Professional Documents
Culture Documents
Great job to WEN IRATA team for excellent safety performance, completed rope access job for Telecom tower
Rivalinno Handoko, Solehudin, Nur Choirul Anwar, Deva, Khaerul Anwar and Rizal Firdaus
TMJO INSULATION
Great job to Edri Maruf Pramudia – Insulator for
excellent safety performance during performing
confined space work
“Line Of Fire”
THE BEST SAFETY PERFORMER OF THE MONTH
November 2022
THE BEST ENVIRONMENTAL PERFORMER OF THE MONTH
November 2022
“WORKER SPEAK-UP” SAFETY SESSION FEEDBACK
11
GROUP EXERCISE
FOCUS GROUP DISCUSSION
Feedback from
“Workers Speak up – Safety Sessions”
INCIDENT REVIEW
(26.11.2022 – 02.12.2022)
|16
INCIDENT REVIEW
(26.11.2022 – 02.12.2022)
|18
INCIDENT REVIEW
(26.11.2022 – 02.12.2022)
|19
INCIDENT REVIEW
(26.11.2022 – 02.12.2022)
|20
SSL Walkthrough Schedule
BARRIER
HOUSEKEEPING MANAGEMENT &
Area 1 Train 3 WALKTHROUGH IWMF DROP OBJECT Train 3
(INTERNAL SBC ONLY) WALKTHROUGH
(INTERNAL SBC ONLY)
Meeting Point BRM Train 3 TBA Insulation/ DDT TBA BRM Train 3
BARRIER
HOUSEKEEPING MANAGEMENT &
Jetty Load
Area 2 Kalikobara WALKTHROUGH DROP OBJECT Brownfield
Platform
(INTERNAL SBC ONLY) WALKTHROUGH
(INTERNAL SBC ONLY)
SECURITY POST 11
Meeting Point BRM Kali Kobara TBA EX. MDI Office TBA
(NEAR TRAIN 3)
Guidelines for Workers about High-Level Noise at Train 3 & Utility Area
Noise Personal Protection Zone: ✓ MANDATORY TO HAVE and BRING HEARING
1. LP Steam Blow: Double hearing protection: < 10 m, Single hearing protection: 10 – 40 m PROTECTION DEVICE (EARPLUG / EARMUFF)
2. HP Steam Blow (with silencer): Double hearing protection: < 20 m, Single hearing protection: 20 – 100 m
WHILE ENTERING TRAIN 3 & UTILITY.
✓ Noise Level Limit of Hearing Protection:
✓ Double Hearing Protection: 100 dBA
✓ Single Hearing Protection: 82 dBA
T08 T07 T05 ✓ There is two types of Steam Blowing: High
T03
Pressure (HP) and Low Pressure (LP).
ORF
e-CoW Transition of Utilities
• HP Steam Blowing Preparation ORF and Brownfield Tie-In
• Main Substation
• N2 Leak Test Campaign
• GIS
• STG A/B/C Jetty
• Recycled Steam Condensate A/B/C • MRT on Hypochlorite Injection Pump
Note: awaiting SH Sign-off- expected date of transition 8-9 Dec, 2022 • Lube Oil Flushing for Jetty Loading Arms Dec. 07,2022|24
(See next slide) • Fire Water Flushing in BOG/Desalination Area
Background
• STGs, Recovered Steam System, and Utility GIS & Substations have been handed
over to MPO (SH-1 signed).
• Robust hazard and activity control New Utility area.
• Systematic activity/work record under eCOW control.
• Minimize any unplanned disturbance for normal running equipment.
Recommendation
• Expand eCOW Area Implementation at TEP New Utility covering newly handed
over system/facilities (STGs, Recovered Condensate, and Substations)
New Utility eCOW Expansion Area Layout
SUEM 2B 3D Layout
T-02
UTILITIES
T-06
T-09
T-04
T-10
T-01
T-03
T-07 T-08
|27
|28
SUEM 2B Critical Joint Layout
|29
THANK YOU
|30