OF GUARANTEE PERIOD ............................................ 173
7.8POWER STATION CRANE: ...................................................................................... 173
7.9Test On Completion at Site .......................................................................................... 173
7.9.1Mechanical: ........................................................................................................ 173
7.9.2Electrical ............................................................................................................. 174
7.9.2.1Generator : .................................................................................................... 174
7.9.2.2Generator control panel (GCP). ..................................................................... 174
7.9.2.3Common control panel (CCP) ...................................................................... 174
7.9.2.4Engine auxiliary drive panel (EA) ................................................................. 174
7.9.2.5Protection Relays. .......................................................................................... 174
7.9.2.6Transformer test. ........................................................................................... 174
7.9.2.7 11KV busbar................................................................................................. 174
7.9.2.8Current transformer: ..................................................................................... 174
7.9.2.9Voltage transformer Test. .............................................................................. 174
7.9.2.1024V battery charger test............................................................................... 174
7.9.2.11 11KV switchgear test. ................................................................................ 174
7.9.2.12Cable test (High pressure & Continuity test)............................................... 174
7.9.2.13Motor test (by meager) & Load test. ........................................................... 174
7.9.2.14Over speed test. ........................................................................................... 174
7. RELIABILITY TESTS
When the contractor has notified the purchaser / Engineer that the plant at the site is
ready for commercial service, The set and all its auxiliaries will be requited to operate
under the working conditions of the station, within the limits of the output specified,
either continuously or intermittently as may be more convenient for the work of the
station, without failure or interruption of any kind for a period or thirty days.
The plant will be operated by the station staff during the reliability test period but the
Contractor will be allowed to make any minor adjustments which may be necessary
provided such adjustments do not In any way interfere with or prevent the commercial
use of the plant by the purchaser or result in reducing the out put or decreasing the
efficiency.
Should any failure or interruption occur in any portion of the plant, due to or arising
from faulty design, materials or workmanship, or due to omission or incorrect erection
but not otherwise, sufficient to prevent the full commercial use of the plant during the
reliability period, then the period will be cancelled and a new reliability period of
thirty days shall commence' after the Contractor has remedied the cause of the defect.
For the purpose of this Clause. The plant shall be sub-divided as follows:
¾ Engine ac generator set and auxiliaries.
¾ Switchgear.
¾ Cabling.
¾ Transformer.
The onus of proving that any defect is due to causes other than those referred to in the
preceding paragraph will lie with the Contractor.
Since the efficiency test is normally performed subsequent to the reliability test
period, the professional acceptance certificate will be issued on the satisfactory
completion of the efficiency test. The issuing of any of this responsibilities in respect
of the proving of the efficiency guarantees nor percent the purchaser from seeking any
of the remedies failing to be proved. The professional Acceptance Certificate shall be
dated to the completion date of the successful reliability period and this shall be the
date from which the twelve month guarantee will operate.
A certified calibration curve shall be provided for each check Instrument and in
particular this must apply to the check instruments which are to be provided to
measure the kwn generated and the fuel and lub. oil consumed. The Contract includes
for the Provision of any recalibration certificate which may be required by the
purchaser/ Engineer to be taken before the tests.
7.2 RE-TESTING:
Should the plant or any portion thereof fail under these tests to give the performance
required. Then any further tests which may be considered necessary by the purchaser/
Engineer may be carried out in a similar manner but the whole cost of the repeated
test shall be borne by the contractor, except that if the retesting is carried out on the
normal commercial load of the station then the fuel, water and lubricating oil used and
the normal operating staff shall be supplied free by the purchaser.
7.3 ADJUSTMENT OF PLANT:
When the plant is completely erected and before the official tests are made, the
Contractor will be given, if desired by him, seven days within which to carry out any
preliminary test and to make any necessary adjustments..
The setting of clearances and all other adjustments provided for the tests shall be the
normal working adjustments and shall be retained without alteration for the full
reliability period.
7.4 PERFORMANCE TEST
The tests on completion, which shall be carried out as described under will include
fuel consumption and electrical tests, together with any other test which the Engineer
may require in order to determine that the plant is in accordance with the
Specification and guarantee.
The load to be used for fuel consumption and temperature rise tests will be the
ordinary load of the station.
7.9.2 Electrical
7.9.2.1Generator :
Generator test general check.
Generator air gap test.