Status of Augmentation & R&M Work under JBVNL-DDUGJY in Palamu, Latehar & Garhwa District in Jharkhand

Sl. PKG Name of Existing PSS Status as per actual Survey Remarks
No.

Additional 1no. of 5MVA Power Transformer installation along


1 Palamu PKG-1 Hariharganj with 1no. of 33kV bay extension, 1no. of 11kV bay extension & Work not Started.
associated equipments.

1 Japla Not Required as intimated by JBVNL. Work not Started.

A. 2 nos. Augmentation w/o Addnl. finalized as per joint visit


2 Palamu PKG-2 Mohammad Ganj with JBVNL officials. Work not Started.
B. Qty. of Main Equipments has been freezed.

A. 1 no. Augmentation w/o Addnl. finalized as per joint visit with


3 Tukbera JBVNL officials. Work not Started.
B. Qty. of Main Equipments has been freezed.

A. 1 no. Augmentation with Addnl. finalized as per joint visit


4 Lesliganj with JBVNL officials. Work not Started.
B. Contour Survey was done.

5 Patan Not Required as intimated by JBVNL. Work not Started.


Palamu PKG-3

A. 1 no. Augmentation w/o Addnl. + 1 no. Augmentation with


Addnl. finalized as per joint visit with JBVNL officials.
6 Semra, (Chainpur) Work not Started.
B. Contour Survey was done.
C. Qty. of Main Equipment has been freezed.
A. 1 no. Augmentation w/o Addnl. finalized as per joint visit with
7 Panki JBVNL officials. Work not Started.
B. Qty. of Main Equipments has been freezed.

A. 1 no. Augmentation w/o Addnl. finalized as per joint visit with


8 Palamu PKG-4 Satbarwa JBVNL officials. Work not Started.
B. Qty. of Main Equipments has been freezed.

A. 1 no. Augmentation with Addnl. Is finalized as per joint visit


9 Padma with JBVNL officials. Work not Started.
B. Contour Survey was done.

Additional 1no. of 5MVA Power Transformer installation along


10 Chandwa with 1no. of 33kV bay extension, 1no. of 11kV bay extension & Work not Started.
associated equipments.

Additional 1no. of 5MVA Power Transformer installation along


11 Barwadih with 1no. of 33kV bay extension, 1no. of 11kV bay extension & Work not Started.
associated equipments.
Latehar
Additional 1no. of 5MVA Power Transformer installation along
12 Balumath with 1no. of 33kV bay extension, 1no. of 11kV bay extension & Work not Started.
associated equipments.

Additional 2no. of 5MVA Power Transformer installation along


13 Manika with 2nos. of 33kV bay extension, 2nos. of 11kV bay extension & Work not Started.
associated equipments.
Additional 1no. of 5MVA Power Transformer installation along
with 1no. of 33kV bay extension, 1no. of 11kV bay extension &
associated equipments.

Replacement of following damaged items is required at existing


PSS:
14 Garhwa PKG-1 Bhawnathpur a) 1no of 33kV VCB Work not Started.
b) 1no of 33kV PT
c) 2nos of 33kV ISO
d) 2nos of 11kV VCB
e) 2nos of 11kV ISO
f) 1no of 11kV PT
g) 5nos. of C & R Panels

15 Garhwa PKG-2 NO AUGMENTATION WORK AS PER SCOPE & ACTUAL SURVEY.

In existing PSS, the augmentation work at Majhiaon PSS has


16 Garhwa PKG-3 Majhiaon been carried out by JBVNL departmentally. JBVNL shall identify Work not Started.
alternate PSS to agency for carrying out augmentation work.
Additional 1no. of 5MVA Power Transformer installation along
with 1no. of 33kV bay extension, 1no. of 11kV bay extension &
associated equipments.

Replacement of following damaged items is required at existing


PSS:
17 Garhwa PKG-4 Bhandaria a) ACDB Work not Started.
b) DCDB
c) Disc Insulator & Post Insulator
d) 4nos. of 11kV VCB
e) 1no. C & R Panel
f) 1no of 11kV Bus coupler
g) Painting of existing structures