Project: Maintenance Work for Amrican Shool of Creative , Dubai

Client : Beam Group Shr

MAINTENANCE COMPLETION SCHEDULE


Plan Manpower
Sl Activity Description Unit Qty % Plan % Done Remarks
Start Date Work Period Finish Date Days

Replacment of 3 Flush fittings of HandiCap Toilet & 6


1 Lot 9 Commencemnt Date 2 Days - 3 100% 0%
Flush fittings of toilet

Supply and replacment of LED lamp Class Room LED


2 Lamps- 34 Nos Lights Coridoor - 11 Nos Lights Toilet- Lot 1 Commencemnt Date 3 Days - 4 100% 0% MATERIAL WILL SUBBMIT TO APPROVAL
5 No Light Sensors - 12 Nos light Switch - 18 Nos

Expansion joints to be cleaned, sealed & fixed where


3 Lot 1 Commencemnt Date 2 Days - 2 100% 0%
missing
Ceiling tiles to be aligned & any dented or damaged
4 Lot 1 Commencemnt Date 3 Days - 4 100% 0%
tiles replaced throughout

▪FAHU 1
LOCATION- PRINCIPAL CORRIDOOR
1. SUPPLY FAN IS NOT WORKING
2. DAMAGE ON DUCT
3. COMPRESSOR B2 AND CONTACTOR
4. THERE IS ISSUE WITH DISPLAY
▪ FAHU 2
LOCATION- GF 1- inspection will be done by Specalist
1. FILTER DOOR HANDLE DAMAGE 2- Electrical inspection will be done
▪FAHU 3 3- Mechinecal Inspection will be done
LOCATION- FF 4- Replace the part where required
1. SUPPLY FAN AND RETURN FAN 5 -Repair part where required
5 2.CONDENSOR B1 AND B2 IS HAVING Lot 1 Commencemnt Date 13 Days - 7 100% 0% 6 -Testing the machine
▪FAHU 4 7- Handing over the sestyem
LOCATION- FF
1. SUPPLY FAN IS NOT WORKING
2. FILTER DOOR HANDLE DAMAGE

▪PACU 1
LOCATION- MAIN RECEPTION
1. SUPPLY FAN AND COMPRESSOR
▪PACU 2
LOCATION- INDOOR PLAY AREA
Replacment of Split unit compressor - 1 no &
repairing of 2 split units leakage

Replace damaged wall tileswhere cracks and holes


6 Lot 1 Commencemnt Date 2 Days - 2 100% 0%
are presnet all areas
Ensure blinds clean & in working order,replace
7 Lot 1 Commencemnt Date 3 Days - 1 100% 0%
damaged & ensure chain is fixed to wall
Covers required on network cable holes in all
8 Lot 1 Commencemnt Date 1 Day 1 - 2 100% 0%
classrooms
9 Any damaged skirting to be replaced Lot 1 Commencemnt Date 2 Days - 3 100% 0%
10 Any damaged grout to be redone for tiling Lot 1 Commencemnt Date 3 Days - 2 100% 0%
Proper corner guards to be applied throughout all
11 Lot 1000 Commencemnt Date 7 Days - 3 100% 0% Approved MATERIAL WILL ORDER AND SUPPLY
corners
Supply and replacment of Faulty Control Panel of
12 Lot 1 Commencemnt Date 1 Day - 2 100% 0%
Genset
Supply and replacment of Faulty Display of Capacitor
13 Lot 1 Commencemnt Date 1 Day - 2 100% 0%
Bank
Supply and replacment of Faulty Access Control of
14 Each 2 Commencemnt Date 1 Days - 3 100% 0%
doors - 2 Nos
Removal of ASCS Signage in the Swimming Pool
15 Lot 1 Commencemnt Date 3 Days - 3 100% 0%
Area
Re painting of the external -road
16 Lot 1 Commencemnt Date 4 Days - 10 100% 0%
markings,arrows/curb stones etc. JOUTIN EPOXY PAINT WILL APPLY
Levelling of all interlocks where trip hazards are
17 Lot 1 Commencemnt Date 5 Days - 5 100% 0%
presented
Dead trees to replace with new one- 3 Nos Palm
18 Nos 3 Commencemnt Date 2 Days - 3 100% 0%
Tree
Security cabin door to be replaced with Aluminium
19 Nos 2 Commencemnt Date 14 Days - 4 100% 0%
door with Half Glass - 2 Nos Door Cabin will order and fixed on site
Security cabin Kitchen cabinets to be replaced - 2
20 Nos 2 Commencemnt Date 13 Days - 3 100% 0%
Nos Cabin Will order , supply and fixed
Supply and fixing of Pole protector in the Play Area -
21 Lot 1 Commencemnt Date 4 Days - 2 100% 0%
Wherever Damaged
22 Expansion joint cover required LM 1 Commencemnt Date 3 Days - 2 100% 0%
23 Cable entries opening requires sealing Lot 1 Commencemnt Date 2 Days - 2 100% 0%
24 All cracks on roofs requires repair Lot 1 Commencemnt Date 1 Days - 4 100% 0%
25 All shaft openings to seal Lot 1 Commencemnt Date 1 Days - 4 100% 0%
All ac and electrical cables requires proper foster
26 RM 1000 Commencemnt Date 3 Days - 7 100% 0%
insulation- Repaint with Oil paint- Approx 1000 RM
27 Damaged insulation needs replacement Lot 1 Commencemnt Date 3 Days - 7 100% 0%
Damaged GI trunking to be replaced and secured
28 Lot 1 Commencemnt Date 3 Days - 7 100% 0%
properly
29 Replace rusted deluge system fittings & paint Lot 1 Commencemnt Date 2 Days - 3 100% 0%
*Swimming pool Filteration pump system replacment
- 1 No - 2 HP, Filter Lid with O ring - Europa
30 Filter Lot 1 Commencemnt Date 3 Days - 3 100% 0%
*Replacment of Sump pump- Submersible pump KP
250- Grundfos with PVC fittings- 1 No Will contact with belhasa for maintenace and finalize
Domestic Water -Booster pumps on roof not working
31 Lot 1 Commencemnt Date 1 Days - 2 100% 0%
to be fixed along with required repair work
Repair or replace the exisiting pump
32 Damaged ducts on roof to be repaired Lot 1 Commencemnt Date 3 Days - 7 100% 0%
Repair of the Canopies & Pole with Paint Touch Up
33 Lot 1 Commencemnt Date 2 Days - 7 100% 0%
wherever Applicable & rusted Area
Supply steel wooden outdoor garbage bin. Size: 100
34 Nos 4 Commencemnt Date 7 Days - 1 100% 0% Material will order and supply
* 200 cm.