You are on page 1of 3

TOKYU-WIKA JOINT OPERATION

Surface Section CP101 & CP102


Construction of Jakarta Mass Rapid Transit Project

BOX CULVERT CHECKLIST

Lot No: Date:

Items to be Checked Yes No


Pre-Checks

Is approval for documentation done prior to commencement of work?

Are all the drawings " Good for Construction"?

Is compressive strength of Pre-cast units used in this Lot tested


& verified as per design?

Survey / Staking Out for temperory & new culvert

Is Survey/ staking out completed?

Is position/ alignment of the culverts marked on ground?

Temperory diversion

Is "Permit to Dig" completed & obtained?

Is correct position/ alignment of the culverts marked on ground?

Is the excavation level for temp. drainage verified by survey team?

Is loose soil at base compacted before lean concrete?

Demolition of existing culvert

Is the demolition & cleaning work carried out as specified in MS?

Spun Pile installation

Is the survey for Spun pile installation carried out?

Is piling Rig installed properly & it's verticality checked?

Are the piles installed as per design drawings?

(Tolerances for - Position: 100 mm in any direction at cut-off level; Vertiality: 1 in 75 deviation from vertical; Rake: 1 in 25
deviation from specified rake)

Base concreting for new culvert

Is the excavation level for new culvert drainage verified by survey team?

Are right dimensioned rubble stones placed & compacted?

Is the base slab Concrete thickness and level checked?

Is the slump test carried out and slump found to be as per design?

TWJO-ITP-PRC-0005-CHK-001revB Page 1 of 3
TOKYU-WIKA JOINT OPERATION
Surface Section CP101 & CP102
Construction of Jakarta Mass Rapid Transit Project

BOX CULVERT CHECKLIST

Have the concrete cylinders casted and kept for testing?

TWJO-ITP-PRC-0005-CHK-001revB Page 2 of 3
TOKYU-WIKA JOINT OPERATION
Surface Section CP101 & CP102
Construction of Jakarta Mass Rapid Transit Project

BOX CULVERT CHECKLIST

Concrete Pouring for Culvert

Is the TWJO-ITP-GEN-0003-CHK-001 & 002 completed prior to concreting?

Backfilling of temperory and new culvert

Have the segments achieved required compressive strength?

Is the backfilling carried out in specified manner as mentioned in MS?

Is the thickness of each backfill layer as per specifications?


(thickness in loose condition = max. 300 mm)

Is the compaction carried out as mentioned in MS?

Remarks:

Checked By:
(Subcon) Name Designation Signature

Verified By:
(TWJO) Name Designation Signature

TWJO-ITP-PRC-0005-CHK-001revB Page 3 of 3

You might also like