Control phase
Control before burn off
No. Component / Control Point Control of Document
point
Stator:
1 Core test a Losses in lamination SC-I 020.10.90

2 Winding data if valid a Type of winding Note on work order


winding information is not b Length of overhang
available c Electrical connection

Rotor:

3 Winding data if valid a Type of winding Note on work order


winding information is not b Length of overhang
available c Electrical connection

Rev. Date Prepared by Division/ Department Description


(yyyy-mm-dd)
A 2012-09-12 BS PG Service First version
B 2013-10-18 BS PG Service Replaced AC machine with induction machine in heading