Professional Documents
Culture Documents
RA-001 Welding & Gas Cutting Scope: Welding & Gas Cutting Rev:01
Risks
Control Measures
Page 1 of 14
Lucky Engineering Services
Risk Assessments for Date:
Miscellaneous Metal Project: Construction of 7 Projects 06/06/2020
Works in Al Ain Zoo
Control Measures
Gas welding torch to be checked regularly.
Sufficient illumination at work areas, LUX meter can be used to measure.
Welding sets calibration.
Oxy-Acetylene cylinders must be stored at designated areas & keep segregated with an appropriate distance. Don’t store
inside buildings. Keep cylinder upright and secured.
At work areas oxy-acetylene cylinders must be carried inside specified trolleys.
Required Permits
Excavation Hot Works Confined Space Ladder OPE Diving
Responsibilities / Accountabilities
General Manager Lifting Coordinator Admin Manager Lifting Scaffold Supervisor
Foreman
Supervisor
Services Emergency Response
Staff Site Manager Safety Team Dive Master
Coordinator
Procurement Engineering Commercial
Project Engineer Quality Team Human Resources
Manager Manager Manager
Marine
Project Manager Logistic
Superintendent Add Other Detail as required
Coordinator
PPE Requirements
Site Mandatory PPE Hand gloves
Face shield
Safety Shoes
Page 2 of 14
Lucky Engineering Services
Risk Assessments for Date:
Miscellaneous Metal Project: Construction of 7 Projects 06/06/2020
Works in Al Ain Zoo
RA-002 Loading & Unloading Materials Scope: Loading & Unloading Materials using Boom Loader/Forklift
Rev:01
Risks
Machine Failure
Falling of Object/Material
Failure of Crane
Failure of lifting gears
Material break / damage
Injury to person/operators Fatality
Material break / damage
Injury to person/operators
Control Measures
Third party certificate for crane, operator and riggers.
All the lifter gear should have third party certificate and physically in good condition.
Lifting permit prior.
All the lifter gear should have third party certificate and physically in good condition. Color Coding
Loading and unloading area must be barricaded and signage’s to be installed
Loading and unloading of material should occur at designated dispatch and receivable points
A lifting supervisor to be assigned
Rigger shall check rigging & slinging before lifting
Load must be raise to require height to move to designated place
Proper supervision by rigging foreman for unloading & loading
Ensure dead end of wire rope is properly secured.
Trained and experience driver should operate crane only.
Required Permits
Excavation Hot Works Confined Space Ladder OPE Diving
Responsibilities / Accountabilities
General Manager Lifting Coordinator Admin Manager Lifting Scaffold Supervisor
Foreman
Supervisor
Page 3 of 14
Lucky Engineering Services
Risk Assessments for Date:
Miscellaneous Metal Project: Construction of 7 Projects 06/06/2020
Works in Al Ain Zoo
PPE Requirements
Site Mandatory PPE Task Specific PPE
Page 4 of 14
Lucky Engineering Services
Risk Assessments for Date:
Miscellaneous Metal Project: Construction of 7 Projects 06/06/2020
Works in Al Ain Zoo
Control Measures
Required Permits
Excavation Hot Works Confined Space Ladder OPE Diving
Working at Height
ESSWP Add Add Add Add
Page 5 of 14
Lucky Engineering Services
Risk Assessments for Date:
Miscellaneous Metal Project: Construction of 7 Projects 06/06/2020
Works in Al Ain Zoo
Responsibilities / Accountabilities
General Manager Lifting Coordinator Admin Manager Lifting Scaffold Supervisor
Foreman
Supervisor
Construction Services Emergency Response
Staff Safety Team Dive Master
Manager Coordinator
Procurement Engineering Commercial
Project Engineer Quality Team Human Resources
Manager Manager Manager
Marine
Project Manager Logistic
Superintendent Add Other Detail as required
Coordinator
PPE Requirements
Site Mandatory PPE Face Shields
Safety Harnesses (Double Lanyards) Welding Masks
Gloves (decking and steel handling) Respiratory Protective Equipment
RA-004 Use of Hand tools Scope: Use of Hand tools for driving bolts and beating metal Rev:01
Risks
Damaged tools.
Page 6 of 14
Lucky Engineering Services
Risk Assessments for Date:
Miscellaneous Metal Project: Construction of 7 Projects 06/06/2020
Works in Al Ain Zoo
Improvised tools
Sharp edges.
Cuts, Abrasions, Amputations to fingers and body parts of a persons.
Injury to eyes.
Broken bones and bruises.
Fall of tools from height.
Control Measures
Ensures the condition of the hand tools are good, when obtaining from the stores
Hand tools shall not be kept on walkways.
Hand tools shall be kept in tool boxes whenever not in use.
All tools shall be inspected for any damages on daily basis and at regular intervals
Tie off tools with a rope to prevent its fall while working at height or near egdes.
Don't keep any tools unattended at the height after work.
Tools should be free of oil & grease.
Secure the tools properly to prevent fall from height
Proper maintenance of tools should be done periodically.
Store keeper will inspect all the new tools before issuing to site.
Ensure operatives are wearing hand gloves during activity.
Required Permits
Excavation Hot Works Confined Space Ladder OPE Diving
Responsibilities / Accountabilities
General Manager Lifting Coordinator Admin Manager Lifting Scaffold Supervisor
Foreman
Supervisor
Construction Services Emergency Response
Staff Safety Team Dive Master
Manager Coordinator
Procurement Engineering Commercial
Project Engineer Quality Team Human Resources
Manager Manager Manager
Marine
Project Manager Logistic
Superintendent Add Other Detail as required
Coordinator
Page 7 of 14
Lucky Engineering Services
Risk Assessments for Date:
Miscellaneous Metal Project: Construction of 7 Projects 06/06/2020
Works in Al Ain Zoo
PPE Requirements
Site Mandatory PPE
Safety Goggles
RA:005 Potable Electrical Equipment Scope: Potable Electrical Equipment for grinding and welding of components on site Rev:01
Risks
Faulty/damaged equipment.
Site environment.
Trailing leads.
Page 8 of 14
Lucky Engineering Services
Risk Assessments for Date:
Miscellaneous Metal Project: Construction of 7 Projects 06/06/2020
Works in Al Ain Zoo
Poor Posture.
Untrained Users.
Injury to Person
Damage to Property
Eye Injury/Skin Injury
Back pain, Muscle Cramp
Electric Shock
Flying Particle
Noise
Vibration
Control Measures
All portable electrical equipment will be individually identified (colour coded) and subject to planned maintenance.
Only 110V tools allowed, if above required then obtained permit from main contractor.
Equipment supplied will be fit for purpose with regard to voltage, power and environmental conditions.
Visual inspection of equipment will be carried out before use.
Safety goggles/ face shield must be wearing while operating tools.
Training/TBT to be conducted prior to use tools.
Ensure the drill machine is inspected and color coded.
Ensure plug, drill bit, drilling machine and electrical cables are free from defects.
Ensure the power tools are provided with yellow colored industrial socket.
Don’t bend and hold the material between legs and operate the power tool.
Competent Operator.
Required Permits
Excavation Hot Works Confined Space Ladder OPE Diving
Responsibilities / Accountabilities
General Manager Lifting Coordinator Admin Manager Lifting Scaffold Supervisor
Foreman
Supervisor
Construction Services Emergency Response
Staff Safety Team Dive Master
Manager Coordinator
Procurement Engineering Project Engineer Commercial Quality Team Human Resources
Page 9 of 14
Lucky Engineering Services
Risk Assessments for Date:
Miscellaneous Metal Project: Construction of 7 Projects 06/06/2020
Works in Al Ain Zoo
PPE Requirements
Site Mandatory PPE Task Specific PPE
Safety Goggles
Safety Gloves
RA:006 Hot Works Scope: Hot Works Include Grinding Cutting, Welding for Fitting Items on Site Rev:01
Risks
Page 10 of 14
Lucky Engineering Services
Risk Assessments for Date:
Miscellaneous Metal Project: Construction of 7 Projects 06/06/2020
Works in Al Ain Zoo
Unauthorized Operation.
Unsuitable Working Environment (including low illumination work areas).
Fire & Explosion.
Severe Burns.
Severe Injuries
Property Damages.
Electric shock.
Eye damage of various kinds, either from exposure to light or from particles in the eye.
Heat stress leading to fainting in extreme conditions.
Respiratory problems from exposure to the welding fume.
Systemic poisoning off fumes from galvanised, lead-coated or other toxic metals, e.g. metal fume fever manifests itself in
the form of a flu-like illness which can last two to three days.
Ignition of other flammable materials whilst welding operations are under way.
Metal spatter.
Infra red and visible light given off by welding gas.
Ultra-violet radiation given off by electric arc welding.
Control Measures
Required Permits
Page 11 of 14
Lucky Engineering Services
Risk Assessments for Date:
Miscellaneous Metal Project: Construction of 7 Projects 06/06/2020
Works in Al Ain Zoo
Responsibilities / Accountabilities
General Manager Lifting Coordinator Admin Manager Lifting
Foreman Scaffold Supervisor
Supervisor
Construction Services Emergency Response
Staff Safety Team Dive Master
Manager Coordinator
Procurement Engineering Commercial
Project Engineer Quality Team Human Resources
Manager Manager Manager
Marine
Project Manager Logistic
Superintendent Add Other Detail as required
Coordinator
PPE Requirements
Site Mandatory PPE Task Specific PPE
Safety Goggles
Safety Gloves
Working at Edge.
Working Outside of Edge Protection.
Objects & Man Falling from Height.
Major Injury.
Page 12 of 14
Lucky Engineering Services
Risk Assessments for Date:
Miscellaneous Metal Project: Construction of 7 Projects 06/06/2020
Works in Al Ain Zoo
Control Measures
Required Permits
Excavation Hot Works Confined Space Ladder OPE Diving
Responsibilities / Accountabilities
General Manager Lifting Coordinator Admin Manager Lifting
Foreman Scaffold Supervisor
Supervisor
Construction Services Emergency Response
Staff Safety Team Dive Master
Manager Coordinator
Procurement Engineering Commercial
Project Engineer Quality Team Human Resources
Manager Manager Manager
Marine
Project Manager Logistic
Superintendent Add Other Detail as required
Coordinator
PPE Requirements
Site Mandatory PPE Task Specific PPE
Safety Goggles
Safety Gloves
Page 13 of 14
Lucky Engineering Services
Risk Assessments for Date:
Miscellaneous Metal Project: Construction of 7 Projects 06/06/2020
Works in Al Ain Zoo
Page 14 of 14