You are on page 1of 47

Document Review

Project DIFC CP-05 Office Building Main Works Package


Doc Ref. CP05-03-MMC-MST-ELE-0026 REV.00
Desc. Testing & Commissioning for Structure Cabling System
Review Ref. PT-CP05-TCMS-16 | 00 | 23.05.23

SN Description

CP05-03-MMC-MST-ELE-0026 REV.00 Testing & Commissioning for Structure Cabling System, has been
1
reviewed and is accepted for onward submission to the Engineer.

For Prime Technologies LLC

Page 1 of 1
DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-03-MMC-MST-EL-0026
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF SCS
Revision 00
Dubai, UAE SYSTEM
Issue Date 08-05-2023 Page 1 of 22

METHOD STATEMENT
FOR TESTING AND COMMISSIONING OF
STRUCTURED CABLING SYSTEM

Contract specifications supersedes all material described in this document.


DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-03-MMC-MST-EL-0026
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF SCS
Revision 00
Dubai, UAE SYSTEM
Issue Date 08-05-2023 Page 2 of 22

CONTENTS

1) SCOPE, PURPOSE & OBJECTIVE

2) REFERENCES & DEFINITIONS

3) HEALTH & SAFETY HAZARDS

4) RESPONSIBILITIES
4.1 PROJECT MANAGER
4.2 COMMISSIONING ENGINEER
4.3 SUPERVISOR
4.4 TECHNICIAN
4.5 QA/QC ENGINEER
4.6 SAFETY ENGINEER
5) PROCEDURE / METHOD TO BE EMPLOYED

6) MANPOWER, EQUIPMENT & MATERIAL REQUIREMENTS

7) HEALTH & SAFETY PROVISIONS

8) Q.C. APPROVAL AND OTHER DOCUMENTARY REQUIREMENTS

9) RISK ASSESSMENT

10) ATTACHMENTS

▪ CHECKLIST FOR TESTING AND COMMISSIONING


▪ RISK ASSESSMENT

Contract specifications supersedes all material described in this document.


DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-03-MMC-MST-EL-0026
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF SCS
Revision 00
Dubai, UAE SYSTEM
Issue Date 08-05-2023 Page 3 of 22

1.0 SCOPE, PURPOSE & OBJECTIVE

1.1 SCOPE
The scope of this method statement is to define the procedure to be adopted for
Testing and Commissioning of Structured Cabling System.
1.2 PURPOSE
The purpose of this documents is to ensure that quality control objectives are
maintained and accurate records are established for all related activities.
1.3 OBJECTIVE
The objective is to ensure that the testing and commissioning plan is executed,
controlled and documented strictly in compliance with the contract drawings and
specifications.

2.0 REFERENCES & DEFINITIONS


2.1 REFERENCES
• Contract Specifications
• Program of Works.
• Approved Shop-drawings.
• Approved Material Submittal.
• Local Authority’s Rules and Regulations.

2.2 DEFINITIONS
• MAIN CONSULTANT means M/S LACASA Architects & Engineering Consultants.
• MAIN CONTRACTOR means Ali & Sons Contracting L.L.C.
• MEP SUB-CONTRACTOR means MENASCO Mechanical Contracting. LLC.
• SECURITY SUB-CONTRACTOR means JOHNSON CONTROLS
INTERNATIONAL.

Abbreviations:
SCS: Structured Cabling System
IR: Inspection Request.
WIR: Work Inspection Request
MIR: Material Inspection Request.
HSE: Health, Safety and Environment
TBT: Toolbox Talk
MSRA: Method Statement and Risk Assessment
PPE: Personal Protective Equipment
SWL: Safe Working Load
IDF: Intermediate Distribution Frame
SCR: Security Control Room
DM: Dubai Municipality
DAC: Dubai Accreditation Center
Contract specifications supersedes all material described in this document.
DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-03-MMC-MST-EL-0026
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF SCS
Revision 00
Dubai, UAE SYSTEM
Issue Date 08-05-2023 Page 4 of 22
DDA: Dubai Development Authority
PTW: Permit to Work
QA/QC: Quality Assurance/ Quality Control

3.0 HEALTH AND SAFETY HAZARDS

All work will be undertaken in full accordance with safety procedures specified in the
contractor’s HSE Plan.
Prior to commencing any activity, the labor force shall receive a toolbox on the project
site as per safety regulation. Refer risk assessment section for further details.
The general safety guidelines are given below:
1. Ensure work area is safe & clean.
2. All employees shall adopt safe working practices.
3. Safety equipment (for example, hard hats, safety shoes, coveralls, gloves, goggles,
face mask as applicable) to be worn at all times.
4. When working at high Level, the appropriate safety harness shall be used and secured,
extra care shall be taken whilst using tools at high level to prevent dropping.
5. Ensure sufficient lighting is available during all stages of testing.
6. Report all accidents no matter how small to the safety officer on duty.
7. Ensure any electrical isolation permit is obtained if required.

4.0 RESPONSIBILITIES

4.1 Project Manager


• Project manager shall be responsible for overall project execution.
• Project manager will be responsible for overall timely completion of project in
accordance to all contractual requirements.
• Project manager shall coordinate with main contractor, MEP sub-contractor and
shall be responsible for progress monitoring, attending review meeting and
resource management.
• Ensure the Health and Safety of the personnel on the site.
• Co-ordinate with engineers and supervisors for execution of the contract scope of
Works.

4.2 Commissioning Engineer


Commissioning engineer coordinates all site activities required for testing and
commissioning as per specification, manufacture datasheet and approved drawing.

Contract specifications supersedes all material described in this document.


DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-03-MMC-MST-EL-0026
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF SCS
Revision 00
Dubai, UAE SYSTEM
Issue Date 08-05-2023 Page 5 of 22
He should ensure to:
• Responsible for the day-to-day activities on site, for commissioning and allocation
of departmental resources to work areas on site. Coordinate and explain the work
to be carried out to the supervisors.
• Coordination with the safety engineer to ensure that the works are carried out in a
safe working atmosphere.
• Coordination with the QC engineer for tests to be carried out and initiate IR for the
inspection for the finished works.
• Preparing daily progress report/ site report and supervising every individual
activity.
• Ensure to apply the related method statement for each job.

4.3 Supervisor

He should ensure that:


• Carrying-out the work and the proper distribution of all the available resources in
coordination with the Commissioning engineer on a daily basis.
• Toolbox talks to be given to work force regarding method statement and risk
assessment.
• Ensures the target dates set from time to time are met.
• Ensuring that the method statements and risk / impact assessments are followed
on site. Responsible for the Health and Safety aspects as per site HSE Plan.
• Daily reports of the works are achieved and coordinated for the future planning
with the commissioning Engineer.
• Incorporate all the QC and Safety requirements as requested by the concerned
engineer.
• Upon meeting with any type of unforeseen incident or requirement report to the
concerned engineer immediately.
• Ensure proper housekeeping is done.

4.4 Technician
• Reporting to commissioning engineer & supervisor.
• Familiar with the method statement and safety requirements.
• Responsible for daily activities on the site with regards to commissioning.
• Under direct supervision of supervisor.
• Ensure proper housekeeping is done.

Contract specifications supersedes all material described in this document.


DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-03-MMC-MST-EL-0026
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF SCS
Revision 00
Dubai, UAE SYSTEM
Issue Date 08-05-2023 Page 6 of 22

4.5 QA/QC Engineer


The QA/QC engineer will coordinate with the Commissioning Agent and MEP
subcontractors QA/QC engineer for raising inspections of completed commissioning
works.
He should ensure that:
• Ensure commissioning works are completed as per contract documents and
approved drawings.
• Submit inspection of completed works and requesting for the consultant’s
approval.
• Coordinate with consultant and Commissioning agent to carry out inspection of the
completed works.

4.6 Safety Engineer


The commissioning engineer, Supervisor and Technician will coordinate with MEP
subcontractors Safety Engineer to ensure all works are carries out as per MSRA and
site HSE plan.
He should ensure to:
• The implementation of all safety measures in accordance with the HSE plan.
• Ensure that all necessary permits shall be obtained from consultant.
• Ensure that good housekeeping is implemented at work site, to maintained site in
a clean and tidy manner.
• Ensure that all necessary personnel protective equipment will be provided as per
the requirement of the job. whether each worker is using necessary PPE.
• Inspection of all the site activities and training personnel in accident prevention and
its proper reporting to the Project Manager and the Consultant.

5.0 PROCEDURE/ METHOD TO BE EMPLOYED

5.1 Procedure

1. Planning, safety precaution, site access and permit to be taken as applicable.


2. Pre task briefing and Pre job inspection check by immediate supervisor.
3. Mandatory PPE shall be equipped.
4. Manual lifting only allowed up to (20 to 25 kg) or use of pallet trolley for material
shifting.
5. Platforms checked for stability.
6. Complete supervision.
Contract specifications supersedes all material described in this document.
DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-03-MMC-MST-EL-0026
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF SCS
Revision 00
Dubai, UAE SYSTEM
Issue Date 08-05-2023 Page 7 of 22
7. Safe access to work areas will be ensured.
8. Equipment & Material shall be moved to the work area in a safe manner and shall
not block access / egress from the site.
9. Ensure that the working platforms are inspected.
10. If any electrical tool to be used, prior inspection of the tool by HSE to be done and
approved for the task.
11. Proper illumination of area to be ensured.
12. Buddy working system is to be followed, where a person is always working with a
partner.
13. Proper ventilation of the area to be ensured.
14. Personnel involved are made aware of all emergency exits and assembly points.
15. Drinking water facilities provided for all personnel involved.
16. Cold water and electrolyte hydration drinks provided during summertime.
17. Mid-day break followed as per law.
18. Inspect the relevant area for any possible clashes with other services.
19. Activity shall be carried out trained, competent, authorized person under
experienced supervision.
20. Once the activity is completed, coordinate with QA/QC to raise inspection requests
for consultant inspection.

5.2 Pre-Commissioning Check


The following pre-checks to be done prior to commencing testing and commissioning
procedure:
• Method statement and risk assessment should be briefed to all operative prior to
work activities.
• Every work area is barricaded and caution sign to be displayed.
• All measuring instruments are calibrated.
• A visual inspection will be carried out prior to testing and commissioning in order
that danger cannot arise when the test is in place. The following are the minimum
checks prior to commissioning:
• The Ensure all termination and splicing is completed.
• Ensure proper cable, patch panel and outlet labelling according to approved labelling
scheme.
• Ensure power availability in ICT IDF cabinets and MDF cabinet.
• Ensure power outlets and isolators are installed; earthing is provided
and properly connected to cabinet or racks.
• Ensure all electronic testing tools are calibrated.
• Ensure the coordination function with other services/ systems
(where applicable) takes place and all relevant personnel are aware
Contract specifications supersedes all material described in this document.
DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-03-MMC-MST-EL-0026
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF SCS
Revision 00
Dubai, UAE SYSTEM
Issue Date 08-05-2023 Page 8 of 22
of requirements prior to comment of works.

• Ensure that all work area is safe, clear and all constraints on operation
have been identified and precautions are taken.
• Arrange all necessary personnel, plants equipment and services as
required for the works and ensure adequate lighting, temporary power
where applicable and access arrangement are in place.
• Implement Employment induction procedure and Tool Box talks for the
ongoing risk assessment and identification of hazards
5.3 Testing & Commissioning Procedure

a. Test for Main Telecom Room (MTR)


i. Check labelling on the distributor and cabinets installed in MTR room.
ii. Check location according to the MTR Room drawing and no. of
cabinets and installation confirming to specifications and DIFC
guidelines.
iii. Check arrangement of patch panels, cable manager, labelling on
patch panels and free space in cabinets

iv. Check arrangement of cabinets.


v. Check installation of patch panels.
vi. Test the terminated fibre backbone cables and record the test results.

b. Test for Optical Network Unit (ONU)


i. Check Labelling on the cabinets installed inside the telephone room.
ii. Check location according to the drawings and no. of
cabinets and installation confirming to specifications.
iii. Check arrangement of patch panels, cable manager, labelling on
patch panels and free space in cabinets.
iv. Check arrangement inside the cabinet.
v. Check installation of patch panels.
vi. Test fiber backbone cables and record the test results.
vii. Test cat6A UTP cables and record the test results.

Contract specifications supersedes all material described in this document.


DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-03-MMC-MST-EL-0026
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF SCS
Revision 00
Dubai, UAE SYSTEM
Issue Date 08-05-2023 Page 9 of 22

c. Test for Main ICT Rack


i. Check labelling on the distributor and cabinets installed in MTR.
ii. Check location according to the drawing and no. of
cabinets and installation confirming to specifications.

iii. Check arrangement of patch panels, cable manager, labelling on


patch panels and free space in cabinets.
iv. Check arrangement of cabinets.
v. Check installation of patch panels.
vi. Test fiber backbone cable and record the test results.

d. Test for ICT IDF Cabinet


i. Check labelling on the distributor and cabinets installed in main ICT room.
ii. Check location according to the drawing and no. of
cabinets and installation confirming to specifications.
iii. Check arrangement of patch panels, cable manager, labelling on
patch panels and free space in cabinets.
iv. Check arrangement inside the cabinet.
v. Check installation of patch panels.
vi. Test fibre backbone fiber and record the test results.
vii. Test cat6A UTP cables and record the test results.

Optical Fibre Cable Testing (ISP & ICT Backbone Fiber Cable)
➢ OTDR Test
This test will acquire a trace of an installed fiber optic cable plant,
singlemode or multimode, including the loss of all fiber, splices and
connectors. Following equipment is needed to perform this test:
- OTDR appropriate for the fiber being tested (Multimode: 850
and/or 1300nm, singlemode, 1310, 1550 and/or 1625 nm)
- Launch and receive reference cables of the same fiber type
Contract specifications supersedes all material described in this document.
DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-03-MMC-MST-EL-0026
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF SCS
Revision 00
Dubai, UAE SYSTEM
Issue Date 08-05-2023 Page 10 of 22

and size as the cable plant and with connectors compatible to


those on the cable plant.
- Mating adapters compatible to connectors.

Test procedure as follows:


- Turn on OTDR and allow time to warm-up
- Clean all connectors and mating adapters.
- Attach launch cable to OTDR. Attach receive cable (if used) to far end of
cable.
- Set up test parameters on OTDR.
- Attach cable to test to end of launch cable. Attach receive cable (if used) to far
end of cable.
- Acquire trace and analyse.
- Generate and record the test report.

Contract specifications supersedes all material described in this document.


DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-03-MMC-MST-EL-0026
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF SCS
Revision 00
Dubai, UAE SYSTEM
Issue Date 08-05-2023 Page 11 of 22

➢ Splicing and Termination of cables


Splicing of all Optical fiber cables shall be carried out by means
of a calibrated fusion splicing machine and optical fiber cleaver.
The theoretical Splice loss reading which is displayed on the
fusion splicing machine shall be kept to maximum of 0.05 dB to
reduce the number of re splicing. All data corresponding to the
theoretical Splice Loss shall record on the Theoretical Splice Loss
Test form Sheet.
The actual splice loss of each individual splice is equal to or less
than the stated splice loss in the contractual specifications.

➢ Splice Loss and Continuity


i. Actual Splice Loss
Once all cables have been spliced, each individual splice loss shall
be measured in both directions at the wavelength of 1550nm for
Single Mode and 850nm for Multi-Mode the average of both
results shall be taken to produce the 'Actual Splice Loss'. If
this loss is greater that the contractual stated splice loss on any
two fibers spliced, and then the splice shall be re-made. A
maximum of three (3) attempts to re-splice a particular high
fiber shall be made to bring the actual splice loss within the
contractual specifications.
ii. Continuity
Once all individual splice losses fall within the contractual
specifications continuity of each individual fiber shall be tested by
means of an optical fiber talk set to ensure continuity between two
regions or repeater sites.

Contract specifications supersedes all material described in this document.


DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-03-MMC-MST-EL-0026
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF SCS
Revision 00
Dubai, UAE SYSTEM
Issue Date 08-05-2023 Page 12 of 22

➢ End to end test


Once the splice loss and continuity tests have been carried out the
End to End power meter test shall be taken to determine the loss
of an individual section of cable which has been completely
spliced, terminated and cleared of any faults.
The test shall be taken using an optical fiber light source and Power
meter from one point of termination to another.

Cat6 Cable Testing

➢ Channel link test


In a network, the channel is the connection from one active
device to another, and it includes any patch cords and
equipment cords. In the LAN, this would include any cable
between the switch in the telecom room and the end device,
including any patch cords from the switch to a patch panel and any
equipment cords from the outlet to end device.
The main and remote testing units have adapters with RJ45

ports. These adapters connect to the cabling with standard


patch cords. The test is, therefore, covering the complete
channel.
Cord + Patch Panel + Cable + Outlet + Cord:

Contract specifications supersedes all material described in this document.


DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-03-MMC-MST-EL-0026
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF SCS
Revision 00
Dubai, UAE SYSTEM
Issue Date 08-05-2023 Page 13 of 22

This test has the advantage of covering the complete cabling


between a switch and a connected device, therefore ensuring
that the application can function properly. However, the test is
only valid as long as the patch cords remain in place. If one
cord is replaced, then the test is no longer valid.

➢ Wiremap
A wiremap test proves the correct continuity on all pairs and
determines if the individual conductors in the cabling are
connected correctly. In a balanced twisted-pair cable the test
should indicate:
➢ Continuity to the remote end
➢ Shorts between any two or more conductors
➢ Transposed pairs
➢ Reversed pairs
➢ Split pairs
➢ Shield continuity (only for shielded cable)
➢ Grounded conductor

➢ Resistance`
Resistance results show the DC loop resistance for each cable pair.
A pair’s resistance depends on the integrity of the contacts in the
connector, the length of the pair, and its wire gauge.
Resistance problems always affect other tests. For example, a
link that is too long has higher-than-normal resistance and will
fail the length test and high-resistance connections reflect signals
that cause the return loss test to fail.
Resistance is tested on coaxial cables and is measured between
the center conductor and shield of the coaxial cable. Resistance is
not required as an acceptance test on balanced twisted-pair
cabling.
Contract specifications supersedes all material described in this document.
DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-03-MMC-MST-EL-0026
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF SCS
Revision 00
Dubai, UAE SYSTEM
Issue Date 08-05-2023 Page 14 of 22

➢ Length
Maximum length for the Permanent Link is 90m (295ft), and
100m (328ft) for the Channel Link. The pair with the shortest
electrical delay is used for the maximum length calculation.
A time domain reflectometer (TDR) method is used to calculate the
length of a cable by measuring the time it takes a pulse to travel down
the cable and back (round trip delay). This time is twice the propagation
delay.
A 2 % to 5 % difference in measured length among cable pairs is normal because
of the following:
• Signals travel at slightly different speeds in each
cable pair, but the tester uses the same speed to
calculate the length of each Pair.
• The twist rate varies slightly among cable pairs. If
you untwisted and straightened all the pairs, they
would have slightly different lengths.

➢ Propagation Delay & Delay Skew


Propagation Delay is the time taken for a test pulse to travel the
length of a cable pair. The delay is measured in nanoseconds.
Propagation delays vary slightly among pairs because of small
differences in electrical characteristics and length.
Delay skews are the differences in propagation delays between the
shortest delay and the delays of the other delay skew results.
➢ Insertion Loss (Attenuation)
Insertion Loss is also known as Attenuation. Insertion loss is the
loss of signal strength over cabling caused by the resistance of the
copper wire and connecting hardware and by leakage of electrical
energy through the cable’s insulation.
At higher frequencies, signals tend to travel only near the surface of
a conductor. This “skin effect”, along with the cabling’s inductance
and capacitance, cause insertion loss to increase
Contract specifications supersedes all material described in this document.
DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-03-MMC-MST-EL-0026
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF SCS
Revision 00
Dubai, UAE SYSTEM
Issue Date 08-05-2023 Page 15 of 22

should be greater than 3 dB at any given frequency for measurement


accuracy. The smaller the loss in decibel (dB), the better the performance.
Insertion Loss deviation is a measure of the worst-case difference in
magnitude between the expected insertion loss and the actual measured
insertion loss. Insertion Loss is not required as an acceptance test for a balanced
twisted pair cabling.

➢ Return Loss
Return loss is the difference between the power of a transmitted
signal and the power of the signals reflected back. Signal reflections
are caused by variations in the cable’s impedance.
Return Loss is a measurement of the power reflected from the
cabling (in dB). The ratio of the reflected voltage to the incident
voltage is used to determine Return Loss. Return Loss is measured
over a frequency range and used as an indication of the
impedance uniformity of the cabling. The larger the value of return loss
in dB, the better the performance.
High return loss means the cabling reflects very little of the
transmitted signal back to the source. High return loss is especially
important for high-speed systems, such as Gigabit Ethernet. The bi-
directional (full-duplex) transceivers used in these systems use
directional couplers to distinguish between incoming and outgoing
signals. The couplers may interpret strong reflected signals as
incoming data, resulting in data errors.

➢ Characteristic Impedance
Characteristic Impedance is the impedance a cable would have if
the cable were infinitely long. Proper network operation depends on
constant characteristic impedance throughout the system’s cables and
connectors. Abrupt changes in characteristic impedance called
anomalies will cause signal reflections that can cause network faults.
Impedance measurements require a cable at least 5m (16ft) long.
Contract specifications supersedes all material described in this document.
DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-03-MMC-MST-EL-0026
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF SCS
Revision 00
Dubai, UAE SYSTEM
Issue Date 08-05-2023 Page 16 of 22
Cables shorter than this length will always pass the impedance
test. Characteristic Impedance results show approximate
characteristic impedance of each cable pair. Characteristic
Impedance is not required as an acceptance test for balanced twisted-
pair cabling.

6.0 MANPOWER, EQUIPMENT & MATERIAL REQUIREMENTS

6.1 Manpower Requirements


• Senior Electrical Engineer.
• Electrical Site engineer
• Electrical Foreman (Supervisor)
• Technicians
• Labours

6.2 Material and Equipment Requirements

▪ Electrician’s Toolbox
▪ Calibrated Multi-tester
▪ Splicing machine
▪ Fluke machine
▪ OTDR
▪ Portable hand tools
▪ Allen key
▪ Hand gloves
▪ Plastic protection covers
▪ Dry Cloth
▪ Marker pen
▪ Scaffolding
▪ Wire stripper
▪ Screw drivers

Contract specifications supersedes all material described in this document.


DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-03-MMC-MST-EL-0026
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF SCS
Revision 00
Dubai, UAE SYSTEM
Issue Date 08-05-2023 Page 17 of 22

6 HEALTH AND SAFETY PROVISIONS


HSE PLANS
• The Ali & Sons Contracting Project HSE Plan shall be strictly complied with by all
M/s MENASCO personnel and sub-contractors under our control.
• All works shall be regularly monitored and supervised by M/s MENASCO site team
to ensure full compliance.
• M/s MENASCO shall provide adequate resources, as appropriate to ensure safe
execution of work scope.
• All work shall be carried out in accordance to all applicable UAE Laws and
Regulations, DM Regulations, Requirements and ASC Project HSE Management
System.
• All new starters shall first receive ASC site HSE induction before entering site.
• M/s MENASCO Site Engineer / Site Supervisors shall check and ensure all safety
precautions are taken prior to commencement of work. Also, they shall ensure
method statement and risk assessment has been communicated and a pre-task
safety briefing is conducted to personnel involved in the task on a daily basis.
• Where required, Permit to work will be provided prior to commencement of works.
Permits shall be issued by suitably trained and experienced ASC HSE personnel
only. Permit to work must be obtained from ASC HSE department before starting
the work, e.g. Excavation Permit, Hot work, Confined Space Entry, Energization /
De-energization (LOTO), etc.
• Personal Protective Equipment - Task specific PPE must be worn at all times
during the work, including hard hat, gloves, safety glasses, safety shoes, adequate
respiratory mask and coveralls.
• All required PPE shall be issued to workers; maintained and replaced, if damaged /
defective. Constant monitoring and supervision of the works shall ensure that at all
times the appropriate PPE is worn by affected operatives.
• Access and Egress - Safe access / egress shall be provided for materials and
operatives at all times. Where emergency routes are required, these shall be
determined, arranged, and instructions given prior to commencement of the
work. If working on scaffolding platforms greater than 1.8m high, personnel must
ensure it is green tagged ‘safe for use’ and also don a full body harness and
observe 100% tie off procedures.
• Materials and Waste Management - Material safety data sheet must be made
available if any substances are used for works to be carried out. Any waste
materials, containers, etc. disposed of properly in the designated skips / waste
points.
Contract specifications supersedes all material described in this document.
DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-03-MMC-MST-EL-0026
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF SCS
Revision 00
Dubai, UAE SYSTEM
Issue Date 08-05-2023 Page 18 of 22
• M/s MENASCO supervision shall ensure that all material deliveries are
coordinated and all vehicles are parked in a position where they present no
• additional risk to the general public or people associated with this project. Where
vehicles are offloaded from public areas, the activity shall be supervised and a
dedicated offloading / storage area shall be provided.
• Plant Equipment - All plant equipment associated with this activity shall be
inspected prior to the works commencing and at regular periods during the works
to ensure that all required certification is current and that the plant equipment is
maintained in a safe and suitably working manner.
• Lighting - At all times, appropriate and suitable lighting shall be provided to ensure
the works can be undertaken in a safe and competent manner.
• Housekeeping - At all times, M/s MENASCO supervision shall monitor the work
area, so as to reduce, as far as reasonably practical the storage of rubbish, waste
materials and debris in the workplace. All waste materials generated during the
curse of the shift / day shall be removed from the workplace to a suitable waste
segregation area.
• Working at height - When required, and working above 1.8m and a potential fall
could arise all appropriate measures shall be enforced to ensure that operatives
are afforded a safe and proper temporary working platform. Materials will be
stacked in a safe and secure manner. Scaffolds shall be erected by competent
operatives to an agreed design. Scaffolds shall be inspected before use and at
regular periods thereafter (every 7 days).
• All lifting activities using lifting equipment and accessories must only be carried out
by third party trained personnel, such as crane operator and rigger
(slinger/signaler). Lifting Plan and Procedure shall be developed, for both common
and critical lifting activities and in place before any work shall commence.
• Any injury / illness sustained whilst at work must be reported immediately and
treated by a trained first aider or HSE Officer. Incident escalation reporting
procedure shall be followed at all times.
• HSE violation in any HSE procedures whether project or legal requirement will
result in black points being issued, as per Subcontractor Agreement and personnel
removed from site, if necessary.
• COVID-19 precautionary measures shall be communicated to the workforce and
all personnel under our control, including but not limited to social distancing,
wearing of face masks, regular hand washing and disinfecting of work areas,
reporting outbreaks or positive cases, as per ASC Emergency Escalation
procedure, etc.
HSE applicable laws and regulations
• Legal and Technical Guidelines to followed at all times, including but not
limited to:
Contract specifications supersedes all material described in this document.
DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-03-MMC-MST-EL-0026
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF SCS
Revision 00
Dubai, UAE SYSTEM
Issue Date 08-05-2023 Page 19 of 22
• Dubai Municipality (DM) – Code of Construction Safety Practice.
• Dubai Development Authority HSE regulations
• Administrative Decision NO. (68) Of 2010 Issue Implementing By-Law of the
Roads and Transport Authority.
• Ministry of Labour and Social Affairs Federal Law No. 8 (1980).
• Ministry of Labour and Social Affairs Ministerial Order No. 32 (1982)
• Federal Law No. 8 Ministerial Order No. 32 (1982) Regarding Determination
of Ways and Means to Protect Employees Against Occupational Hazards
• Ministerial Order No. 37/2 (1982) Regarding the Requirements Standards of
Medical Care to be Provided by the Employer for his Employees
• Ministerial Decision No. 557 of 2008, for the Executive Order of the Federal
Law No.37 of 2006 Concerning Private Security Companies.

HEALTH AND SAFETY PROVISIONS

7.1 HSE PLANS


• The Ali & Sons Contracting Project HSE Plan shall be strictly complied with by
Johnson Controls International under M/s MENASCO personnel.
• All works shall be regularly monitored by M/s MENASCO site team to ensure full
compliance.
• M/s MENASCO shall provide adequate resources, as appropriate to ensure safe
execution of work scope.
• All work shall be carried out in accordance to all applicable UAE Laws and
Regulations, DM Regulations, Requirements and ASC Project HSE Management
System.
• All new starters shall first receive ASC site HSE induction before entering site.
• M/s MENASCO Site Engineer / Site Supervisors shall check and ensure all safety
precautions are taken prior to commencement of work. Also, they shall ensure
method statement and risk assessment has been communicated and a pre-task
safety briefing is conducted to personnel involved in the task on a daily basis.
• Where required, Permit to work will be provided prior to commencement of works.
Permits shall be issued by suitably trained and experienced ASC HSE personnel
only. Permit to work must be obtained from ASC HSE department before starting
the work, e.g. Excavation Permit, Hot work, Confined Space Entry, Energization /
De-energization (LOTO), etc.
• Personal Protective Equipment - Task specific PPE must be worn at all times
during the work, including hard hat, gloves, safety glasses, safety shoes, adequate
respiratory mask and coveralls.

Contract specifications supersedes all material described in this document.


DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-03-MMC-MST-EL-0026
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF SCS
Revision 00
Dubai, UAE SYSTEM
Issue Date 08-05-2023 Page 20 of 22
• All required PPE shall be issued to workers; maintained and replaced, if damaged /
defective. Constant monitoring and supervision of the works shall ensure that at all
times the appropriate PPE is worn by affected operatives.
• Access and Egress - Safe access / egress shall be provided for materials and
operatives at all times. Where emergency routes are required, these shall be
determined, arranged, and instructions given prior to commencement of the
work. If working on scaffolding platforms greater than 1.8m high, personnel must
ensure it is green tagged ‘safe for use’ and also don a full body harness and
observe 100% tie off procedures.
• Materials and Waste Management - Material safety data sheet must be made
available if any substances are used for works to be carried out. Any waste
materials, containers, etc. disposed of properly in the designated skips / waste
points.
• Additional risk to the general public or people associated with this project, Where
vehicles are offloaded from public areas, the activity shall be supervised and a
dedicated offloading / storage area shall be provided.
• Plant Equipment - All plant equipment associated with this activity shall be
inspected prior to the works commencing and at regular periods during the works
to ensure that all required certification is current and that the plant equipment is
maintained in a safe and suitably working manner.
• Lighting - At all times, appropriate and suitable lighting shall be provided to ensure
the works can be undertaken in a safe and competent manner.
• Housekeeping - At all times, M/s MENASCO supervision shall monitor the work
area, so as to reduce, as far as reasonably practical the storage of rubbish, waste
materials and debris in the workplace. All waste materials generated during the
curse of the shift / day shall be removed from the workplace to a suitable waste
segregation area.
• Working at height - When required, and working above 1.8m and a potential fall
could arise all appropriate measures shall be enforced to ensure that operatives
are afforded a safe and proper temporary working platform. Materials will be
stacked in a safe and secure manner. Scaffolds shall be erected by competent
operatives to an agreed design. Scaffolds shall be inspected before use and at
regular periods thereafter (every 7 days).
• All lifting activities using lifting equipment and accessories must only be carried out
by third party trained personnel, such as crane operator and rigger
(slinger/signaler). Lifting Plan and Procedure shall be developed, for both common
and critical lifting activities and in place before any work shall commence.
• Any injury / illness sustained whilst at work must be reported immediately and
treated by a trained first aider or HSE Officer. Incident escalation reporting
procedure shall be followed at all times.
Contract specifications supersedes all material described in this document.
DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-03-MMC-MST-EL-0026
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF SCS
Revision 00
Dubai, UAE SYSTEM
Issue Date 08-05-2023 Page 21 of 22
• HSE violation in any HSE procedures whether project or legal requirement will
result in black points being issued, as per Subcontractor Agreement and personnel
removed from site, if necessary.
• COVID-19 precautionary measures shall be communicated to the workforce and
all personnel under our control, including but not limited to social distancing,
wearing of face masks, regular hand washing and disinfecting of work areas,
reporting outbreaks or positive cases, as per ASC Emergency Escalation
procedure, etc.

7.2 HSE applicable laws and regulations

• Legal and Technical Guidelines to followed at all times, including but not limited to:
• Dubai Municipality (DM) – Code of Construction Safety Practice.
• Dubai Development Authority HSE regulations
• Administrative Decision NO. (68) Of 2010 Issue Implementing By-Law of the
Roads and Transport Authority.
• Ministry of Labour and Social Affairs Federal Law No. 8 (1980).
• Ministry of Labour and Social Affairs Ministerial Order No. 32 (1982)
• Federal Law No. 8 Ministerial Order No. 32 (1982) Regarding Determination of
Ways and Means to Protect Employees Against Occupational Hazards
• Ministerial Order No. 37/2 (1982) Regarding the Requirements Standards of
Medical Care to be Provided by the Employer for his Employees
• Ministerial Decision No. 557 of 2008, for the Executive Order of the Federal Law
No.37 of 2006 Concerning Private Security Companies.

7.0 Q.C. APPROVAL AND OTHER DOCUMENTARY REQUIREMENTS


All the quality control documentation related for this work to the sub-structure should
be approved before commencing the work. And as follows:

• Approved shop drawings.


• Approved Materials.
• Approved method statement for Testing and Commissioning.
• Approved Installation of devices.

8.0 RISK ASSESSMENT


Prior to the commencement of any activities the risk assessment of Structure Cable
system (refer to attachments) shall be reviewed jointly by the Commissioning team and

Contract specifications supersedes all material described in this document.


DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-03-MMC-MST-EL-0026
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF SCS
Revision 00
Dubai, UAE SYSTEM
Issue Date 08-05-2023 Page 22 of 22
the HSE team to ensure that all the risks are addressed and the required mitigation
measures are in place and remain fully implemented during operation.

9.0 ATTACHMENTS

• Checklist for Testing and Commissioning of Structure Cable system.


• Risk Assessment

Contract specifications supersedes all material described in this document.


DIFC CP-05
OFFICE
BUILDING MAIN
WORKS

INSPECTION CHECKLIST
Pre-commissioning Check List for Structured Cabling System
Area/Location: Date:

S/N ACTIVITIES / ITEMS TO BE INSPECTED Yes NO REM

Check service provider incoming cable entry duct, entry box, manholes ready
1 and completed

Check horizontal and vertical containment and conduits are completed as per
2 approved shop drawings

Check all cabinets such as ONU, IDF cabinet, Equipment’s and cabling are
3
done in MMR1 and MMR2
4 Check outlets and devices for any external damages.
Ensure that all the cabling work including copper cables, SMF, MMF cables
5
and fiber drop cables are completed.
6 Check the arrangement of components and wiring
Check equipment installation and cable termination as per the schematic and
7
schedule.
Labelling of cables and field devices as per the approved shop drawings and
8
labelling scheme.
All testing instruments are available in good working condition with valid
9
calibration certificate.
10 Availability of electrical power supply in ONU and IDF cabinets.
11 Proper & safe access shall be maintained

Comments (if any):

MMC/SUPPLIER CA ASC LACASA


Name
Designation
Signature/Date
DIFC CP-05
OFFICE
BUILDING MAIN
WORKS

INSPECTION CHECKLIST
Testing and Commissioning Check List for Structured Cabling System
Area/Location: Date:

S/N ACTIVITIES / ITEMS TO BE INSPECTED Yes NO REM

Check the material are free from defects, rust, and damages and are
1 appropriate for use.

Check the installations have been carried out as per manufacturer


2 recommendation

Ensure Bending radius of cat6Acable during draw in is greater than or equal


3
to 45mm and permanently installed is greater than or equal to 22.5mm.
Ensure minimum performance distance is maintained for UTP cables from
4
other electrical cables/sources to avoid the EMI effect.
Ensure all labels of the cabling scheme are as per project specification
5

6 All pairs of the UTP cables have been tested for continuity and position
Ensure safe clearance followed between data and power cables
7
Each terminated fiber link has been tested for continuity, position and loss.
8
All fiber connectors have been tested for continuity, position and loss
9
Ensure all cabinets and racks such as ONU, Mini ODF, IDFs, MDFs are
10
labelled and terminated neatly.
11 All the test results have been documented.
Comments(if any):
MMC/SUPPLIER CA ASC LACASA
Name
Designation
Signature/Date
MENASCO MECHANICAL CONTRACTING L.L.C.
( DIFC CP - 05 BUILDING LINK BRIDGE MAIN WORKS )
( RISK ASSESSMENT)
Date: 20-05-2023
Reference No CP05-03-MMC-MST-ELE-0026
Revision Rev 00
Main Activity: TESTING AND COMMISSIONING OF STRUCTURED CABLING SYSTEM
Location: DIFC CP - 05 BUILDING LINK BRIDGE MAIN WORKS

Severity

Minor or Serious Major Injury – Lost Single Fatality


Slight Injury – First Aid Multiple Fatalities
Injury Time > 3 Days Permanent Disability

Likelihood 1 2 3 4 5
Certain 5 5 10 15 20 25

Very Likely 4 4 8 12 16 20

Likely 3 3 6 9 12 15

May Happen 2 2 4 6 8 10

Unlikely 1 1 2 3 4 5

Trivial Risk - No further improvements necessary provided control measures are maintained
Adequately Controlled Risk - Risk is tolerable when control measures identified are implemented
Moderately controlled Risk - Further risk reduction measures should be considered
Intolerable Risk - Seek specialist advice/ support

Aravi Ashok Designation Proj, HSE Manager Date: 20th May 2023 Signature:

Salman Abu Assali Designation Project Manager Date: 20th May 2023 Signature:
MENASCO MECHANICAL CONTRACTING L.L.C. Page 2 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)

Likelihood

Likelihood
(Refer To Risk Mitigations

(T/A/M/I)

(T/A/M/I)
(The potential to cause harm (The harm which could

Outcome
(Sequence of

Outcome
Severity

Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)

     
 01 Access to work  Unfamiliarity to the site  Minor injury  3 2 6  The Ali & Sons Contracting Project HSE Plan 1 2 2  Compliance to
area  Unauthorized parking  Property / asset shall be strictly complied with by all M/s DM, COP- CHP
 Unauthorized access to site or damage MENASCO personnel and sub-contractors 2- 2.1, 2.3
taken shortcut under our control.  Y

 Manual handling  MENASCO shall provide ESSW, as Project Manager

 Over speeding appropriate to ensure safe execution of work

 Reversing without flag man, scope. Construction

warning alarm/ warning light  All work shall be carried out in accordance to Manager

 Slip, trip and fall all applicable UAE Laws and Regulations, DM

 Obstructed the walkway /traffic Regulations and MMC Project HSE Senior Project

route and emergency exit Management System. Engineer

 Untrained / incompetent  All personnel to undergo site HSE induction


before accessing the site for the first time Site Engineer
personnel
 Inadequate supervision  M/s MENASCO Site Engineer / Site
Supervisors shall check and ensure all safety HSE Officer
 Collision with other vehicles,
precautions are taken prior to commencement
pedestrians, and other fixed
of the work. Supervisors
objects
 Poor working posture while  MSRA to be communicated with the
operatives by the foreman or supervisor and Foreman
handling of materials
to ensure its purpose.
 Lack of P.P. E
 Permit to Work to be obtained prior to start the operators

activity
 All material shall be segregated accordingly to Driver & Helper

facilitate location of the items


MENASCO MECHANICAL CONTRACTING L.L.C. Page 3 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)

Likelihood

Likelihood
(Refer To Risk Mitigations

(T/A/M/I)

(T/A/M/I)
(The potential to cause harm (The harm which could

Outcome
(Sequence of

Outcome
Severity

Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)

 All new employees are to be trained on safe


work process and procedures at site.
 All employees are to be advised on avoiding
 . horse play in the work place.
 Local Language understood by the
Employees are to be used as mode of
communication during TBT, Training and
awareness.
 Load must be properly positioned and
adequately secured on vehicle
 Site speed limit and site traffic rules shall be
observed at all times
 Pedestrian movements to be taken care of
while entering the building
 Vehicles to be parked in designated area only
 Mandatory and required Task specific P.P.E
like hardhats with chin strap, safety glasses,
safety gloves, safety shoes, dust mask,
coveralls, etc. to be worn while on site and
during the task.
 Coved -19 precautionary measures shall strict
to be followed as required
MENASCO MECHANICAL CONTRACTING L.L.C. Page 4 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)

Likelihood

Likelihood
(Refer To Risk Mitigations

(T/A/M/I)

(T/A/M/I)
(The potential to cause harm (The harm which could

Outcome
(Sequence of

Outcome
Severity

Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)

 Method statement and risk assessment


02 Pre-  Untrained operatives.  Minor should be briefed to all operative prior to
Commissioning  Defect/ damage  Personal injury Work activities.
 Commissioning
Check for tool/equipment.  Property / assets  Every work area is barricaded and caution
Engineer
Structure  Lack / poor supervision damage sign to be displayed.
Cabling system  Incompetent/untrained  Training to be provided the excavation
 Project Manager
operatives team members to safe sequence of T & C
 Poor lightening structured cabling system
 Construction
 Trip, slip and fall  All measuring instruments are calibrated.
3 2 6 1 2 2 Manager
 Uninspected equipment  A visual inspection will be carried out prior
 Shortcut maneuvering to testing and commissioning in order that
 Senior Project
 Obstructed access danger cannot arise when the test is in
Engineer
 Poor Housekeeping place. The following are the minimum  Y
checks prior to commissioning:
 Site Engineer
 The Ensure all termination and splicing is
completed.
 HSE Officer
 Ensure proper cable, patch panel and
outlet labelling according to approved
 Supervisors
labelling scheme.
 Ensure power availability in ICT IDF
Foreman
cabinets and MDF cabinet.
 Ensure power outlets and isolators are
operators
installed; earthling is provided
And properly connected to cabinet or
racks.
MENASCO MECHANICAL CONTRACTING L.L.C. Page 5 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)

Likelihood

Likelihood
(Refer To Risk Mitigations

(T/A/M/I)

(T/A/M/I)
(The potential to cause harm (The harm which could

Outcome
(Sequence of

Outcome
Severity

Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)

 Ensure all electronic testing tools are


calibrated.
 Ensure that all work area is safe, clear and
all constraints on operation have been
identified and precautions are taken.
 Arrange all necessary personnel, plants
equipment and services as required for the
works and ensure adequate lighting,
temporary power where applicable and
access arrangement are in place.
 Implement Employment induction procedure
and Tool Box talks for the ongoing risk
   assessment and identification of hazards   
 Complete PPE to be used, safety shoe,
safety jacket, helmet, hand gloves, safety
glass, and Nose/Face mask and safety
harness. Suitable PPE as per activity
requirement
MENASCO MECHANICAL CONTRACTING L.L.C. Page 6 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)

Likelihood

Likelihood
(Refer To Risk Mitigations

(T/A/M/I)

(T/A/M/I)
(The potential to cause harm (The harm which could

Outcome
(Sequence of

Outcome
Severity

Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)

 03 Preparation of test  Obstruction of access in test  Minor Injuries  ASC Policies and Procedures shall be
instruments, location  Property / assets followed by Menasco team prior to start of
 Commissioning
Materials,  Uncertified or damaged test damage the Activity.
Engineer
Manpower, for equipment meters  MSRA to be communicated with the
 Environmental
testing and  Inexperience or inadequate 4 operatives by the foreman or supervisor. 4
Impact  Project Manager
Commissioning of training of workers involved 3 2 6  Pre-Task briefing or TBT to be carried out 1 2 2
Structural Cabling  Poor illumination by foreman or supervisor prior to start of
system  Construction
 Open or damaged cable of work communicating hazard and control
Manager
the test meter measures to its workers.
 Poor housekeeping  Menasco to comply with Local Authority
 Senior Project
 Untrained operatives. regulations and HSE requirements.
Engineer
 Defect/ damage  Ensure that all the pre-commissioning
tool/equipment. checks are carried out successfully and  Y
 Site Engineer
 Lack / poor supervision commissioning of Structural Cabling

 Incompetent/untrained system work.


 HSE Officer
operatives for T & C  Commissioning Engineer to supervise and

 Poor lightening monitor the commissioning activity.


 Supervisors
 Trip, slip and fall  All access to test area to be cleared of all

 Uninspected equipment obstruction and accessible to all.


Foreman
 Shortcut maneuvering  The work area shall be inspected for
completion and safe to start the testing and
Operators
commissioning work Ensure the LAN cable
(CAT6A) is connected between the Access
T & C Engrs
Control systems to the Network Switch &
Connect the Workstation PC to the LAN.

MENASCO MECHANICAL CONTRACTING L.L.C. Page 7 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)

Likelihood

Likelihood
(Refer To Risk Mitigations

(T/A/M/I)

(T/A/M/I)
(The potential to cause harm (The harm which could

Outcome
(Sequence of

Outcome
Severity

Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)

 Testing and  Lack of /ineffective Personal  MSRA/TBT to be communicated and


 04 Commissioning of communication during the Injuries, conducted to all workers prior to start of
Structural Cabling Property
test procedure activity.
system  Project Manager
 Lack of Supervision and Damage,  Permit to be obtained prior to start of
1. Test lead Monitoring ill-health, testing and commissioning of Structural
 Construction
2. Certification  Incompetent crew Cabling system.
Manager
 Inadequate access  All procedure must be followed all through.
testing
 Inadequate light  Experienced and trained personnel to be
3. Fiber inspection  Senior Project
 Lack of communication used for testing and commissioning of
and cleaning Engineer
 Tools striking due to Structural Cabling system
4. Loss Length congested work atmosphere.  Commissioning Engineer to supervise and
 Site Engineer
5. Fiber Plant  Heat stress due hot climate monitor the commissioning activity.
 3 2 6  1 2 2 Y
or doing hot work.  LOTO Permit to be obtained prior to start
6. UTP Cabling test  HSE Officer
 Inability to escape. of testing and commissioning of Gate
7. Troubleshooting
 Lack of PPE Barrier System.
 Supervisors
 LOTO Procedure must be followed all
through.
Foreman
 Check & ensure that the correct Fiber/Cat6
cables are used. Physically check and
Operators
verify the manufacturer’s markings.
Confirm that the cables used for voice
T & C Engrs
applications are Fiber cables.
 Pre-installation cable check, check and
verify the cable for cuts or damages before
MENASCO MECHANICAL CONTRACTING L.L.C. Page 8 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)

Likelihood

Likelihood
(Refer To Risk Mitigations

(T/A/M/I)

(T/A/M/I)
(The potential to cause harm (The harm which could

Outcome
(Sequence of

Outcome
Severity

Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)

  Check for cable pair twists, physically


check and verify that the cable pairs
terminated in the CAT6 / RJ45 Patch Panel
do not twist into each other.
 Check for bend radius, open the
compartments. Check and verify that the
stipulated bend radius is not less than 4
times the cable diameter. Inspect the fiber
end-face (or port) using a video
microscope to identify contamination.
 If only dust needs to be removed, use a
mechanical dry cleaner.

    If you see grease or oil from skin contact,   


use the following “wet “procedure:
 Dab the contaminated end-face with a
solvent-dampened wipe (or swab).
 Swipe the fiber end-face perpendicularly
one time against a dry wipe.
 Re-inspect the fiber end-face (or port) with
the video microscope to ensure that all the
debris has been removed.
 If contamination is still observed, repeat
the cleaning process until all contamination
is removed.
MENASCO MECHANICAL CONTRACTING L.L.C. Page 9 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)

Likelihood

Likelihood
(Refer To Risk Mitigations

(T/A/M/I)

(T/A/M/I)
(The potential to cause harm (The harm which could

Outcome
(Sequence of

Outcome
Severity

Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)

  Stress Relief, randomly check individual


cables for cable stress / pulling tensions,
as excessive stress on the cable may
cause micro bending
 Adjust the area of view and focus as per
the requirement/Approved Drawing
 Ensure to open the STRUCTURAL
CABLING SYSTEM Management software
in PC/Server and start communicating the
NVR through the Client Workstation.
 Connect using the default IP address,
initialize the NVR and set Password.
    Proper signage’s and access control to be  
put in place during testing period.
 ABC Policies and Procedures shall be
followed by Menasco team prior to start of
the Activity.
 Menasco to comply with Local Authority
regulations and HSE requirements.
 Proper signage’s and access control to be
put in place during testing period.
 ASC Policies and Procedures shall be
followed by Menasco team prior to start of
the Activity.
 Use Appropriate PPE’s
MENASCO MECHANICAL CONTRACTING L.L.C. Page 10 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)

Likelihood

Likelihood
(Refer To Risk Mitigations

(T/A/M/I)

(T/A/M/I)
(The potential to cause harm (The harm which could

Outcome
(Sequence of

Outcome
Severity

Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)

 Used of temporary  Electrocution  Minor Injury  The Ali & Sons Contracting Project HSE
 05 power supply and  Slip / Trip and falls  Major Injury Plan shall be strictly complied with by all
Extension leads.  Untrained operative.  Property  All works shall be regularly monitored and
 Use of damage extension damaged supervised by M/s MENASCO site team to  Project Manager
leads. ensure full compliance
 Use of damaged  MENASCO shall provide adequate  Construction
equipment's resources, as appropriate to ensure safe Manager
 Lack of PPE. execution of work scope.

 Work In wet areas with  All work shall be carried out in accordance  Senior Project
damaged cable lead or to all applicable UAE Laws and Engineer
equipment Regulations, DM Regulations and MMC
Project HSE Management System. Obtain  Site Engineer
 3 3 9 the required work permit and clearance  
1 3 3 Y
prior to start the task  HSE Officer
 SOS / MSRA should communicate to
workers prior to commencement of work.  Supervisors
 Pre-Task briefing or TBT to be carried out
by foreman or supervisor prior to start of Foreman
work communicating hazard and control
measures to its workers Operators
 Only competent person can carried out the
electrical task at site T & C Engrs
 Inspected and color-coded extension
leads to be used on site.
 All electrical tools and equipment's free
from defects and fit to safe use
MENASCO MECHANICAL CONTRACTING L.L.C. Page 11 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)

Likelihood

Likelihood
(Refer To Risk Mitigations

(T/A/M/I)

(T/A/M/I)
(The potential to cause harm (The harm which could

Outcome
(Sequence of

Outcome
Severity

Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)

    Damage extension leads must be remove on


the work area immediately and returned to store
for replacement.
Power supply must be off if not in use
Electrical power board to be fitted with
RCD/ELCB of 30mili ampere.
Electrical Distribution board are to be inspected
periodically and labelled or tagged.
Do not overload the electrical Distribution
board.
CABLES are to be routed above head or below
ground level
      
CABLES are not to be routed along or across
wet area
Ali & Sons Policies and Procedures shall be
followed by Menisci team prior to start of the
Activity.
Menasco to comply with Local Authority
regulations, DDA Code of practices and HSE
requirements.
Complete PPE to be used, safety shoe, safety
jacket, helmet, hand gloves, safety glass,
Nose/Face mask and safety harness. Suitable
PPE as per activity requirement.
MENASCO MECHANICAL CONTRACTING L.L.C. Page 12 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)

Likelihood

Likelihood
(Refer To Risk Mitigations

(T/A/M/I)

(T/A/M/I)
(The potential to cause harm (The harm which could

Outcome
(Sequence of

Outcome
Severity

Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)

     Ali & Sons HSE Policies and Procedures DM - Code of


 06 Using of hand  Using defective power tools.  Minor injury shall be followed by Menasco team prior to construction
tools and portable
 Used of un-inspected power  Personal injury start of the Activity. Safety
power 
tools.  Property/asset Permit to Work to be obtained prior to activity. Practices
 Untrained Workers using damage  Menasco to comply with Local Authority CHAPTER 14
• Portable POE
Power tools regulations and DDA HSE requirements. HandandPowe
injector.
 Failure to use correct PPE  MSRA to be communicated with the Operated Tools
• Toolbox with
 Improper handling/storage operatives by the foreman or supervisor. 182
Hand Tools
 Misuse of tools  Hot Work Permit to be obtained prior to start
• Multi tester
 Excess pressure on tools of cutting or grinding activities (If applicable).  Project Manager
• Multi-meter
 Electric Shock  Operator must be trained for Safe Handling of
• Walkie-talkie
 Flying fragments Power Tools. Construction
• Commissioning  3 3 9  
1 3 3  Y
 Poor/lack of supervision  Use power tools with both hands never use Manager
laptop
 Tripping single hand.
 Maintain cable management and use cable Senior Project
stand. Engineer

 Never modify the power tools maintenance


 Repairing must be done only by a competent Site Engineer

person.
 Do not use any damage power tool and worn HSE Officer

out cable wires.


 Grinding/Cutting handle to be available Supervisors

always prior to use at site Foreman


T & C Engrs
MENASCO MECHANICAL CONTRACTING L.L.C. Page 13 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)

Likelihood

Likelihood
(Refer To Risk Mitigations

(T/A/M/I)

(T/A/M/I)
(The potential to cause harm (The harm which could

Outcome
(Sequence of

Outcome
Severity

Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)

     Grinding disc should only be used for grinding


machine
 While cutting disc to be used on Cutting
machine only.
 Grinding/Cutting Machine Disc RPM should
be greater than or equal to Grinding/Cutting
Machine
 All power tools issued from Store must be
pre-Inspected and in good conditions before
issuing to Workers by Storekeepers
 All power tools issued from Store must be pre-
Inspected and in good conditions before
   issuing to Workers by Storekeepers.     
 All damaged and unsafe to use Power tools to
be tagged out and returned to central store for
repair for fit to use purpose.
 Follow manufacturer instruction. All power
tools to be used at site must be of 110 volts
Proper insulation of terminals and cables, Use
of standard fitting.
 All electrical equipment’s / tools to be
protected from water.
 Daily inspection of equipment’s, tools, cables
and fittings
Disconnect the power cable while not in use

.
MENASCO MECHANICAL CONTRACTING L.L.C. Page 14 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)

Likelihood

Likelihood
(Refer To Risk Mitigations

(T/A/M/I)

(T/A/M/I)
(The potential to cause harm (The harm which could

Outcome
(Sequence of

Outcome
Severity

Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)

    Ensure that work area is free (as is



practicable) from trailing cables, tools,

materials debris and spills. Inspected

power tools to be used on site.

 Do not overload the Electrical Distribution

Board (EDB).

 All electrical tools to be grounded or double

insulated.

 All electrical tools above 110 volts use on site


 
are to be connected through ELCB / RCD   

  installed Electrical distribution board.

 All electrical tools and equipment’s to be

checked by competent electrical on regular

intervals without fail

 Complete PPE to be used: safety shoe, safety

jacket, helmet, hand gloves, safety glass,

earplug and Face/Nose mask


MENASCO MECHANICAL CONTRACTING L.L.C. Page 15 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)

Likelihood

Likelihood
(Refer To Risk Mitigations

(T/A/M/I)

(T/A/M/I)
(The potential to cause harm (The harm which could

Outcome
(Sequence of

Outcome
Severity

Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)

 Work at Height - Falling of men and materials from Major Injuries The Ali & Sons Contracting Project HSE Plan
08 Using Scaffold, A- shall be strictly complied with by all DM – Compliance
height Minor Injury CHAPTER 8
Type ladder / All works shall be regularly monitored and
Scaffolding
Presence of overhead services Fatality
Podium Ladders supervised by M/s MENASCO site team Safety
Incompetent workers  Property damaged to ensure full compliance 101CHAPTER
MENASCO shall provide adequate resources, 4Personal
Lack of supervision
Protective
as appropriate to ensure safe execution of work
Improper use of work platform Equipment
scope. All work shall be carried out in
44Project
Unauthorized access to the accordance to all applicable UAE Laws and Manager
Regulations, DM Regulations and MMC Project
equipment
HSE Management System. Construction
Untrained operator Manager
MSRA to be communicated with the operatives
Unfavourableclimatic conditions  3 3 9 by the foreman or supervisor.  
1 3 3 Y
Permit For work at height on scaffolding to be Senior Project
Unbalancing of work platform
available and approved from concerned team prior Engineer
Caught-in between
to start of work. Pre-Task briefing or TBT to be
Working under direct sun light carried out by foreman or supervisor prior to start Site Engineer

of work communicating hazard and control


Dust
measures to its workers. HSE Officer
Noise
Only Competent scaffolder which is 3rd party
Slippery surface due to leak of oil certified to erect mobile Aluminum scaffolding and Supervisors

platform.

Foreman
 Operative Working at height must be trained for
Safe Work at height.
T & C Engrs
MENASCO MECHANICAL CONTRACTING L.L.C. Page 16 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)

Likelihood

Likelihood
(Refer To Risk Mitigations

(T/A/M/I)

(T/A/M/I)
(The potential to cause harm (The harm which could

Outcome
(Sequence of

Outcome
Severity

Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)

    Scaffolders must undergo training for Working


at Height prior erection and dismantling of
scaffolding.
Permit For work at height on scaffolding to be
available and approved from concerned team prior
to start of work.
Proper lightning of work areas to be put in place
by supervisor and foreman before start of activity
Simultaneous operation or activities to be
avoided during Work at height activity.
Standard and approved materials to be used.
Mobile Aluminum scaffolding must be inspected by

   the scaffolding inspector who is 3rd party certified


   
3 points of contact to be maintained while using
Step/A-Type ladders.
Buddy system to be in place when using Step
ladders/A-type ladders.
Power tools are not to be used on Step/A-type
ladders instead Podium ladders or scaffolding to
be used. No workers should stand on the last
rung of the ladder
The A-Type ladder lock to be engaged prior to
start of work.
A-type/Step ladders not to be used at floor
openings or edges.
Workers should not overreach when using A-
type/Step Ladders.
MENASCO MECHANICAL CONTRACTING L.L.C. Page 17 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)

Likelihood

Likelihood
(Refer To Risk Mitigations

(T/A/M/I)

(T/A/M/I)
(The potential to cause harm (The harm which could

Outcome
(Sequence of

Outcome
Severity

Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)

 Mental Stress  Psychological  Night work permit to be obtained prior to start


09 Night Work
 Psychological Stress trauma of work
 Project Manager
 Poor Coordination  Sleeplessness  Workers to be provided rest period or off days

 Lack of Supervision and  Restlessness after extended night work.


 Construction
Monitoring  Minor Injury  Welfare facilities to be provided for Night work Manager

 Low or high illumination  Property shift


 Senior Project
 Poor ventilation Damage  First Aid facility and first aiders to be provided
Engineer
 Sleeping on the job for night work
 Site Engineer
 Lack of rest  Emergency Vehicle and contact numbers to

be readily available at point of work Y


3 3 9 1 3 3  HSE Officer
 Proper Ventilation to be provided during

humid period at night, with rehydration and  Supervisors

observing job rotation


Foreman
 ABC Policies and Procedures shall be
Operators
followed by Menasco team prior to start of the

Activity.
 T & C Engrs
 Menasco to comply with Local Authority 
 ERT
regulations and HSE requirements

 Proper supervision and Monitoring to be

Maintained for all Night Work.


MENASCO MECHANICAL CONTRACTING L.L.C. Page 18 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)

Likelihood

Likelihood
(Refer To Risk Mitigations

(T/A/M/I)

(T/A/M/I)
(The potential to cause harm (The harm which could

Outcome
(Sequence of

Outcome
Severity

Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)

  General  Obstructed emergency route  Minor Injury


 09 Emergency  Lack of emergency rescue team  First Aid case MSRA should communicate to workers prior to
Situations  Lack of emergency rescue kit  Medical treatment commencement of work.

 Lack of training to Emergency case Operatives must be trained of safe and proper
responder  Fines use of hand tools.  Project Manager
 Incompetent emergency  Property damage All tools provided must be assessed to ensure
that they are fit for purpose, they fit for the  Construction
responders  Lack of training to Manager
 Improper or lack of illumination Emergency responder environment in which they are to be used and they

 Improper or lack of ventilation  Incompetent are in good condition.  Senior Project


.Sharp tools, which cut steel, can cut flesh Engineer
 emergency responders
without trouble. Hammers, which can drive nails,
 Improper or lack of  Site Engineer
can squash fingers too. Open-bladed knives,
illumination  3 2 6  
1 2 2  Y
screwdrivers, and other sharp tools are to be  HSE Officer
 Improper or lack of
carried and used so as not to cause injury to the
ventilation  Supervisors
user or others.
Non-ferrous (spark free) tools are to be used in  Foreman
flammable atmospheres.
Insulated tools must be used where there is a  Operators
possibility of live electrical work
Visual checks must be completed by operatives  ERT TEAM
on tools prior to their use. They rely on them, as
skilled trade’s persons, to assist them in this by
reporting immediately if something is not suitable
or is broken.
MENASCO MECHANICAL CONTRACTING L.L.C. Page 19 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)

Likelihood

Likelihood
(Refer To Risk Mitigations

(T/A/M/I)

(T/A/M/I)
(The potential to cause harm (The harm which could

Outcome
(Sequence of

Outcome
Severity

Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)

          
 Proper ventilation to be provided
 Proper and safe access to be provided in work
areas.
 Ali & Sons HSE Policies and Procedures shall be
followed by Menasco team prior to start of the
Activity.
 Menasco to comply with Local Authority
regulations and HSE requirements  

 Emergency response and contact details to be


made available and known to workers at site.
 Emergency vehicle to be available for emergency
rescue to nearest hospital.

 DIFC - Site Nurse Contact:


 No # 0568212770

Note: If any new scenarios emerge that are not covered by this risk assessment, site management should be contacted immediately, and the task should not be completed until a specific risk
assessment has been completed, issued, and understood.

You might also like