CP05-03-MMC-MST-ELE-0026 Testing & Commissioning For Structure Cabling System
CP05-03-MMC-MST-ELE-0026 Testing & Commissioning For Structure Cabling System
SN Description
CP05-03-MMC-MST-ELE-0026 REV.00 Testing & Commissioning for Structure Cabling System, has been
1
reviewed and is accepted for onward submission to the Engineer.
Page 1 of 1
DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-03-MMC-MST-EL-0026
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF SCS
Revision 00
Dubai, UAE SYSTEM
Issue Date 08-05-2023 Page 1 of 22
METHOD STATEMENT
FOR TESTING AND COMMISSIONING OF
STRUCTURED CABLING SYSTEM
CONTENTS
4) RESPONSIBILITIES
4.1 PROJECT MANAGER
4.2 COMMISSIONING ENGINEER
4.3 SUPERVISOR
4.4 TECHNICIAN
4.5 QA/QC ENGINEER
4.6 SAFETY ENGINEER
5) PROCEDURE / METHOD TO BE EMPLOYED
9) RISK ASSESSMENT
10) ATTACHMENTS
1.1 SCOPE
The scope of this method statement is to define the procedure to be adopted for
Testing and Commissioning of Structured Cabling System.
1.2 PURPOSE
The purpose of this documents is to ensure that quality control objectives are
maintained and accurate records are established for all related activities.
1.3 OBJECTIVE
The objective is to ensure that the testing and commissioning plan is executed,
controlled and documented strictly in compliance with the contract drawings and
specifications.
2.2 DEFINITIONS
• MAIN CONSULTANT means M/S LACASA Architects & Engineering Consultants.
• MAIN CONTRACTOR means Ali & Sons Contracting L.L.C.
• MEP SUB-CONTRACTOR means MENASCO Mechanical Contracting. LLC.
• SECURITY SUB-CONTRACTOR means JOHNSON CONTROLS
INTERNATIONAL.
Abbreviations:
SCS: Structured Cabling System
IR: Inspection Request.
WIR: Work Inspection Request
MIR: Material Inspection Request.
HSE: Health, Safety and Environment
TBT: Toolbox Talk
MSRA: Method Statement and Risk Assessment
PPE: Personal Protective Equipment
SWL: Safe Working Load
IDF: Intermediate Distribution Frame
SCR: Security Control Room
DM: Dubai Municipality
DAC: Dubai Accreditation Center
Contract specifications supersedes all material described in this document.
DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-03-MMC-MST-EL-0026
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF SCS
Revision 00
Dubai, UAE SYSTEM
Issue Date 08-05-2023 Page 4 of 22
DDA: Dubai Development Authority
PTW: Permit to Work
QA/QC: Quality Assurance/ Quality Control
All work will be undertaken in full accordance with safety procedures specified in the
contractor’s HSE Plan.
Prior to commencing any activity, the labor force shall receive a toolbox on the project
site as per safety regulation. Refer risk assessment section for further details.
The general safety guidelines are given below:
1. Ensure work area is safe & clean.
2. All employees shall adopt safe working practices.
3. Safety equipment (for example, hard hats, safety shoes, coveralls, gloves, goggles,
face mask as applicable) to be worn at all times.
4. When working at high Level, the appropriate safety harness shall be used and secured,
extra care shall be taken whilst using tools at high level to prevent dropping.
5. Ensure sufficient lighting is available during all stages of testing.
6. Report all accidents no matter how small to the safety officer on duty.
7. Ensure any electrical isolation permit is obtained if required.
4.0 RESPONSIBILITIES
4.3 Supervisor
4.4 Technician
• Reporting to commissioning engineer & supervisor.
• Familiar with the method statement and safety requirements.
• Responsible for daily activities on the site with regards to commissioning.
• Under direct supervision of supervisor.
• Ensure proper housekeeping is done.
5.1 Procedure
• Ensure that all work area is safe, clear and all constraints on operation
have been identified and precautions are taken.
• Arrange all necessary personnel, plants equipment and services as
required for the works and ensure adequate lighting, temporary power
where applicable and access arrangement are in place.
• Implement Employment induction procedure and Tool Box talks for the
ongoing risk assessment and identification of hazards
5.3 Testing & Commissioning Procedure
Optical Fibre Cable Testing (ISP & ICT Backbone Fiber Cable)
➢ OTDR Test
This test will acquire a trace of an installed fiber optic cable plant,
singlemode or multimode, including the loss of all fiber, splices and
connectors. Following equipment is needed to perform this test:
- OTDR appropriate for the fiber being tested (Multimode: 850
and/or 1300nm, singlemode, 1310, 1550 and/or 1625 nm)
- Launch and receive reference cables of the same fiber type
Contract specifications supersedes all material described in this document.
DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-03-MMC-MST-EL-0026
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF SCS
Revision 00
Dubai, UAE SYSTEM
Issue Date 08-05-2023 Page 10 of 22
➢ Wiremap
A wiremap test proves the correct continuity on all pairs and
determines if the individual conductors in the cabling are
connected correctly. In a balanced twisted-pair cable the test
should indicate:
➢ Continuity to the remote end
➢ Shorts between any two or more conductors
➢ Transposed pairs
➢ Reversed pairs
➢ Split pairs
➢ Shield continuity (only for shielded cable)
➢ Grounded conductor
➢ Resistance`
Resistance results show the DC loop resistance for each cable pair.
A pair’s resistance depends on the integrity of the contacts in the
connector, the length of the pair, and its wire gauge.
Resistance problems always affect other tests. For example, a
link that is too long has higher-than-normal resistance and will
fail the length test and high-resistance connections reflect signals
that cause the return loss test to fail.
Resistance is tested on coaxial cables and is measured between
the center conductor and shield of the coaxial cable. Resistance is
not required as an acceptance test on balanced twisted-pair
cabling.
Contract specifications supersedes all material described in this document.
DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-03-MMC-MST-EL-0026
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF SCS
Revision 00
Dubai, UAE SYSTEM
Issue Date 08-05-2023 Page 14 of 22
➢ Length
Maximum length for the Permanent Link is 90m (295ft), and
100m (328ft) for the Channel Link. The pair with the shortest
electrical delay is used for the maximum length calculation.
A time domain reflectometer (TDR) method is used to calculate the
length of a cable by measuring the time it takes a pulse to travel down
the cable and back (round trip delay). This time is twice the propagation
delay.
A 2 % to 5 % difference in measured length among cable pairs is normal because
of the following:
• Signals travel at slightly different speeds in each
cable pair, but the tester uses the same speed to
calculate the length of each Pair.
• The twist rate varies slightly among cable pairs. If
you untwisted and straightened all the pairs, they
would have slightly different lengths.
➢ Return Loss
Return loss is the difference between the power of a transmitted
signal and the power of the signals reflected back. Signal reflections
are caused by variations in the cable’s impedance.
Return Loss is a measurement of the power reflected from the
cabling (in dB). The ratio of the reflected voltage to the incident
voltage is used to determine Return Loss. Return Loss is measured
over a frequency range and used as an indication of the
impedance uniformity of the cabling. The larger the value of return loss
in dB, the better the performance.
High return loss means the cabling reflects very little of the
transmitted signal back to the source. High return loss is especially
important for high-speed systems, such as Gigabit Ethernet. The bi-
directional (full-duplex) transceivers used in these systems use
directional couplers to distinguish between incoming and outgoing
signals. The couplers may interpret strong reflected signals as
incoming data, resulting in data errors.
➢ Characteristic Impedance
Characteristic Impedance is the impedance a cable would have if
the cable were infinitely long. Proper network operation depends on
constant characteristic impedance throughout the system’s cables and
connectors. Abrupt changes in characteristic impedance called
anomalies will cause signal reflections that can cause network faults.
Impedance measurements require a cable at least 5m (16ft) long.
Contract specifications supersedes all material described in this document.
DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-03-MMC-MST-EL-0026
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF SCS
Revision 00
Dubai, UAE SYSTEM
Issue Date 08-05-2023 Page 16 of 22
Cables shorter than this length will always pass the impedance
test. Characteristic Impedance results show approximate
characteristic impedance of each cable pair. Characteristic
Impedance is not required as an acceptance test for balanced twisted-
pair cabling.
▪ Electrician’s Toolbox
▪ Calibrated Multi-tester
▪ Splicing machine
▪ Fluke machine
▪ OTDR
▪ Portable hand tools
▪ Allen key
▪ Hand gloves
▪ Plastic protection covers
▪ Dry Cloth
▪ Marker pen
▪ Scaffolding
▪ Wire stripper
▪ Screw drivers
• Legal and Technical Guidelines to followed at all times, including but not limited to:
• Dubai Municipality (DM) – Code of Construction Safety Practice.
• Dubai Development Authority HSE regulations
• Administrative Decision NO. (68) Of 2010 Issue Implementing By-Law of the
Roads and Transport Authority.
• Ministry of Labour and Social Affairs Federal Law No. 8 (1980).
• Ministry of Labour and Social Affairs Ministerial Order No. 32 (1982)
• Federal Law No. 8 Ministerial Order No. 32 (1982) Regarding Determination of
Ways and Means to Protect Employees Against Occupational Hazards
• Ministerial Order No. 37/2 (1982) Regarding the Requirements Standards of
Medical Care to be Provided by the Employer for his Employees
• Ministerial Decision No. 557 of 2008, for the Executive Order of the Federal Law
No.37 of 2006 Concerning Private Security Companies.
9.0 ATTACHMENTS
INSPECTION CHECKLIST
Pre-commissioning Check List for Structured Cabling System
Area/Location: Date:
Check service provider incoming cable entry duct, entry box, manholes ready
1 and completed
Check horizontal and vertical containment and conduits are completed as per
2 approved shop drawings
Check all cabinets such as ONU, IDF cabinet, Equipment’s and cabling are
3
done in MMR1 and MMR2
4 Check outlets and devices for any external damages.
Ensure that all the cabling work including copper cables, SMF, MMF cables
5
and fiber drop cables are completed.
6 Check the arrangement of components and wiring
Check equipment installation and cable termination as per the schematic and
7
schedule.
Labelling of cables and field devices as per the approved shop drawings and
8
labelling scheme.
All testing instruments are available in good working condition with valid
9
calibration certificate.
10 Availability of electrical power supply in ONU and IDF cabinets.
11 Proper & safe access shall be maintained
INSPECTION CHECKLIST
Testing and Commissioning Check List for Structured Cabling System
Area/Location: Date:
Check the material are free from defects, rust, and damages and are
1 appropriate for use.
6 All pairs of the UTP cables have been tested for continuity and position
Ensure safe clearance followed between data and power cables
7
Each terminated fiber link has been tested for continuity, position and loss.
8
All fiber connectors have been tested for continuity, position and loss
9
Ensure all cabinets and racks such as ONU, Mini ODF, IDFs, MDFs are
10
labelled and terminated neatly.
11 All the test results have been documented.
Comments(if any):
MMC/SUPPLIER CA ASC LACASA
Name
Designation
Signature/Date
MENASCO MECHANICAL CONTRACTING L.L.C.
( DIFC CP - 05 BUILDING LINK BRIDGE MAIN WORKS )
( RISK ASSESSMENT)
Date: 20-05-2023
Reference No CP05-03-MMC-MST-ELE-0026
Revision Rev 00
Main Activity: TESTING AND COMMISSIONING OF STRUCTURED CABLING SYSTEM
Location: DIFC CP - 05 BUILDING LINK BRIDGE MAIN WORKS
Severity
Likelihood 1 2 3 4 5
Certain 5 5 10 15 20 25
Very Likely 4 4 8 12 16 20
Likely 3 3 6 9 12 15
May Happen 2 2 4 6 8 10
Unlikely 1 1 2 3 4 5
Trivial Risk - No further improvements necessary provided control measures are maintained
Adequately Controlled Risk - Risk is tolerable when control measures identified are implemented
Moderately controlled Risk - Further risk reduction measures should be considered
Intolerable Risk - Seek specialist advice/ support
Aravi Ashok Designation Proj, HSE Manager Date: 20th May 2023 Signature:
Salman Abu Assali Designation Project Manager Date: 20th May 2023 Signature:
MENASCO MECHANICAL CONTRACTING L.L.C. Page 2 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
01 Access to work Unfamiliarity to the site Minor injury 3 2 6 The Ali & Sons Contracting Project HSE Plan 1 2 2 Compliance to
area Unauthorized parking Property / asset shall be strictly complied with by all M/s DM, COP- CHP
Unauthorized access to site or damage MENASCO personnel and sub-contractors 2- 2.1, 2.3
taken shortcut under our control. Y
warning alarm/ warning light All work shall be carried out in accordance to Manager
Slip, trip and fall all applicable UAE Laws and Regulations, DM
Obstructed the walkway /traffic Regulations and MMC Project HSE Senior Project
activity
All material shall be segregated accordingly to Driver & Helper
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
03 Preparation of test Obstruction of access in test Minor Injuries ASC Policies and Procedures shall be
instruments, location Property / assets followed by Menasco team prior to start of
Commissioning
Materials, Uncertified or damaged test damage the Activity.
Engineer
Manpower, for equipment meters MSRA to be communicated with the
Environmental
testing and Inexperience or inadequate 4 operatives by the foreman or supervisor. 4
Impact Project Manager
Commissioning of training of workers involved 3 2 6 Pre-Task briefing or TBT to be carried out 1 2 2
Structural Cabling Poor illumination by foreman or supervisor prior to start of
system Construction
Open or damaged cable of work communicating hazard and control
Manager
the test meter measures to its workers.
Poor housekeeping Menasco to comply with Local Authority
Senior Project
Untrained operatives. regulations and HSE requirements.
Engineer
Defect/ damage Ensure that all the pre-commissioning
tool/equipment. checks are carried out successfully and Y
Site Engineer
Lack / poor supervision commissioning of Structural Cabling
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
Used of temporary Electrocution Minor Injury The Ali & Sons Contracting Project HSE
05 power supply and Slip / Trip and falls Major Injury Plan shall be strictly complied with by all
Extension leads. Untrained operative. Property All works shall be regularly monitored and
Use of damage extension damaged supervised by M/s MENASCO site team to Project Manager
leads. ensure full compliance
Use of damaged MENASCO shall provide adequate Construction
equipment's resources, as appropriate to ensure safe Manager
Lack of PPE. execution of work scope.
Work In wet areas with All work shall be carried out in accordance Senior Project
damaged cable lead or to all applicable UAE Laws and Engineer
equipment Regulations, DM Regulations and MMC
Project HSE Management System. Obtain Site Engineer
3 3 9 the required work permit and clearance
1 3 3 Y
prior to start the task HSE Officer
SOS / MSRA should communicate to
workers prior to commencement of work. Supervisors
Pre-Task briefing or TBT to be carried out
by foreman or supervisor prior to start of Foreman
work communicating hazard and control
measures to its workers Operators
Only competent person can carried out the
electrical task at site T & C Engrs
Inspected and color-coded extension
leads to be used on site.
All electrical tools and equipment's free
from defects and fit to safe use
MENASCO MECHANICAL CONTRACTING L.L.C. Page 11 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
person.
Do not use any damage power tool and worn HSE Officer
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
.
MENASCO MECHANICAL CONTRACTING L.L.C. Page 14 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
Board (EDB).
insulated.
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
Work at Height - Falling of men and materials from Major Injuries The Ali & Sons Contracting Project HSE Plan
08 Using Scaffold, A- shall be strictly complied with by all DM – Compliance
height Minor Injury CHAPTER 8
Type ladder / All works shall be regularly monitored and
Scaffolding
Presence of overhead services Fatality
Podium Ladders supervised by M/s MENASCO site team Safety
Incompetent workers Property damaged to ensure full compliance 101CHAPTER
MENASCO shall provide adequate resources, 4Personal
Lack of supervision
Protective
as appropriate to ensure safe execution of work
Improper use of work platform Equipment
scope. All work shall be carried out in
44Project
Unauthorized access to the accordance to all applicable UAE Laws and Manager
Regulations, DM Regulations and MMC Project
equipment
HSE Management System. Construction
Untrained operator Manager
MSRA to be communicated with the operatives
Unfavourableclimatic conditions 3 3 9 by the foreman or supervisor.
1 3 3 Y
Permit For work at height on scaffolding to be Senior Project
Unbalancing of work platform
available and approved from concerned team prior Engineer
Caught-in between
to start of work. Pre-Task briefing or TBT to be
Working under direct sun light carried out by foreman or supervisor prior to start Site Engineer
platform.
Foreman
Operative Working at height must be trained for
Safe Work at height.
T & C Engrs
MENASCO MECHANICAL CONTRACTING L.L.C. Page 16 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
Activity.
T & C Engrs
Menasco to comply with Local Authority
ERT
regulations and HSE requirements
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
Lack of training to Emergency case Operatives must be trained of safe and proper
responder Fines use of hand tools. Project Manager
Incompetent emergency Property damage All tools provided must be assessed to ensure
that they are fit for purpose, they fit for the Construction
responders Lack of training to Manager
Improper or lack of illumination Emergency responder environment in which they are to be used and they
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
Proper ventilation to be provided
Proper and safe access to be provided in work
areas.
Ali & Sons HSE Policies and Procedures shall be
followed by Menasco team prior to start of the
Activity.
Menasco to comply with Local Authority
regulations and HSE requirements
Note: If any new scenarios emerge that are not covered by this risk assessment, site management should be contacted immediately, and the task should not be completed until a specific risk
assessment has been completed, issued, and understood.