Mega Asset Management Co., Ltd.

DEFECT LIST Canadia Tower, 10F, No.315, Ang Duong Street


(corner of Monivong Blvd), Phnom Penh, Cambodia

PROJECT NAME: Cambodia China Polytechnic University (CCPU)


LOCATION: Chroy Chongvar Satellite City, Phnom Penh, Cambodia
PREPARED BY: Chhem Sophea (Mr.)
PHONE / EMAIL: 010 384 758/ sophea.c88@gmail.com
REFERENCE NUMBER: CCPU-DFL-007
DATE: December 15, 2018
ATTENTION: KPCC
CC: Mega Asset Management Co., Ltd.

ID COMMENTS/ DESCRIPTION ACTION STATUS


A Concrete for bored pile PR6
1 Late to finish concreting before its setting time, no provided molds to new DIBP & Disapprove
proportion adjustment for strength test. KPBP
2 Bad effect of hydraulic piling vibrator on concrete in bored hole at its KPBP Disapprove
setting time

Please refer the ID in the table to the ID in Photo Report below:

Additional Comments (if any)

PR6 : Koh Pich Bored Pile (KPBP) contractor should pay high attention on concrete working, thus

the team should casting bored pile before the setting time of concrete.

KPBP/DIBP shall also have notified related parties about the adjustment of concrete slump &

chemical admixture adding.

Note: With these mentioned issues, KPCC should have taken action and dealt with the teams.

ID LOCATION ON DRAWING (RED ZONE) PHOTO DESCRIPTION ON SITE

Mega Asset Management Co.,Ltd.


Mega Asset Management Co., Ltd.
Canadia Tower, 10F, No.315, Ang Duong Street
(corner of Monivong Blvd), Phnom Penh, Cambodia

Casting concrete with CM-44, concrete mixer truck

Concrete delivery’s slip CM-44 as reference


 Element: Bored pile PR6
 Location: Ground floor ramp’s base

Mega Asset Management Co.,Ltd.


Mega Asset Management Co., Ltd.
Canadia Tower, 10F, No.315, Ang Duong Street
(corner of Monivong Blvd), Phnom Penh, Cambodia

 Issue: Continuing concreting at the setting time. Concrete has already reached initial setting time; bored pile
contractor has fully spent 5 hours to completely finish casting concrete which supplied by concrete mixer
truck CM-44; included with delivery concrete to site.
Slump : Concrete was adjusted slump and added chemical admixture to delay the setting time without notify
officially to related parties or without formal substances list submitted of the mixing. KPBP proposed for
slump adjusting.
Molds : DIBP did not provide additional molds to the new made up mixture for its strength testing.
Delivery duration : 1 hour and 30mn as average from Koh Pich batching plant to site
 Date: 15.December.2018
2

Bad ground mud poured out, fresh concrete


appered on the top of casing by 7:19

Removing temporary casing length 9.0m by 7:50

Mega Asset Management Co.,Ltd.


Mega Asset Management Co., Ltd.
Canadia Tower, 10F, No.315, Ang Duong Street
(corner of Monivong Blvd), Phnom Penh, Cambodia

Concrete delivery’s slip CM-44 as reference


 Element: Bored pile PR6
 Location: Ground floor ramp’s base
 Issue: Vibration effect on concrete at its setting time. Remove the temporary casing spent time more than
30mn due to the failure to operate hydraulic piling vibrator.
 Date: 15.December.2018

Mega Asset Management Co.,Ltd.