Professional Documents
Culture Documents
Grafic Executie
Grafic Executie
Mode Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025
1 Ansamblu rezidential NOVUM VIILOR-bloc A 165 days Mon 11/10/21 Thu 21/04/22 91%
2 anunt incepere lucrari Primarie Sector 5 3 days Mon 18/10/21 Wed 20/10/21 100%
3 anunt incepere lucrari ISC 3 days Wed 20/10/21 Fri 22/10/21 100%
4 proces verbal trasare limita proprietate 1 day Mon 08/11/21 Mon 08/11/21 100%
5 Organizarea de santier 94 days Mon 11/10/21 Thu 27/01/22 100%
57 Infrastructura 100 days Mon 08/11/21 Thu 03/03/22 100%
58 sapatura plot -4.25- 4.95 faza 1 21 days Mon 08/11/21 Wed 01/12/21 100%
70 sapatura plot -5.25 faza 1 31 days Fri 03/12/21 Fri 07/01/22 100%
83 armare radier zona bloc A zona -4.25- 4.95 24 days Mon 22/11/21 Sat 18/12/21 100%
93 instalatii radier zona bloc A 26 days Wed 24/11/21 Thu 23/12/21 100%
103 cofrare radier zona bloc A ( inclusiv base) 5 days Thu 16/12/21 Tue 21/12/21 100%
106 radier zona bloc A si parcare subterana 50 days Mon 22/11/21 Tue 18/01/22 100%
134 Verticale subsol parcare subterana 53 days Tue 21/12/21 Sat 19/02/22 100%
154 Placa peste subsol corp A si parcare subterana 16 days Mon 14/02/22 Thu 03/03/22 100%
164 Lucrari de incinta 39 days Mon 31/01/22 Wed 16/03/22 92%
178 Hidroizolatie pereti subsol 27 days Mon 14/02/22 Wed 16/03/22 100%
187 Bransament apa-canal faza 1 (interior proprietate)20 days Mon 21/02/22 Tue 15/03/22 4%
197 Umplutura pamant bloc A si parcare subterana 19 days Mon 07/03/22 Mon 28/03/22 0%
200 Suprastructura 43 days Wed 02/03/22 Thu 21/04/22 93%
201 PARTER 19 days Wed 02/03/22 Wed 23/03/22 100%
215 ETAJ 1 31 days Wed 16/03/22 Thu 21/04/22 88%
216 Verticale etaj 1-bloc A 20 days Wed 16/03/22 Thu 07/04/22 100%
224 Placa peste etaj 1 corp A 21 days Mon 28/03/22 Thu 21/04/22 75%
225 solicitare planse proiect 1 day Mon 28/03/22 Mon 28/03/22 100%
226 receptionare planse proiect 1 day Mon 11/04/22 Mon 11/04/22 100%
227 cofrare placa si grinzi si scara P_ E1 9 days Mon 04/04/22 Wed 13/04/22 100%
228 dispunere goluri tehnologice 2 days Mon 04/04/22 Tue 05/04/22 100%
229 lansare comanda fier grinzi peste etaj 1 2 days Mon 11/04/22 Tue 12/04/22 100%
230 aprovizionare fier grinzi , placa, scara 3 days Thu 14/04/22 Mon 18/04/22 100%
231 armare grinzi 3 days Mon 18/04/22 Wed 20/04/22 0%
232 armare placa -plasa inferioara 1 day Wed 20/04/22 Wed 20/04/22 0%
233 armare placa -plasa superioara si scara P_1 E1
day Thu 21/04/22 Thu 21/04/22 0%
234 betonare placa 1 day Thu 21/04/22 Thu 21/04/22 0%