This document provides a status update on augmentation and repair & maintenance work under the Jharkhand Bijli Vitran Nigam Limited - Deen Dayal Upadhyaya Gram Jyoti Yojana in Palamu, Latehar, and Garhwa districts in Jharkhand. It lists 17 packages and the existing power substations under each package. For each substation, it describes the planned augmentation work and current status, noting that work has not started on any of the packages. Replacement of damaged equipment is also required at some substations.
This document provides a status update on augmentation and repair & maintenance work under the Jharkhand Bijli Vitran Nigam Limited - Deen Dayal Upadhyaya Gram Jyoti Yojana in Palamu, Latehar, and Garhwa districts in Jharkhand. It lists 17 packages and the existing power substations under each package. For each substation, it describes the planned augmentation work and current status, noting that work has not started on any of the packages. Replacement of damaged equipment is also required at some substations.
This document provides a status update on augmentation and repair & maintenance work under the Jharkhand Bijli Vitran Nigam Limited - Deen Dayal Upadhyaya Gram Jyoti Yojana in Palamu, Latehar, and Garhwa districts in Jharkhand. It lists 17 packages and the existing power substations under each package. For each substation, it describes the planned augmentation work and current status, noting that work has not started on any of the packages. Replacement of damaged equipment is also required at some substations.
Status of Augmentation & R&M Work under JBVNL-DDUGJY in Palamu, Latehar & Garhwa District in Jharkhand
Sl. PKG Name of Existing PSS Status as per actual Survey Remarks No.
Additional 1no. of 5MVA Power Transformer installation along
1 Palamu PKG-1 Hariharganj with 1no. of 33kV bay extension, 1no. of 11kV bay extension & Work not Started. associated equipments.
1 Japla Not Required as intimated by JBVNL. Work not Started.
A. 2 nos. Augmentation w/o Addnl. finalized as per joint visit
2 Palamu PKG-2 Mohammad Ganj with JBVNL officials. Work not Started. B. Qty. of Main Equipments has been freezed.
A. 1 no. Augmentation w/o Addnl. finalized as per joint visit with
3 Tukbera JBVNL officials. Work not Started. B. Qty. of Main Equipments has been freezed.
A. 1 no. Augmentation with Addnl. finalized as per joint visit
4 Lesliganj with JBVNL officials. Work not Started. B. Contour Survey was done.
5 Patan Not Required as intimated by JBVNL. Work not Started.
Palamu PKG-3
A. 1 no. Augmentation w/o Addnl. + 1 no. Augmentation with
Addnl. finalized as per joint visit with JBVNL officials. 6 Semra, (Chainpur) Work not Started. B. Contour Survey was done. C. Qty. of Main Equipment has been freezed. A. 1 no. Augmentation w/o Addnl. finalized as per joint visit with 7 Panki JBVNL officials. Work not Started. B. Qty. of Main Equipments has been freezed.
A. 1 no. Augmentation w/o Addnl. finalized as per joint visit with
8 Palamu PKG-4 Satbarwa JBVNL officials. Work not Started. B. Qty. of Main Equipments has been freezed.
A. 1 no. Augmentation with Addnl. Is finalized as per joint visit
9 Padma with JBVNL officials. Work not Started. B. Contour Survey was done.
Additional 1no. of 5MVA Power Transformer installation along
10 Chandwa with 1no. of 33kV bay extension, 1no. of 11kV bay extension & Work not Started. associated equipments.
Additional 1no. of 5MVA Power Transformer installation along
11 Barwadih with 1no. of 33kV bay extension, 1no. of 11kV bay extension & Work not Started. associated equipments. Latehar Additional 1no. of 5MVA Power Transformer installation along 12 Balumath with 1no. of 33kV bay extension, 1no. of 11kV bay extension & Work not Started. associated equipments.
Additional 2no. of 5MVA Power Transformer installation along
13 Manika with 2nos. of 33kV bay extension, 2nos. of 11kV bay extension & Work not Started. associated equipments. Additional 1no. of 5MVA Power Transformer installation along with 1no. of 33kV bay extension, 1no. of 11kV bay extension & associated equipments.
Replacement of following damaged items is required at existing
PSS: 14 Garhwa PKG-1 Bhawnathpur a) 1no of 33kV VCB Work not Started. b) 1no of 33kV PT c) 2nos of 33kV ISO d) 2nos of 11kV VCB e) 2nos of 11kV ISO f) 1no of 11kV PT g) 5nos. of C & R Panels
15 Garhwa PKG-2 NO AUGMENTATION WORK AS PER SCOPE & ACTUAL SURVEY.
In existing PSS, the augmentation work at Majhiaon PSS has
16 Garhwa PKG-3 Majhiaon been carried out by JBVNL departmentally. JBVNL shall identify Work not Started. alternate PSS to agency for carrying out augmentation work. Additional 1no. of 5MVA Power Transformer installation along with 1no. of 33kV bay extension, 1no. of 11kV bay extension & associated equipments.
Replacement of following damaged items is required at existing
PSS: 17 Garhwa PKG-4 Bhandaria a) ACDB Work not Started. b) DCDB c) Disc Insulator & Post Insulator d) 4nos. of 11kV VCB e) 1no. C & R Panel f) 1no of 11kV Bus coupler g) Painting of existing structures