(Project Time Frame: September 2021- March 2022)

I. Project Contacts:

Contacts Role Email


Queenie E. CI Team Leader queenie.butalid@deped.gov.ph
Butalid
Marivic A. Alcaide CI Team marivic.alcaide@deped.gov.ph
Member
Annie D. CI Team annie.manahon@deped.gov.ph
Manahon Member
Teofila A. CI Team teofila.tiongco@deped.gov.ph
Tiongco Member
Lorna M. Deleǹa CI Team lorna.delena001@deped.gov.ph
Member
Dr. Modesta C. CI M and E modesta.cabiara@deped.gov.ph
Cabiara Leader
Josephine E. Ma CI M and E josephine.ma001@deped.gov.ph
Member
Elani D. Alalong CI M and E elani.alalong@deped.gov.ph
Member
Ana Grace A. CI M and E anagrace.alabata@deped.gov.ph
Olequino Member

II. Project Summary:

LIBROrary in a Box Project is the adaptation version of the Gugma sa

Pagbasa Project of Bulak Elementary School which starred from 2018-

2020 when in-face learning was yet applicable. However, with the havoc

made by the Covid 19 Pandemic to the usual educational setting, a

1
turnaround project must be initiated to continue educating young minds of

Bulak Elementary School despite the introduction of distance learning

modalities to combat the ongoing disease while everyone awaits concrete

solutions for in-face learning to happen.

In Bulak Elementary School, a considerable number of non-readers

and non-numerates exist primarily because the children enrolled in this

school are yet starting their formative years in their academic journey.

Though the situation is understandable, it would pose a great challenge for

the school leader and teachers to contest the situation to higher ground.

With the advent of massive changes in the academic environment,

reading and learning number concepts are basic skills that need to be

developed in young minds for them to thrive in the spiraling educational

system. These two skills are lifesavers of today’s generation because it

fuels them to gain more in life by capacitating themselves with the basic

skills of reading and numeracy. Relatively, we need professional and well-

trained teachers to be able to see to it that these basic skills are inculcated

in the minds of the children. However, the pandemic situation does not

permit direct contact between the teacher and the children due to health

measures set by the health department of this country, the school must

navigate other means to concretize these ideals.

The current situation led to the decision of creating an academic home

environment where these children live and study in the meantime while the

access to physical school is restricted. LIBROrary in a Box Project was

then conceptualized to put up a class home where these children live. L-

ove for I-nteresting B-ooks to R-ead O-n (rary-Read Aloud, Read with You)

2
envisioned to put up a sense of personal library at home amid the

challenges of a pandemic to sustain the learners’ literacy and numeracy

skills of Bulak Elementary School. The box is utilized by the learners

where the learning resources from the school are brought home by their

home learning facilitators. It includes the printed modules which is the

main facility for learning, supplementary books to enhance the capacity to

read and mastery of numeracy skills, laminated materials for further

remediation to learners who are academically struggling, and wallpapers

for mastery of nationalistic and school customs. The learners are required

to put up a wall in their homes posting the wallpapers and setting the

LIBROrary box beside their study area.

By doing so, the school anticipates an increment in learners’ academic

performance at the end of the school year with the great partnership with

the home learning facilitators (parents and relatives helping the child to

learn) as front liners in this claim.

III. Project Background

The LIBROrary in a box project is a learning support system to improve

continuously the literacy and numeracy skills of learners of Bulak

Elementary School during these challenging times. Literacy and numeracy

skills help learners to thrive across different learning areas. The project

specifically focuses on literacy development which includes reading and

writing skills. At the same time, it also enables learners to develop

learners’ numeracy skills which focus on enhancing the ability to

3
comprehend and apply mathematical concepts and processes in solving

problems and making decisions that can be applied to real-life scenarios.

IV. Project Objectives

The LIBROrary in a Box project aims to support learning activities for

children during the implementation of the distance learning scheme.

Specifically, it

a. Requires all children to have learning spaces at home while they

develop their literacy and numeracy skills.

b. Expects academic gains in all subject areas by providing learners

with effective learning resources for enhancement.

c. Inspires other learners by showcasing readers and mathematicians

of the week/month on a social media platform.

V. Project Methodology

This section presents the phases of implementation of the project to

achieve its desired goals.

Work Task time Persons Resource Project


Objectives
Breakdown Estimates Responsible Requirements Cost
Pre-Implementation Phase
1. Organize a CI Meet the August School Head Laptop & Printer Php
Team to work participants of 2021 Internet 100.00
on the project. the CI training CI Team Connection
last July 2021 Leader and Communication
and undergo Members platforms and
the stages of devices.
CI Project CI M and E
Making in Team
schools.
Define roles School Head Laptop & Printer Php
and August Internet 100.00
responsibilities 2021 Connection
of the CI Team Communication
through a platforms and

4
Work Task time Persons Resource Project
Objectives
Breakdown Estimates Responsible Requirements Cost
school memo. devices.
Create general School Head Laptop & Printer Php
guidelines on August Internet 100.00
the 2021 Connection
implementatio Communication
n of the platforms and
LIBROrary in a devices.
Box Project
2. Design the Layout a August School Head Laptop & Printer Php
LIBROrary in a design for 2021 School ICT Internet 100.00
Box package LIBROrary in a Coordinator Connection
Box Project for Communication
packaging. platforms and
devices.
Seek partners School 216 pcs plastic Php
to fund plastic 4th Week Head/ bin boxes 50,000
bin boxes for of August Grade Level
216 pupils. 2021 to 1st Advisers
week of
December
2021
Conduct School Head Laptop & Printer Php
orientation to 1st Week Internet 100.00
home learning of Grade Level Connection
facilitators on September Advisers Communication
how to set up 2021 platforms and
for the Home devices.
LIBROrary in a learning
Box Project at Facilitators
home.

Implementation Phase/ Project Deliverables


1. Distribute the Monitor the 2nd Week School Head Learning Php
LIBROrary in a setting-up of of Resources 10,000
Box package to the home September CI Team
set up for the learning 2021 Leader and Wallpapers
home learning spaces at Members reflecting the
spaces of the home through DepEd’s VMG,
learners at the GC of the CI M and E National
home. grade levels Team Anthem,
and the Prayers Before
teachers. Home and after study,
learning Literacy/
Facilitators Numeracy
charts
2. Monitor the Conduct Quarterly School Head Laptop & Printer Php

5
Work Task time Persons Resource Project
Objectives
Breakdown Estimates Responsible Requirements Cost
academic quarterly CI Team Internet 100.00
performance of SMEA as a Leader and Connection
the learners. benchmark for Members Communication
technical CI M and E platforms and
assistance. Team devices.
Home
learning
Facilitators
3. Feature Ask for grade Weekly/ School Head Laptop & Printer Php
readers and level advisers Monthly Internet 5000.00
mathematicians to recommend School ICT Connection
for the week/ reader/ Coordinator Communication
month mathematician platforms and
of the week to Grade Level devices.
be featured Advisers
through social
media
platforms and
tarpaulins
showcasing
learners’ ability
in literacy and
numeracy
skills.
Post-Implementation Phase
1. Conduct Mobilize the CI March School Head Laptop & Printer Php
project M and E Team 2022 Internet 500.00
effectiveness to conduct CI M and E Connection
assessment. project Team Communication
effectiveness platforms and
assessment. devices.

Show a
document
showing the
effectiveness
of the project.
(Accomplishm
ent report/
Project
Completion
report)

2. Recognize the Conduct a March School Head Laptop & Printer Php
team’s efforts. recognition 2022 Internet 1000
ceremony of Connection

6
Work Task time Persons Resource Project
Objectives
Breakdown Estimates Responsible Requirements Cost
the team Communication
players of the platforms and
project by devices.
giving medals
and
certificates.

VI. Project Risk Management


If Risk
Happens,
Impact on Specific
Specific Action
Milestone Likely Risk Project if Risk Action to
to Prevent Risk
Happens Soften
Impact of
Risk

Pre- Participants from The planning to Conduct a re- Walkthrough


Implementation the CI training will develop orientation or with the
Activities not be able to innovation short refresher participants
recall the CI through the CI course to the and ensure
Process way in school will participants. the CI
not happen. process is
applied.
Implementation Implementors of The goal of the Encourage Apply
Activities the project will not project will not be implementors partnership
cooperate. achieved. through constant skills to
reminders the various age
purpose of the groups to
project and its strengthened
impact to the relationship
bigger with the
community. bigger
communities
for possible
support.
Post- Team players will The project is Conduct quarterly Make sure
Implementation not be able to ineffective. SMEA so that the that the team
Activities reach the targets CICP’s will be is going
addressed and towards the
resolved at the goal and
end of the project. objectives
through
close
monitoring.

7
Prepared by:
QUEENIE E. BUTALID EdD MARIVIC A. ALCAIDE
School Principal I/ CI Team Leader Teacher II/ CI Team Member

ANNIE D. MANAHON TEOFILA A. TIONGCO


Teacher II/ CI Team Member Teacher III/ CI Team Member

MODESTA C. CABIARA EdD JOSEPHINE E. MA


Master Teacher I/ M and E Team Leader Teacher III/ CI M and E Team Member

ELANI D. ALALONG ANA GRACE A. OLEQUINO


Teacher I/ CI M and E Team Member Teacher III/ CI M and E Team
Member

Recommending Approval:

BEDA JOVENCIANA A. DAVAD EdD


Public Schools District Supervisor
Dauin District

Approved:

SENEN PRISCILLO P. PAULIN CESO V


School Division Superintendent
Division of Negros Oriental